GATES RANCH "A"

Operated by LEWIS PETRO PROPERTIES, INC. (P-5 499978) in the CATARINA, SW. (SAN MIGUEL-GAS) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 88657District 01Field 16340900CondensateGasSaveExport
Value, all time
$26 k
Jan 1993 – Feb 2006
Value, last 12 filed months
$6 k
at the published price for each month
Months reported
158
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 120 leases and 120 wells, and the rule below applies to all of them.

Discovered
1978-05-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,200 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 80 acres. The field rule took effect on 1979-05-21.

The Commission's schedule remark for this field reads: KERNS O&G, INC. EFFECTIVE APRIL 1, 1997.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition81 bbl$2,220
GasProduction6,855 Mcf$23,639
Total$25,860

1,937 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 28.2066, -99.8447. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

28.20660, -99.84469 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
5,572 ft
1 wells filed one
Completion to plug
25.8 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 5,572 ft.

Completions filed
May 1980
1 of 1 wells
Plug dates filed
Feb 2006
1 of 1 wells

Last completion to plug: a median of 25.8 years across the 1 well that filed both dates, with the middle half between 25.8 years and 25.8 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-1273202620745,572 ftMay 1980Feb 2006Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (158)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

158 months

Feb 200604357.597.75$333
Jan 200605860.598.93$518
Dec 200504554.9413.42$604
Nov 20050054.6910.59$0
Oct 200506958.3413.80$952
Sep 200504761.4512.08$568
Aug 200506861.519.80$666
Jul 200507455.697.84$580
Jun 200505952.337.38$435
May 200506645.226.65$439
Apr 200507549.207.36$552
Mar 200506750.377.15$479
Feb 200564545.226.31$555
Jan 200505643.166.32$354
Dec 200403739.866.75$250
Nov 200405945.286.33$373
Oct 200406749.706.52$437
Sep 200404743.245.28$248
Aug 200405742.375.55$316
Jul 200405338.286.08$322
Jun 200405336.106.43$341
May 200407437.486.49$481
Apr 200406934.475.86$404
Mar 200408534.365.53$470
Feb 200408632.455.51$474
Jan 200408532.036.30$535
Dec 200346130.266.30$505
Nov 200336928.804.60$403
Oct 200357128.174.76$479
Sep 200358426.314.75$531
Aug 2003157929.765.13$852
Jul 2003310429.415.17$626
Jun 200359628.565.98$717
May 200329726.595.97$633
Apr 200384626.675.41$462
Mar 200324031.146.10$306
Feb 200343333.487.93$395
Jan 200333730.315.58$297
Dec 200203926.914.85$189
Nov 200204024.664.14$165
Oct 200203626.464.23$152
Sep 200203727.443.64$135
Aug 200204325.963.16$136
Jul 200204124.583.06$126
Jun 200203823.733.34$127
May 200203724.663.58$133
Apr 200204123.653.51$144
Mar 200205022.003.10$155
Feb 200205718.222.38$135
Jan 200206317.172.38$150
Dec 200105316.932.36$125
Nov 200105118.072.41$123
Oct 200102519.782.53$63
Sep 200102824.262.25$63
Aug 200103024.873.05$92
Jul 200102723.933.20$86
Jun 200102524.563.82$96
May 200102925.524.31$125
Apr 200102824.685.34$149
Mar 200103024.545.38$161
Feb 200102727.755.77$156
Jan 200102827.478.40$235
Dec 200002726.889.12$246
Nov 200002732.215.66$153
Oct 200001931.235.15$98
Sep 200001931.875.19$99
Aug 200003429.644.54$154
Jul 200002628.534.09$106
Jun 200002829.304.40$123
May 200002427.263.68$88
Apr 200002924.513.12$90
Mar 200003128.422.86$89
Feb 200002927.622.73$79
Jan 200003425.272.48$84
Dec 199904024.282.42$97
Nov 199904523.192.43$110
Oct 199903920.982.80$109
Sep 199904521.752.62$118
Aug 199903619.262.88$104
Jul 199903717.892.37$88
Jun 199903515.942.36$83
May 199903915.792.32$91
Apr 199903815.102.21$84
Mar 199904212.471.84$77
Feb 19990319.981.82$56
Jan 199904210.381.90$80
Dec 19980409.201.77$71
Nov 199803610.892.19$79
Oct 199803712.421.97$73
Sep 199834112.592.08$123
Aug 199803611.301.91$69
Jul 199804411.742.24$98
Jun 199804411.242.24$98
May 199804812.622.21$106
Apr 199805013.042.51$125
Mar 199804312.802.31$99
Feb 199803713.952.30$85
Jan 199802914.702.15$62
Dec 199703016.322.41$72
Nov 199702618.193.09$80
Oct 199702519.253.15$79
Sep 199702617.742.95$77
Aug 199702617.862.55$66
Jul 199703617.582.25$81
Jun 199702817.242.26$63
May 199703318.972.31$76
Apr 199703417.882.08$71
Mar 199703718.951.94$72
Feb 199703320.492.21$73
Jan 199703923.483.54$138
Dec 199603723.32$0
Nov 199603621.97$0
Oct 199604423.31$0
Sep 199603622.22$0
Aug 199604720.26$0
Jul 199604719.55$0
Jun 199604318.73$0
May 199604619.43$0
Apr 199605021.51$0
Mar 199603119.38$0
Feb 199603016.98$0
Jan 199603117.07$0
Dec 199502617.19$0
Nov 199502516.00$0
Oct 199502815.43$0
Sep 199503116.18$0
Aug 199503915.92$0
Jul 199504815.24$0
Jun 199505316.41$0
May 199505017.56$0
Apr 199503717.73$0
Mar 199514816.44$16
Feb 199505716.58$0
Jan 199504615.92$0
Dec 199424715.03$30
Nov 199405915.90$0
Oct 199405115.58$0
Sep 199415015.29$15
Aug 199404516.13$0
Jul 199424317.56$35
Jun 199423317.09$34
May 199403215.88$0
Apr 199423514.14$28
Mar 199403212.46$0
Feb 199413212.50$13
Jan 199413312.66$13
Dec 199303412.33$0
Nov 199303514.49$0
Oct 199313515.85$16
Sep 199303715.03$0
Aug 199303715.66$0
Jul 199304715.46$0
Jun 199304516.79$0
May 199304217.68$0
Apr 199303918.05$0
Mar 199304118.14$0
Feb 199304117.90$0
Jan 199304616.93$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Feb 2006 — as filed, then multipliedworked
Condensate             0 bbl  × $ 57.59 =         $0
Gas                   43 Mcf  × $  7.75 =       $333

────────────────────────────────────────────────────
Month total                                     $333

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 01/G/88657 is the state's own key, not one this site invented.