AMG CHATO 25 C

Operated by LEWIS PETRO PROPERTIES, INC. (P-5 499978) in the SUN T S H (OLMOS) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 233688District 01Field 872515002 tax incentive programmesCondensateGasSaveExport
Value, all time
$2.0 M
Apr 2007 – May 2026
Value, last 12 filed months
$9 k
at the published price for each month
Months reported
230
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 326 leases and 350 wells, and the rule below applies to all of them.

Discovered
1983-04-30
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2013-01-15.

The Commission's schedule remark for this field reads: ALLOCATION FORMULA OF 5% PER WELL 95% DEL. IF CAPACITY RESCINDED

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112008-05-12181912
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition3,473 bbl$272,268
GasProduction328,315 Mcf$1,747,835
Total$2,020,104

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 28.1791, -99.2465. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

28.17908, -99.24649 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
7,900 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,900 ft.

Completions filed
Apr 2007
1 of 1 wells

1 well

42-28332019387,900 ftApr 2007

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (230)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

230 months

May 202605106.413.05$15
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 2026023859.138.00$1,904
Dec 2025039556.664.41$1,743
Nov 2025017058.593.93$667
Oct 2025927859.383.30$1,453
Sep 2025029262.743.08$898
Aug 2025029963.933.01$901
Jul 2025029366.743.32$971
Jun 2025026366.483.13$823
May 2025022460.553.23$724
Apr 2025713362.363.54$908
Mar 2025016667.704.27$709
Feb 202504670.884.34$200
Jan 202504574.324.28$193
Dec 202402868.993.12$87
Nov 2024010769.052.20$235
Oct 2024918771.372.28$1,069
Sep 2024014569.612.36$343
Aug 202407275.632.06$149
Jul 2024015579.932.15$333
Jun 2024015978.082.63$419
May 2024024678.812.20$541
Apr 20242254484.451.66$2,761
Mar 2024075080.301.55$1,159
Feb 2024026476.091.78$471
Jan 20243051473.023.30$3,886
Dec 2023092371.262.61$2,410
Nov 2023096877.892.81$2,718
Oct 2023081585.443.09$2,516
Sep 2023020589.042.74$561
Aug 2023013380.522.67$355
Jul 2023020674.852.64$544
Jun 2023023568.962.26$531
May 2023024170.622.23$537
Apr 2023034678.122.24$774
Mar 2023057972.852.39$1,386
Feb 2023061775.112.47$1,521
Jan 2023055676.533.39$1,884
Dec 2022061376.415.73$3,512
Nov 2022088085.005.65$4,969
Oct 2022062387.185.86$3,653
Sep 2022031384.888.16$2,555
Aug 2022063594.529.13$5,796
Jul 202201,058101.587.54$7,980
Jun 202201,098115.097.98$8,759
May 202201,199109.378.43$10,111
Apr 202201,252104.226.84$8,561
Mar 202201,384108.885.08$7,026
Feb 202201,00991.054.86$4,903
Jan 202201,03881.844.54$4,710
Dec 2021099571.323.90$3,880
Nov 202101,12277.435.24$5,876
Oct 202101,56379.795.71$8,931
Sep 202101,39669.865.35$7,470
Aug 2021069666.024.22$2,938
Jul 2021091670.783.98$3,648
Jun 202101,13269.493.38$3,827
May 2021064063.483.02$1,931
Apr 2021079960.362.76$2,204
Mar 202101,22461.302.72$3,326
Feb 2021033557.805.55$1,859
Jan 2021016750.412.81$469
Dec 2020031544.642.68$843
Nov 202001,05638.772.71$2,858
Oct 2020032436.972.48$803
Sep 202051,18237.091.99$2,539
Aug 2020012939.982.39$308
Jul 2020012738.371.83$232
Jun 2020020634.901.69$348
May 2020028316.921.81$514
Apr 2020046814.751.80$844
Mar 2020057230.341.86$1,062
Feb 2020065549.881.98$1,297
Jan 2020097757.252.09$2,047
Dec 201901,04259.012.30$2,401
Nov 201901,14255.302.75$3,141
Oct 201901,36753.472.42$3,306
Sep 2019083055.052.66$2,206
Aug 2019036653.112.30$843
Jul 2019068756.272.46$1,690
Jun 20192074452.782.49$2,909
May 2019051758.482.74$1,417
Apr 201901,16862.632.75$3,213
Mar 20191055756.803.06$2,274
Feb 2019029950.852.79$835
Jan 2019010046.033.23$323
Dec 2018024546.594.19$1,025
Nov 2018220752.934.24$983
Oct 2018129961.443.40$1,077
Sep 2018042059.543.11$1,305
Aug 2018058559.403.07$1,794
Jul 2018053265.142.93$1,560
Jun 2018028860.183.08$886
May 2018038465.382.90$1,114
Apr 2018072963.842.90$2,115
Mar 201821,11361.222.79$3,224
Feb 201811,49461.782.77$4,194
Jan 2018142262.874.01$1,755
Dec 2017088357.272.92$2,580
Nov 201711,09955.423.12$3,483
