PEREZ

Operated by AMPAK OIL COMPANY (P-5 20463) in the COLETTO CREEK, SOUTH (3000) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 213341District 02Field 19561328GasSaveExport
Value, all time
$530 k
Mar 2005 – May 2026
Value, last 12 filed months
$420
at the published price for each month
Months reported
255
no gaps in the span
Streams
1
gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 23 leases and 23 wells, and the rule below applies to all of them.

Discovered
1962-04-23
as the register files it
Field class
Gas
the register's own label
Between wells
1,200 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 100 acres. The field rule took effect on 1968-01-01.

The Commission's schedule remark for this field reads: DENSITY RULES AND ASSIGNED 100 % ACRES ALLOCATION FORMULA.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
GasProduction73,944 Mcf$529,557
Total$529,557

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 28.7224, -97.0883. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

28.72238, -97.08834 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
5,100 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 5,100 ft.

Completions filed
Mar 2005
1 of 1 wells

1 well

42-4693341015,100 ftMar 2005

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (255)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

255 months

May 20260106.413.05$0
Apr 20261298.932.87$34
Mar 2026089.753.15$0
Feb 2026163.503.75$4
Jan 20261859.138.00$144
Dec 2025056.664.41$0
Nov 2025158.593.93$4
Oct 2025859.383.30$26
Sep 2025962.743.08$28
Aug 20252663.933.01$78
Jul 20252266.743.32$73
Jun 2025966.483.13$28
May 20254360.553.23$139
Apr 2025762.363.54$25
Mar 2025467.704.27$17
Feb 2025270.884.34$9
Jan 2025674.324.28$26
Dec 2024768.993.12$22
Nov 2024869.052.20$18
Oct 20241471.372.28$32
Sep 20242369.612.36$54
Aug 20242475.632.06$50
Jul 20243779.932.15$79
Jun 20241978.082.63$50
May 20242378.812.20$51
Apr 20243784.451.66$61
Mar 20241480.301.55$22
Feb 20243176.091.78$55
Jan 2024073.023.30$0
Dec 20234171.262.61$107
Nov 20233077.892.81$84
Oct 2023085.443.09$0
Sep 20232489.042.74$66
Aug 20233280.522.67$86
Jul 20232774.852.64$71
Jun 20232468.962.26$54
May 20231970.622.23$42
Apr 2023078.122.24$0
Mar 20231672.852.39$38
Feb 20231275.112.47$30
Jan 20232076.533.39$68
Dec 20222176.415.73$120
Nov 20221485.005.65$79
Oct 20221987.185.86$111
Sep 20222884.888.16$229
Aug 20222794.529.13$246
Jul 202253101.587.54$400
Jun 202249115.097.98$391
May 202240109.378.43$337
Apr 202232104.226.84$219
Mar 202229108.885.08$147
Feb 20223791.054.86$180
Jan 20224181.844.54$186
Dec 20214671.323.90$179
Nov 20215177.435.24$267
Oct 20216379.795.71$360
Sep 20212669.865.35$139
Aug 20211266.024.22$51
Jul 20215470.783.98$215
Jun 20216669.493.38$223
May 20214163.483.02$124
Apr 20212760.362.76$74
Mar 20211561.302.72$41
Feb 20213457.805.55$189
Jan 20216650.412.81$185
Dec 20202844.642.68$75
Nov 20202638.772.71$70
Oct 20207736.972.48$191
Sep 20205937.091.99$117
Aug 20203839.982.39$91
Jul 20204638.371.83$84
Jun 20204834.901.69$81
May 20205716.921.81$103
Apr 20204314.751.80$78
Mar 20204530.341.86$84
Feb 20204649.881.98$91
Jan 20206857.252.09$142
Dec 20196759.012.30$154
Nov 20198455.302.75$231
Oct 20196953.472.42$167
Sep 20197555.052.66$199
Aug 20196953.112.30$159
Jul 2019956.272.46$22
Jun 20196752.782.49$167
May 20197858.482.74$214
Apr 20198062.632.75$220
Mar 20197856.803.06$239
Feb 20197050.852.79$195
Jan 20198246.033.23$265
Dec 20187546.594.19$314
Nov 20188052.934.24$339
Oct 20182361.443.40$78
Sep 20188659.543.11$267
Aug 20189559.403.07$291
Jul 20189665.142.93$281
Jun 20188760.183.08$268
May 20185265.382.90$151
Apr 20184963.842.90$142
Mar 20187361.222.79$203
Feb 20186261.782.77$172
Jan 20185862.874.01$233
Dec 20176457.272.92$187
Nov 20176255.423.12$193
Oct 20177649.292.98$227
Sep 20177547.523.09$232
Aug 20176945.373.00$207
Jul 20178143.873.09$250
Jun 20176142.493.09$188
May 20177845.373.26$255
Apr 20177547.933.21$241
Mar 20173346.772.98$98
Feb 20173350.452.95$97
Jan 20174449.413.42$150
Dec 20164748.763.72$175
