MILAM HALL UNIT

Operated by WILDFIRE ENERGY OPERATING LLC (P-5 923444) in the GIDDINGS (AUSTIN CHALK, GAS) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 293225District 03Field 347735502 tax incentive programmesCondensateGasSaveExport
Value, all time
$34.9 M
Dec 2021 – May 2026
Value, last 12 filed months
$2.3 M
at the published price for each month
Months reported
53
1 month not filed
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 1,061 leases and 1,061 wells, and the rule below applies to all of them.

Discovered
1978-08-01
as the register files it
Field class
Gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 80 acres. The field rule took effect on 2018-10-16.

The Commission's schedule remark for this field reads: AMENDED DRILLING PERMITS, NOTICE, OR HEARING.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
NGPA1none
ST-1112022-10-05231037

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition308,943 bbl$26,464,204
GasProduction1,847,102 Mcf$8,439,101
Total$34,903,305

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.1963, -96.6830. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.19632, -96.68299 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
11,099 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 11,099 ft.

Completions filed
Dec 2021
1 of 1 wells

1 well

42-477311481H11,099 ftDec 2021

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (53)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

53 months

May 20262,12912,691106.413.05$265,202
Apr 20262,03912,76598.932.87$238,350
Mar 20262,25912,33889.753.15$241,603
Feb 20262,31814,02763.503.75$199,799
Jan 20262,35311,76259.138.00$233,204
Dec 20252,66014,80356.664.41$216,047
Nov 20252,29714,14258.593.93$190,109
Oct 20251,5158,48659.383.30$118,006
Sep 20253,48720,62362.743.08$282,230
Aug 20253,26218,88263.933.01$265,464
Jul 2025107066.743.32$7,141
Jun 20251,0436,40766.483.13$89,384
May 20252,77417,50860.553.23$224,557
Apr 20252,57416,74562.363.54$219,844
Mar 20253,68017,96267.704.27$325,804
Feb 20253,28816,66670.884.34$305,398
Jan 20253,99419,14774.324.28$378,758
Dec 20243,82619,43368.993.12$324,613
Nov 20243,48419,80769.052.20$284,115
Oct 20243,38120,99871.372.28$289,207
Sep 20243,42623,14469.612.36$293,205
Aug 20242,67822,67375.632.06$249,326
Jul 20242,08413,91079.932.15$196,433
Jun 20243,42622,72878.082.63$327,367
May 20243,34724,25678.812.20$317,102
Apr 20243,90724,67684.451.66$370,889
Mar 20244,03426,62580.301.55$365,069
Feb 20243,85926,46176.091.78$340,828
Jan 20243,91326,63773.023.30$373,567
Dec 20234,27429,21671.262.61$380,840
Nov 20234,23230,46377.892.81$415,157
Oct 20233,76130,92085.443.09$416,799
Sep 20234,36444,99589.042.74$511,634
Aug 20236,11935,15980.522.67$586,678
Jul 20236,37637,38074.852.64$575,994
Jun 20235,87938,95468.962.26$493,393
May 20236,23540,13970.622.23$529,721
Apr 20237,13441,82778.122.24$650,907
Mar 20236,73245,93572.852.39$600,356
Feb 20236,77042,70375.112.47$613,787
Jan 20237,70350,02876.533.39$758,991
Dec 20228,63453,29176.415.73$965,032
Nov 20228,59356,18485.005.65$1,047,631
Oct 20229,49960,42287.185.86$1,182,423
Sep 202210,34474,63684.888.16$1,487,303
Aug 20229,88552,31394.529.13$1,411,799
Jul 202212,78459,401101.587.54$1,746,606
Jun 202213,29667,901115.097.98$2,071,897
May 202215,32882,387109.378.43$2,371,196
Apr 202218,60395,843104.226.84$2,594,141
Mar 202218,28593,487108.885.08$2,465,448
Feb 202223,448136,11091.054.86$2,796,277
Dec 20217,52141,10671.323.90$696,675

Not filed, and not zero: Jan 2022. The Railroad Commission holds no report for those months, so this page shows none — a zero would state that the lease produced nothing.

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate         2,129 bbl  × $106.41 =   $226,547
Gas               12,691 Mcf  × $  3.05 =    $38,655

────────────────────────────────────────────────────
Month total                                 $265,202

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 03/G/293225 is the state's own key, not one this site invented.