HAIDUSEK

Operated by BSE PRODUCTION CO. (P-5 104965) in the HOLYFIELD FAN MAN SAND (YEGUA) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 176317District 02Field 42371480CondensateGasSaveExport
Value, all time
$3.7 M
Jan 2000 – Oct 2010
Value, last 12 filed months
$19 k
at the published price for each month
Months reported
130
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 8 leases and 8 wells, and the rule below applies to all of them.

Discovered
1993-11-16
as the register files it
Field class
Gas
the register's own label
Between wells
no field rule filed
From a lease line
no field rule filed

The Commission's schedule remark for this field reads: AOF-1 AND AOF-2 EFFECTIVE 06/01/97.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition2,224 bbl$68,929
GasProduction705,597 Mcf$3,649,320
Total$3,718,249

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 29.3612, -96.8141. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

29.36124, -96.81408 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
5,400 ft
1 wells filed one
Completion to plug
10.6 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 5,400 ft.

Completions filed
Jan 2000
1 of 1 wells
Plug dates filed
Aug 2010
1 of 1 wells

Last completion to plug: a median of 10.6 years across the 1 well that filed both dates, with the middle half between 10.6 years and 10.6 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-2853243715,400 ftJan 2000Aug 2010Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (130)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

130 months

Oct 20100078.103.51$0
Sep 20100072.633.98$0
Aug 201071073.684.42$5,231
Jul 2010010372.554.74$488
Jun 2010014970.364.91$732
May 2010018471.124.24$779
Apr 2010015481.694.12$635
Mar 2010019078.394.39$834
Feb 2010018773.585.44$1,018
Jan 2010049974.365.96$2,976
Dec 2009058871.445.48$3,224
Nov 2009079274.593.75$2,971
Oct 2009087972.544.11$3,613
Sep 2009084765.543.06$2,596
Aug 2009070967.423.22$2,282
Jul 200901,01061.133.46$3,499
Jun 2009092666.163.90$3,607
May 200901,02154.743.93$4,008
Apr 200901,14346.773.59$4,101
Mar 200901,30242.144.06$5,285
Feb 200901,09432.814.63$5,069
Jan 200901,45735.865.37$7,826
Dec 200801,53037.105.98$9,145
Nov 200801,60655.496.86$11,018
Oct 200801,93175.246.92$13,366
Sep 200801,765101.767.88$13,903
Aug 200801,923114.228.48$16,313
Jul 200801,824131.0811.39$20,774
Jun 200801,636131.3313.03$21,321
May 200801,808123.1711.57$20,926
Apr 200801,555110.3110.45$16,257
Mar 200805,832101.909.66$56,361
Feb 200801,42192.538.77$12,463
Jan 200805,20290.388.21$42,686
Dec 2007058488.337.30$4,264
Nov 200702,07491.677.29$15,123
Oct 2007099382.856.92$6,874
Sep 2007962,08475.846.24$20,293
Aug 200701,96369.066.39$12,540
Jul 200702,01170.906.39$12,846
Jun 200701,98862.007.55$15,006
May 200702,45858.747.85$19,286
Apr 200703,03859.617.81$23,712
Mar 200713,59156.927.30$26,278
Feb 200702,17055.108.22$17,829
Jan 200702,04950.306.73$13,783
Dec 200601,80456.656.92$12,481
Nov 200602,04654.207.62$15,585
Oct 200601,86254.906.01$11,198
Sep 200601,81960.085.04$9,163
Aug 200602,92268.717.34$21,447
Jul 200603,08669.376.34$19,574
Jun 200602,66366.286.38$17,000
May 200603,42366.016.42$21,993
Apr 200603,07964.397.36$22,663
Mar 200603,96956.707.08$28,112
Feb 200603,45557.597.75$26,780
Jan 200604,37160.598.93$39,048
Dec 200504,80354.9413.42$64,434
Nov 200504,76054.6910.59$50,401
Oct 200503,47858.3413.80$47,982
Sep 200503,77761.4512.08$45,622
Aug 200504,96361.519.80$48,622
Jul 200505,28955.697.84$41,485
Jun 200504,66452.337.38$34,425
May 200504,87145.226.65$32,398
Apr 200505,72549.207.36$42,139
Mar 200506,88850.377.15$49,283
Feb 20050045.226.31$0
Jan 20050043.166.32$0
Dec 20040039.866.75$0
Nov 20040045.286.33$0
Oct 20041753,92449.706.52$34,263
Sep 200403,13143.245.28$16,544
Aug 200404,31242.375.55$23,934
Jul 200401,85938.286.08$11,310
Jun 200404,14936.106.43$26,691
May 200406,83837.486.49$44,410
Apr 200407,46934.475.86$43,757
Mar 200408,18634.365.53$45,270
Feb 200408,71032.455.51$47,989
Jan 200408,23732.036.30$51,890
Dec 20031708,23330.266.30$57,026
Nov 200308,09528.804.60$37,198
Oct 200308,24828.174.76$39,258
Sep 200309,50526.314.75$45,143
Aug 200317210,31229.765.13$58,016
Jul 200309,98929.415.17$51,652
Jun 200309,35828.565.98$55,989
May 200309,94326.595.97$59,386
Apr 200309,42126.675.41$50,942
Mar 200309,80331.146.10$59,759
Feb 200306,14133.487.93$48,673
Jan 200309,92630.315.58$55,407
Dec 200208,86926.914.85$43,048
Nov 200209,47124.664.14$39,181
Oct 20021669,81126.464.23$45,884
Sep 200206,75727.443.64$24,563
Aug 2002011,26525.963.16$35,644
Jul 2002011,56424.583.06$35,406
Jun 20021539,98723.733.34$36,970
May 2002010,35424.663.58$37,109
Apr 2002010,38523.653.51$36,475
Mar 200214712,31622.003.10$41,447
Feb 2002011,62518.222.38$27,617
Jan 2002011,10717.172.38$26,387
Dec 20011709,39116.932.36$25,082
Nov 20011018,51118.072.41$22,298
Oct 200109,27419.782.53$23,453
Sep 200106,27724.262.25$14,132
Aug 2001010,49624.873.05$32,046
Jul 200116111,81123.933.20$41,613
Jun 20016610,75024.563.82$42,731
May 2001010,03525.524.31$43,224
Apr 200114410,30124.685.34$58,513
Mar 2001010,28824.545.38$55,313
Feb 200109,40227.755.77$54,222
Jan 200106,99727.478.40$58,766
Dec 2000697,58826.889.12$71,076
Nov 2000010,76832.215.66$60,925
Oct 2000011,92031.235.15$61,334
Sep 20005612,72331.875.19$67,773
Aug 20005611,93629.644.54$55,858
Jul 2000012,73428.534.09$52,079
Jun 200010013,13829.304.40$60,701
May 20006913,81827.263.68$52,728
Apr 2000015,17524.513.12$47,285
Mar 20008114,26228.422.86$43,088
Feb 2000014,50427.622.73$39,545
Jan 2000014,21125.272.48$35,250

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Aug 2010 — as filed, then multipliedworked
Condensate            71 bbl  × $ 73.68 =     $5,231
Gas                    0 Mcf  × $  4.42 =         $0

────────────────────────────────────────────────────
Month total                                   $5,231

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 02/G/176317 is the state's own key, not one this site invented.