KOSUB UNIT

Operated by THREE J ENERGY, INC. (P-5 857686) in the LA VERNIA, WEST (AUSTIN CHALK) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Oil lease lease 14496District 01Field 51099050Hydrogen sulphide fieldOilCasinghead gasSaveExport
Value, all time
$654 k
Nov 2003 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
271
no gaps in the span
Streams
2
oil, casinghead gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6 leases and 7 wells, and the rule below applies to all of them.

Discovered
1993-03-20
as the register files it
Field class
Oil
the register's own label
Between wells
900 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 80 acres. The field rule took effect on 1993-10-25.

The register flags this field for hydrogen sulphide. That is a poisonous gas that occurs naturally in some formations. The flag is a property of the field as the Commission records it. It is not a measurement taken at this lease, and it is not a statement that gas is escaping anywhere.

The Commission's schedule remark for this field reads: WERE SET UP IN ERROR AND WERE SPECIAL HORIZONTAL RULE SPACING.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
OilDisposition10,271 bbl$648,957
Casinghead gasProduction698 Mcf$5,410
Total$654,367

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 29.3214, -98.1877. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

29.32142, -98.18773 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
2,854 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 2,854 ft.

Completions filed
Oct 2004
1 of 1 wells

1 well

42-4933251512,854 ftOct 2004Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (271)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