Oct 2017077749.292.98$2,318
Sep 2017097747.523.09$3,016
Aug 201701,00545.373.00$3,019
Jul 2017069243.873.09$2,136
Jun 201701,25542.493.09$3,875
May 2017189645.373.26$2,969
Apr 201711,12247.933.21$3,651
Mar 201701,67246.772.98$4,989
Feb 201762,32350.452.95$7,162
Jan 201711,62149.413.42$5,591
Dec 2016159248.763.72$2,253
Nov 2016252042.492.64$1,460
Oct 2016146546.193.09$1,483
Sep 2016182341.553.10$2,593
Aug 2016060941.442.92$1,781
Jul 201611,25041.622.92$3,697
Jun 2016183845.352.69$2,296
May 201621,90842.521.99$3,884
Apr 2016189636.561.99$1,821
Mar 2016124533.011.79$473
Feb 2016020226.472.06$417
Jan 2016522327.352.36$664
Dec 2015121932.362.00$471
Nov 2015121938.792.17$513
Oct 2015022043.552.43$534
Sep 2015119142.992.76$570
Aug 2015016740.162.87$480
Jul 20151021148.152.95$1,103
Jun 2015117256.152.88$552
May 2015079855.212.96$2,358
Apr 201502,04149.822.71$5,524
Mar 201502,20442.892.93$6,468
Feb 201551,91244.662.98$5,914
Jan 2015643443.433.10$1,606
Dec 2014837554.693.59$1,784
Nov 2014035270.464.25$1,497
Oct 2014550978.303.90$2,377
Sep 2014063386.164.05$2,561
Aug 2014111,05689.394.04$5,244
Jul 2014099796.564.18$4,167
Jun 2014189598.164.74$4,338
May 201401,09494.734.73$5,171
Apr 2014111,08995.944.81$6,292
Mar 201481,17195.895.06$6,689
Feb 2014121,00797.406.19$7,404
Jan 2014141,17690.404.86$6,982
Dec 201311,24691.824.35$5,518
Nov 201301,31088.853.74$4,897
Oct 201301,31297.423.78$4,959
Sep 201301,336104.113.72$4,967
Aug 201301,332104.253.52$4,692
Jul 2013171,336102.523.72$6,710
Jun 201301,21394.403.93$4,771
May 201301,24794.834.15$5,174
Apr 201311,19493.964.28$5,207
Mar 2013191,24493.623.91$6,646
Feb 201311,21591.233.42$4,246
Jan 2013141,35291.603.42$5,906
Dec 201201,31786.773.42$4,504
Nov 201211,38586.953.62$5,108
Oct 2012121,46489.383.40$6,050
Sep 2012171,42394.672.92$5,762
Aug 201201,49792.662.91$4,354
Jul 201201,45785.133.02$4,401
Jun 2012161,39379.822.52$4,786
May 201201,47491.612.49$3,668
Apr 2012701,481101.652.00$10,073
Mar 201201,540105.052.22$3,422
Feb 2012101,498101.102.57$4,861
Jan 2012411,61098.092.73$8,424
Dec 201101,57296.873.24$5,093
Nov 2011391,51395.723.31$8,743
Oct 201101,55184.983.65$5,659
Sep 201101,50683.623.99$6,003
Aug 2011411,63783.404.15$10,212
Jul 201101,48794.144.52$6,717
Jun 201101,63992.904.64$7,605
May 201101,68998.134.40$7,440
Apr 201101,715105.964.33$7,432
Mar 201101,81496.364.06$7,360
Feb 2011321,65285.644.18$9,646
Jan 201101,88186.504.59$8,632
Dec 201001,85185.734.35$8,048
Nov 2010078780.843.80$2,987
Oct 201001,93978.103.51$6,804
Sep 2010331,84672.633.98$9,743
Aug 201002,05473.684.42$9,077
Jul 201001,98372.554.74$9,392
Jun 2010412,12670.364.91$13,324
May 201002,20571.124.24$9,339
Apr 201002,15981.694.12$8,901
Mar 201002,19978.394.39$9,651
Feb 2010392,00673.585.44$13,787
Jan 201002,32874.365.96$13,884
Dec 200902,34171.445.48$12,837
Nov 200902,29374.593.75$8,602
Oct 2009232,43972.544.11$11,693
Sep 200902,42665.543.06$7,435
Aug 200902,54267.423.22$8,181
Jul 2009372,60661.133.46$11,290
Jun 200902,58966.163.90$10,084
May 2009392,78654.743.93$13,072
Apr 200902,78946.773.59$10,006
Mar 2009382,93542.144.06$13,514
Feb 200902,80732.814.63$13,005
Jan 2009353,17335.865.37$18,297
Dec 2008343,18837.105.98$20,317
Nov 2008323,08755.496.86$22,954
Oct 200803,28775.246.92$22,753
Sep 2008363,353101.767.88$30,075
Aug 2008363,660114.228.48$35,160
Jul 2008353,906131.0811.39$49,075
Jun 2008364,055131.3313.03$57,575
May 2008334,402123.1711.57$55,015
Apr 20081704,652110.3110.45$67,389
Mar 20081124,700101.909.66$56,834
Feb 20081094,34692.538.77$48,203
Jan 20081045,48390.388.21$54,392
Dec 20071055,61388.337.30$50,261
Nov 20071585,82491.677.29$56,951
Oct 20071576,48882.856.92$57,917
Sep 20071377,17575.846.24$55,192
Aug 20073579,06569.066.39$82,561
Jul 200739411,48370.906.39$101,287
Jun 200718712,70662.007.55$107,505
May 200738414,16058.747.85$133,659
Apr 200702,14659.617.81$16,750

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                    5 Mcf  × $  3.05 =        $15

────────────────────────────────────────────────────
Month total                                      $15

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 01/G/233688 is the state's own key, not one this site invented.