Nov 20166142.492.64$161
Oct 20168246.193.09$253
Sep 20167441.553.10$229
Aug 201611741.442.92$342
Jul 20163841.622.92$111
Jun 20166545.352.69$175
May 20168242.521.99$163
Apr 20168136.561.99$161
Mar 20166333.011.79$113
Feb 20167126.472.06$147
Jan 20167727.352.36$182
Dec 20156132.362.00$122
Nov 20156938.792.17$150
Oct 20159643.552.43$233
Sep 20158942.992.76$246
Aug 20157240.162.87$207
Jul 20158248.152.95$242
Jun 20157256.152.88$208
May 20159155.212.96$269
Apr 20158849.822.71$238
Mar 20157942.892.93$232
Feb 20157644.662.98$226
Jan 20156643.433.10$205
Dec 20145554.693.59$198
Nov 20141870.464.25$77
Oct 20143178.303.90$121
Sep 20144586.164.05$182
Aug 20142589.394.04$101
Jul 20143396.564.18$138
Jun 20142898.164.74$133
May 20142094.734.73$95
Apr 20141195.944.81$53
Mar 20141595.895.06$76
Feb 20142797.406.19$167
Jan 20142490.404.86$117
Dec 20131291.824.35$52
Nov 2013788.853.74$26
Oct 20132197.423.78$79
Sep 201328104.113.72$104
Aug 201326104.253.52$92
Jul 201332102.523.72$119
Jun 20132294.403.93$87
May 20132294.834.15$91
Apr 20133193.964.28$133
Mar 20133193.623.91$121
Feb 20132891.233.42$96
Jan 20132991.603.42$99
Dec 20124486.773.42$150
Nov 20125386.953.62$192
Oct 20126489.383.40$218
Sep 20124394.672.92$125
Aug 20123392.662.91$96
Jul 20123885.133.02$115
Jun 20128779.822.52$219
May 20127991.612.49$197
Apr 201277101.652.00$154
Mar 201269105.052.22$153
Feb 201258101.102.57$149
Jan 20126098.092.73$164
Dec 20115296.873.24$168
Nov 20114095.723.31$132
Oct 20114984.983.65$179
Sep 20114483.623.99$175
Aug 20114983.404.15$203
Jul 20113194.144.52$140
Jun 20112692.904.64$121
May 20112498.134.40$106
Apr 201133105.964.33$143
Mar 20112096.364.06$81
Feb 20112585.644.18$105
Jan 20113786.504.59$170
Dec 20102885.734.35$122
Nov 20104280.843.80$159
Oct 20104678.103.51$161
Sep 20105072.633.98$199
Aug 201014273.684.42$628
Jul 201017072.554.74$805
Jun 201011970.364.91$584
May 20103771.124.24$157
Apr 20106081.694.12$247
Mar 201018978.394.39$829
Feb 201061173.585.44$3,325
Jan 201035374.365.96$2,105
Dec 200930571.445.48$1,673
Nov 200937174.593.75$1,392
Oct 200943572.544.11$1,788
Sep 200938165.543.06$1,168
Aug 200956167.423.22$1,806
Jul 200972661.133.46$2,515
Jun 200974966.163.90$2,917
May 200983354.743.93$3,270
Apr 200983146.773.59$2,981
Mar 200979142.144.06$3,211
Feb 200971632.814.63$3,317
Jan 200979835.865.37$4,286
Dec 200878637.105.98$4,698
Nov 200880455.496.86$5,516
Oct 200892675.246.92$6,410
Sep 2008988101.767.88$7,783
Aug 2008848114.228.48$7,194
Jul 2008955131.0811.39$10,877
Jun 2008875131.3313.03$11,404
May 20081,231123.1711.57$14,248
Apr 20081,311110.3110.45$13,706
Mar 20081,506101.909.66$14,554
Feb 200830992.538.77$2,710
Jan 20081,12790.388.21$9,248
Dec 200786988.337.30$6,345
Nov 200780791.677.29$5,884
Oct 200793682.856.92$6,479
Sep 200788575.846.24$5,526
Aug 200796169.066.39$6,139
Jul 20071,02870.906.39$6,567
Jun 20071,33862.007.55$10,100
May 20071,52558.747.85$11,966
Apr 20071,72159.617.81$13,433
Mar 20071,65056.927.30$12,048
Feb 20071,46555.108.22$12,036
Jan 20071,15050.306.73$7,736
Dec 20061,02256.656.92$7,071
Nov 20061,21454.207.62$9,248
Oct 20061,15354.906.01$6,934
Sep 20061,13160.085.04$5,697
Aug 20061,38068.717.34$10,129
Jul 20061,38269.376.34$8,766
Jun 20061,45266.286.38$9,269
May 20061,59066.016.42$10,216
Apr 20061,38864.397.36$10,216
Mar 20061,67656.707.08$11,871
Feb 20061,46557.597.75$11,355
Jan 20061,73860.598.93$15,526
Dec 20051,99654.9413.42$26,777
Nov 20051,75354.6910.59$18,561
Oct 20051,35858.3413.80$18,735
Sep 200591961.4512.08$11,101
Aug 200594461.519.80$9,248
Jul 20051,34755.697.84$10,565
Jun 20051,76952.337.38$13,057
May 20051,41645.226.65$9,418
Apr 20051,46249.207.36$10,761
Mar 200595250.377.15$6,811

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Apr 2026 — as filed, then multipliedworked
Gas                   12 Mcf  × $  2.87 =        $34

────────────────────────────────────────────────────
Month total                                      $34

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 02/G/213341 is the state's own key, not one this site invented.