271 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 2019157053.472.42$8,395
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 2019194056.803.06$11,019
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 20180059.543.11$0
Aug 20180059.403.07$0
Jul 20180065.142.93$0
Jun 20180060.183.08$0
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 20170045.373.00$0
Jul 201791043.873.09$3,992
Jun 20170042.493.09$0
May 20170045.373.26$0
Apr 2017125047.933.21$5,991
Mar 20170046.772.98$0
Feb 20170050.452.95$0
Jan 20170049.413.42$0
Dec 2016164048.763.72$7,997
Nov 20160042.492.64$0
Oct 20160046.193.09$0
Sep 20160141.553.10$3
Aug 20160141.442.92$3
Jul 2016172141.622.92$7,162
Jun 2016172145.352.69$7,803
May 20160142.521.99$2
Apr 20160136.561.99$2
Mar 2016154133.011.79$5,085
Feb 20160126.472.06$2
Jan 20160127.352.36$2
Dec 2015157132.362.00$5,083
Nov 20150138.792.17$2
Oct 20150143.552.43$2
Sep 20150142.992.76$3
Aug 20150140.162.87$3
Jul 20150148.152.95$3
Jun 2015161156.152.88$9,043
May 20150155.212.96$3
Apr 20150149.822.71$3
Mar 20150142.892.93$3
Feb 20150144.662.98$3
Jan 2015156143.433.10$6,778
Dec 20140154.693.59$4
Nov 20140170.464.25$4
Oct 2014147178.303.90$11,514
Sep 20140186.164.05$4
Aug 20140189.394.04$4
Jul 20140196.564.18$4
Jun 2014148198.164.74$14,532
May 20140194.734.73$5
Apr 20140195.944.81$5
Mar 20140195.895.06$5
Feb 2014148197.406.19$14,421
Jan 20140190.404.86$5
Dec 20130191.824.35$4
Nov 2013150188.853.74$13,331
Oct 20130197.423.78$4
Sep 201301104.113.72$4
Aug 201301104.253.52$4
Jul 20131391102.523.72$14,254
Jun 20130194.403.93$4
May 20130194.834.15$4
Apr 2013154193.964.28$14,474
Mar 20130193.623.91$4
Feb 2013162191.233.42$14,783
Jan 20130191.603.42$3
Dec 20120186.773.42$3
Nov 2012162186.953.62$14,090
Oct 20120189.383.40$3
Sep 20120194.672.92$3
Aug 2012164192.662.91$15,199
Jul 20120185.133.02$3
Jun 2012154179.822.52$12,295
May 20120191.612.49$2
Apr 201201101.652.00$2
Mar 201201105.052.22$2
Feb 20121591101.102.57$16,077
Jan 20120198.092.73$3
Dec 2011154196.873.24$14,921
Nov 20110195.723.31$3
Oct 20110184.983.65$4
Sep 2011162183.623.99$13,550
Aug 20110183.404.15$4
Jul 20110194.144.52$5
Jun 2011152192.904.64$14,125
May 20110198.134.40$4
Apr 201101105.964.33$4
Mar 2011157196.364.06$15,133
Feb 20110185.644.18$4
Jan 20110186.504.59$5
Dec 2010162185.734.35$13,893
Nov 20100180.843.80$4
Oct 20100178.103.51$4
Sep 2010158172.633.98$11,480
Aug 20100173.684.42$4
Jul 20100172.554.74$5
Jun 2010161170.364.91$11,333
May 20100171.124.24$4
Apr 20100181.694.12$4
Mar 20100178.394.39$4
Feb 20100173.585.44$5
Jan 2010151174.365.96$11,234
Dec 20090171.445.48$5
Nov 20090174.593.75$4
Oct 20090172.544.11$4
Sep 20090165.543.06$3
Aug 20090167.423.22$3
Jul 20090161.133.46$3
Jun 20090166.163.90$4
May 20090154.743.93$4
Apr 20090146.773.59$4
Mar 2009154142.144.06$6,494
Feb 20090132.814.63$5
Jan 20090135.865.37$5
Dec 20080137.105.98$6
Nov 2008160155.496.86$8,885
Oct 20080175.246.92$7
Sep 200801101.767.88$8
Aug 200801114.228.48$8
Jul 200801131.0811.39$11
Jun 200801131.3313.03$13
May 20081801123.1711.57$22,182
Apr 200801110.3110.45$10
Mar 200801101.909.66$10
Feb 20080192.538.77$9
Jan 2008156190.388.21$14,107
Dec 20070188.337.30$7
Nov 20070191.677.29$7
Oct 20070182.856.92$7
Sep 2007150175.846.24$11,382
Aug 20070169.066.39$6
Jul 20070170.906.39$6
Jun 20070162.007.55$8
May 2007153158.747.85$8,995
Apr 20070159.617.81$8
Mar 20070156.927.30$7
Feb 2007156155.108.22$8,604
Jan 20070150.306.73$7
Dec 20060156.656.92$7
Nov 20060154.207.62$8
Oct 2006164154.906.01$9,010
Sep 20060160.085.04$5
Aug 2006158168.717.34$10,864
Jul 20060169.376.34$6
Jun 20060166.286.38$6
May 2006178166.016.42$11,756
Apr 200603064.397.36$221
Mar 200603156.707.08$220
Feb 20061732857.597.75$10,180
Jan 200603160.598.93$277
Dec 20051693154.9413.42$9,701
Nov 20052043054.6910.59$11,474
Oct 200503158.3413.80$428
Sep 20051853061.4512.08$11,731
Aug 200503161.519.80$304
Jul 20051783155.697.84$10,156
Jun 20051993052.337.38$10,635
May 20051833145.226.65$8,481
Apr 20052013049.207.36$10,110
Mar 20051843050.377.15$9,483
Feb 20056022845.226.31$27,399
Jan 20051843143.166.32$8,137
Dec 20041613139.866.75$6,627
Nov 20045523045.286.33$25,184
Oct 20048402849.706.52$41,930
Sep 20040043.245.28$0
Aug 20040042.375.55$0
Jul 20040038.286.08$0
Jun 20040036.106.43$0
May 20040037.486.49$0
Apr 20040034.475.86$0
Mar 20040034.365.53$0
Feb 20040032.455.51$0
Jan 20040032.036.30$0
Dec 20030030.266.30$0
Nov 20030028.804.60$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Oct 2019 — as filed, then multipliedworked
Oil                  157 bbl  × $ 53.47 =     $8,395
Casinghead gas         0 Mcf  × $  2.42 =         $0

────────────────────────────────────────────────────
Month total                                   $8,395

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 01/O/14496 is the state's own key, not one this site invented.