JONES, B. E.

Operated by WHEELER OPERATING CORPORATION (P-5 914263) in the CONROE (CONS. U) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 193418District 03Field 20211087GasSaveExport
Value, all time
$263 k
Jan 2003 – Sep 2011
Value, last 12 filed months
$0
at the published price for each month
Months reported
105
no gaps in the span
Streams
1
gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 50 leases and 52 wells, and the rule below applies to all of them.

Discovered
2002-12-03
as the register files it
Field class
Oil and gas
the register's own label
Between wells
330 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2002-12-03.

The Commission's schedule remark for this field reads: PER DOCKET 03-0237806 EFF 4/14/04, ALLOCATION FORMULA SUSPENDED.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
GasProduction36,003 Mcf$262,917
Total$262,917

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.2606, -95.3824. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.26062, -95.38240 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
5,204 ft
1 wells filed one
Completion to plug
8.7 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 5,204 ft.

Completions filed
Jan 2003
1 of 1 wells
Plug dates filed
Sep 2011
1 of 1 wells

Last completion to plug: a median of 8.7 years across the 1 well that filed both dates, with the middle half between 8.7 years and 8.7 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-339304334A5,204 ftJan 2003Sep 2011Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (105)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

105 months

Sep 2011083.623.99$0
Aug 2011083.404.15$0
Jul 2011094.144.52$0
Jun 2011092.904.64$0
May 2011098.134.40$0
Apr 20110105.964.33$0
Mar 2011096.364.06$0
Feb 2011085.644.18$0
Jan 2011086.504.59$0
Dec 2010085.734.35$0
Nov 2010080.843.80$0
Oct 2010078.103.51$0
Sep 2010072.633.98$0
Aug 2010073.684.42$0
Jul 2010072.554.74$0
Jun 2010070.364.91$0
May 2010071.124.24$0
Apr 2010081.694.12$0
Mar 2010078.394.39$0
Feb 2010073.585.44$0
Jan 2010074.365.96$0
Dec 2009071.445.48$0
Nov 2009074.593.75$0
Oct 2009072.544.11$0
Sep 2009065.543.06$0
Aug 2009067.423.22$0
Jul 2009061.133.46$0
Jun 2009066.163.90$0
May 20091154.743.93$43
Apr 20091446.773.59$50
Mar 20091342.144.06$53
Feb 20091232.814.63$56
Jan 2009935.865.37$48
Dec 2008937.105.98$54
Nov 2008755.496.86$48
Oct 2008975.246.92$62
Sep 200812101.767.88$95
Aug 200821114.228.48$178
Jul 200824131.0811.39$273
Jun 200828131.3313.03$365
May 200814123.1711.57$162
Apr 200813110.3110.45$136
Mar 200835101.909.66$338
Feb 20082392.538.77$202
Jan 20081890.388.21$148
Dec 20072488.337.30$175
Nov 20072791.677.29$197
Oct 20071682.856.92$111
Sep 20071075.846.24$62
Aug 2007869.066.39$51
Jul 20071170.906.39$70
Jun 20072462.007.55$181
May 20071358.747.85$102
Apr 20072259.617.81$172
Mar 20071656.927.30$117
Feb 200728055.108.22$2,300
Jan 20072050.306.73$135
Dec 2006656.656.92$42
Nov 2006554.207.62$38
Oct 200646454.906.01$2,790
Sep 20061,41860.085.04$7,143
Aug 200612268.717.34$895
Jul 200616569.376.34$1,047
Jun 200624066.286.38$1,532
May 200631066.016.42$1,992
Apr 200631164.397.36$2,289
Mar 200651656.707.08$3,655
Feb 200661257.597.75$4,744
Jan 200664060.598.93$5,717
Dec 200561254.9413.42$8,210
Nov 200580454.6910.59$8,513
Oct 20051,32858.3413.80$18,321
Sep 20051,26161.4512.08$15,232
Aug 20051,56061.519.80$15,283
Jul 20051,60755.697.84$12,605
Jun 20051,48452.337.38$10,953
May 20051,66145.226.65$11,048
Apr 20051,75049.207.36$12,881
Mar 20051,99650.377.15$14,281
Feb 200567445.226.31$4,254
Jan 20052743.166.32$171
Dec 20042539.866.75$169
Nov 20042345.286.33$146
Oct 20041549.706.52$98
Sep 20042143.245.28$111
Aug 20041742.375.55$94
Jul 20041038.286.08$61
Jun 20041236.106.43$77
May 20041537.486.49$97
Apr 20041234.475.86$70
Mar 20041534.365.53$83
Feb 20041632.455.51$88
Jan 20041832.036.30$113
Dec 20032030.266.30$126
Nov 20031628.804.60$74
Oct 2003028.174.76$0
Sep 200322526.314.75$1,069
Aug 2003029.765.13$0
Jul 20031,55429.415.17$8,035
Jun 20035,80428.565.98$34,725
May 20036,50926.595.97$38,876
Apr 2003026.675.41$0
Mar 2003031.146.10$0
Feb 200368033.487.93$5,390
Jan 200368030.315.58$3,796

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2009 — as filed, then multipliedworked
Gas                   11 Mcf  × $  3.93 =        $43

────────────────────────────────────────────────────
Month total                                      $43

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 03/G/193418 is the state's own key, not one this site invented.