J.Y.F. (BUDA), District 01, Texas
A field is the Railroad Commission's unit of geology and of regulation. Its spacing rule is what decides how many wells an acreage can hold.
Our estimate: volumes the operator filed with the Commission, valued at the EIA first-purchase price for that month. It is not a payment anyone received, and it is not a royalty. It sums the 5 leases in this field that have a page here — 83% of the register's 6 — so it understates the field.
Production, 2025
The Railroad Commission's Oil and Gas Annual Report for 2025, its most recent. These are the state's figures for the whole field, not ours.
| Wells | In the field | Producing | Produced in 2025 | Also produced | Cumulative |
|---|---|---|---|---|---|
| Oil | 2 | 2 | 778 bbl | 12 mcfcasinghead | 651,096 bblsince discovery |
The discovery well's oil measured 31.5° API gravity, perforated at 7,707 ft.
Spacing rule
What the Commission requires of a well on this field.
| Wells | Rule | Effective | From the lease line | Between wells | Acres per unit | Max diagonal |
|---|---|---|---|---|---|---|
| Oil | B | 1984-04-09 | 467 ft | 1,200 ft | 160 | 4,500 ft |
| Oil | O | 1984-04-09 | 467 ft | 1,200 ft | 80 | 3,250 ft |
Commission remarks: OP 80 ACRES W/DIAG. 3250'
County
Leases in this field
Every lease here files this field's number with the Commission and has a page on this site.
| Lease | Operator | Value |
|---|---|---|
| GERACI | BODDEN PRODUCTION | $7.2 M |
| CHANDLER, FRED H. | MARATHON OIL COMPANY | $2.6 M |
| THOMS-WILSON | PEDECO, INC. | $262 k |
| GERACI II | BODDEN PRODUCTION | $203 k |
| RUNK STAYTON | PEDECO, INC. | $28 k |
Field number 45239500, from the Railroad Commission's field register. The register's own index resolves 6 leases and 15 wells to this field by name, over every lease in Texas rather than only those with a page here. It resolves a lease by NAME and refuses an ambiguous one, so it counts nothing for a field that shares its name with another — which is why the lease count above comes from the field number instead.