O'CONNOR, DENNIS ET AL -L-

Operated by T-C OIL COMPANY, LLC (P-5 833782) in the LAKE PASTURE (H-434) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 188176District 02Field 51512902GasSaveExport
Value, all time
$8.2 M
Jan 2002 – May 2013
Value, last 12 filed months
$58 k
at the published price for each month
Months reported
137
no gaps in the span
Streams
1
gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 86 leases and 210 wells, and the rule below applies to all of them.

Discovered
1971-02-04
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 5 acres. The field rule took effect on 2004-08-12.

The Commission's schedule remark for this field reads: NEED P-15, NO PLAT FOR ENTITY FOR DENSITY.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
GasProduction1,228,777 Mcf$8,239,793
Total$8,239,793

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 28.4052, -97.0663. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

28.40516, -97.06633 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
4,675 ft
1 wells filed one
Completion to plug
2.1 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 4,675 ft.

Completions filed
Nov 2019
1 of 1 wells
Plug dates filed
Dec 2021
1 of 1 wells

Last completion to plug: a median of 2.1 years across the 1 well that filed both dates, with the middle half between 2.1 years and 2.1 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-39130210L 394,675 ftNov 2019Dec 2021Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (137)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

137 months

May 2013094.834.15$0
Apr 2013093.964.28$0
Mar 2013093.623.91$0
Feb 201336791.233.42$1,255
Jan 20131,80191.603.42$6,159
Dec 20121,07286.773.42$3,666
Nov 20121,98086.953.62$7,177
Oct 20122,33989.383.40$7,952
Sep 20122,15094.672.92$6,275
Aug 20121,55192.662.91$4,511
Jul 20123,85985.133.02$11,657
Jun 20123,85879.822.52$9,718
May 20124,22291.612.49$10,506
Apr 20124,100101.652.00$8,187
Mar 20123,831105.052.22$8,513
Feb 20122,803101.102.57$7,204
Jan 20124,13298.092.73$11,297
Dec 20113,76096.873.24$12,181
Nov 20112,10095.723.31$6,954
Oct 201147984.983.65$1,748
Sep 201153483.623.99$2,128
Aug 20114,06883.404.15$16,879
Jul 20111,77494.144.52$8,014
Jun 201180092.904.64$3,712
May 20115,04598.134.40$22,222
Apr 20114,744105.964.33$20,557
Mar 20114,53096.364.06$18,380
Feb 20115,80785.644.18$24,273
Jan 20115,14786.504.59$23,618
Dec 20104,46485.734.35$19,408
Nov 20103,88780.843.80$14,752
Oct 20105,39078.103.51$18,913
Sep 20105,26972.633.98$20,968
Aug 20106,43473.684.42$28,434
Jul 20106,00672.554.74$28,447
Jun 20105,99270.364.91$29,423
May 20103,51771.124.24$14,895
Apr 20103,38381.694.12$13,947
Mar 20104,90378.394.39$21,518
Feb 20104,89573.585.44$26,640
Jan 20104,48674.365.96$26,755
Dec 20093,10871.445.48$17,044
Nov 20093,72274.593.75$13,963
Oct 20096,24572.544.11$25,669
Sep 20096,19165.543.06$18,974
Aug 20094,67467.423.22$15,043
Jul 20094,92661.133.46$17,066
Jun 20094,59766.163.90$17,905
May 20094,61554.743.93$18,117
Apr 20095,03946.773.59$18,077
Mar 20094,96642.144.06$20,157
Feb 20094,64632.814.63$21,525
Jan 20095,28535.865.37$28,386
Dec 20084,29337.105.98$25,660
Nov 20081,62855.496.86$11,169
Oct 20086,15375.246.92$42,591
Sep 20085,432101.767.88$42,788
Aug 20086,089114.228.48$51,653
Jul 20085,154131.0811.39$58,701
Jun 20085,370131.3313.03$69,985
May 20086,187123.1711.57$71,610
Apr 20083,848110.3110.45$40,230
Mar 20084,982101.909.66$48,146
Feb 20086,35492.538.77$55,728
Jan 20085,05490.388.21$41,472
Dec 20076,62488.337.30$48,368
Nov 20078,51091.677.29$62,052
Oct 20079,29182.856.92$64,312
Sep 20076,49575.846.24$40,556
Aug 20073,85669.066.39$24,632
Jul 20078,41770.906.39$53,767
Jun 200712,70262.007.55$95,880
May 200717,20158.747.85$134,964
Apr 200717,68159.617.81$138,004
Mar 200721,14756.927.30$154,415
Feb 200721,87155.108.22$179,692
Jan 200728,92350.306.73$194,561
Dec 200633,52656.656.92$231,948
Nov 200634,44554.207.62$262,384
Oct 200639,25854.906.01$236,090
Sep 200637,59560.085.04$189,374
Aug 200633,54768.717.34$246,232
Jul 200634,77069.376.34$220,538
Jun 200639,13366.286.38$249,820
May 200638,32266.016.42$246,219
Apr 200638,59864.397.36$284,100
Mar 200636,23056.707.08$256,614
Feb 200636,15557.597.75$280,242
Jan 200635,56660.598.93$317,722
Dec 200538,77954.9413.42$520,236
Nov 200532,85054.6910.59$347,829
Oct 200527,18558.3413.80$375,038
Sep 20056,32661.4512.08$76,412
Aug 2005061.519.80$0
Jul 2005055.697.84$0
Jun 2005052.337.38$0
May 2005045.226.65$0
Apr 2005049.207.36$0
Mar 2005050.377.15$0
Feb 2005045.226.31$0
Jan 2005043.166.32$0
Dec 2004039.866.75$0
Nov 200434,98445.286.33$221,463
Oct 200435,19049.706.52$229,266
Sep 20044,28843.245.28$22,657
Aug 2004042.375.55$0
Jul 2004038.286.08$0
Jun 200467436.106.43$4,336
May 2004037.486.49$0
Apr 2004034.475.86$0
Mar 2004034.365.53$0
Feb 2004032.455.51$0
Jan 20042,73232.036.30$17,211
Dec 200310,57230.266.30$66,621
Nov 200315,81828.804.60$72,686
Oct 200313,98828.174.76$66,578
Sep 200314,46626.314.75$68,704
Aug 200314,44629.765.13$74,104
Jul 20036,91129.415.17$35,736
Jun 20036,56328.565.98$39,266
May 20037,00626.595.97$41,845
Apr 20036,50826.675.41$35,191
Mar 20036,90631.146.10$42,099
Feb 20035,96033.487.93$47,238
Jan 20036,60130.315.58$36,847
Dec 20025,82526.914.85$28,273
Nov 20026,70624.664.14$27,742
Oct 20026,85726.464.23$28,999
Sep 20026,58927.443.64$23,952
Aug 20026,24825.963.16$19,770
Jul 20026,85424.583.06$20,985
Jun 20026,74523.733.34$22,516
May 20027,21424.663.58$25,855
Apr 20026,75923.653.51$23,740
Mar 20026,62622.003.10$20,559
Feb 20024,80118.222.38$11,406
Jan 20024,90017.172.38$11,641

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Feb 2013 — as filed, then multipliedworked
Gas                  367 Mcf  × $  3.42 =     $1,255

────────────────────────────────────────────────────
Month total                                   $1,255

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 02/G/188176 is the state's own key, not one this site invented.