GARZA, L.

Operated by MOUNTAIN V TEXAS, LLC (P-5 103601) in the GARZA (CONSOLIDATED) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 186016District 04Field 341123502 tax incentive programmesCondensateGasSaveExport
Value, all time
$3.5 M
Nov 2001 – May 2026
Value, last 12 filed months
$32 k
at the published price for each month
Months reported
295
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 22 leases and 22 wells, and the rule below applies to all of them.

Discovered
1997-05-07
as the register files it
Field class
Gas
the register's own label
Between wells
1,200 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 1997-06-27.

The Commission's schedule remark for this field reads: ASSIGNED TWO PART ALLOCATION FORMULA.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112003-05-12151359
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition2,855 bbl$62,453
GasProduction904,383 Mcf$3,432,550
Total$3,495,004

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 27.0769, -99.1080. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

27.07685, -99.10801 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
11,000 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 11,000 ft.

Completions filed
Dec 2001
1 of 1 wells

1 well

42-505344191711,000 ftDec 2001

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (295)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

295 months

May 202606,340106.413.05$19,311
Apr 2026051298.932.87$1,469
Mar 2026030989.753.15$973
Feb 2026028363.503.75$1,061
Jan 2026026259.138.00$2,095
Dec 2025035356.664.41$1,558
Nov 2025025858.593.93$1,013
Oct 2025031259.383.30$1,031
Sep 2025049962.743.08$1,535
Aug 2025010063.933.01$301
Jul 2025022466.743.32$743
Jun 2025018766.483.13$585
May 2025018660.553.23$601
Apr 2025022062.363.54$779
Mar 2025015367.704.27$653
Feb 2025014370.884.34$621
Jan 2025019674.324.28$839
Dec 2024028368.993.12$883
Nov 2024024569.052.20$539
Oct 2024019371.372.28$440
Sep 2024013969.612.36$329
Aug 202405575.632.06$114
Jul 202409779.932.15$208
Jun 2024020678.082.63$543
May 2024018978.812.20$416
Apr 2024016184.451.66$267
Mar 2024012880.301.55$198
Feb 2024022876.091.78$407
Jan 2024012573.023.30$412
Dec 2023018871.262.61$491
Nov 2023011277.892.81$314
Oct 2023017885.443.09$550
Sep 202309889.042.74$268
Aug 202306680.522.67$176
Jul 2023013174.852.64$346
Jun 2023012468.962.26$280
May 2023016770.622.23$372
Apr 2023016978.122.24$378
Mar 2023024272.852.39$579
Feb 2023015475.112.47$380
Jan 2023015576.533.39$525
Dec 2022023576.415.73$1,346
Nov 2022019185.005.65$1,078
Oct 2022020787.185.86$1,214
Sep 2022017684.888.16$1,437
Aug 2022015594.529.13$1,415
Jul 20220141101.587.54$1,063
Jun 20220110115.097.98$877
May 20220140109.378.43$1,181
Apr 20220242104.226.84$1,655
Mar 20220144108.885.08$731
Feb 2022020491.054.86$991
Jan 2022017081.844.54$771
Dec 2021027471.323.90$1,068
Nov 2021014277.435.24$744
Oct 2021010079.795.71$571
Sep 2021014269.865.35$760
Aug 202106666.024.22$279
Jul 2021011770.783.98$466
Jun 2021013269.493.38$446
May 202107563.483.02$226
Apr 2021013060.362.76$359
Mar 2021012661.302.72$342
Feb 202103457.805.55$189
Jan 2021014550.412.81$407
Dec 2020020244.642.68$540
Nov 2020017838.772.71$482
Oct 2020025536.972.48$632
Sep 2020012537.091.99$249
Aug 2020015439.982.39$367
Jul 2020024538.371.83$447
Jun 2020014134.901.69$238
May 2020023616.921.81$428
Apr 2020021414.751.80$386
Mar 2020019630.341.86$364
Feb 2020019449.881.98$384
Jan 2020019257.252.09$402
Dec 2019012859.012.30$295
Nov 2019018855.302.75$517
Oct 2019013453.472.42$324
Sep 201905355.052.66$141
Aug 201905053.112.30$115
Jul 201909856.272.46$241
Jun 2019024452.782.49$608
May 2019063458.482.74$1,737
Apr 201901,09162.632.75$3,001
Mar 201901,17056.803.06$3,583
Feb 201901,67450.852.79$4,674
Jan 201901,14446.033.23$3,693
Dec 201801,91846.594.19$8,028
Nov 2018048352.934.24$2,047
Oct 201801,88861.443.40$6,416
Sep 201802,09359.543.11$6,505
Aug 2018010059.403.07$307
Jul 2018068765.142.93$2,014
Jun 201801,55860.183.08$4,794
May 2018041965.382.90$1,215
Apr 201804,83663.842.90$14,028
Mar 201801,45861.222.79$4,063
Feb 2018013361.782.77$368
Jan 2018016062.874.01$641
Dec 2017010157.272.92$295
Nov 2017017255.423.12$536
Oct 2017021049.292.98$627
Sep 2017019547.523.09$602
Aug 2017014245.373.00$427
Jul 2017013443.873.09$414
Jun 2017012242.493.09$377
May 2017033645.373.26$1,097
Apr 2017012347.933.21$395
Mar 2017030446.772.98$907
Feb 2017068450.452.95$2,020
Jan 201702,65849.413.42$9,087
Dec 201602,86948.763.72$10,681
Nov 201602,92742.492.64$7,740
Oct 201604,06446.193.09$12,559
Sep 201604,87041.553.10$15,100
Aug 201604,55841.442.92$13,329
Jul 201608,21341.622.92$24,018
Jun 201602,60545.352.69$6,997
May 2016025742.521.99$512
Apr 2016010836.561.99$215
Mar 2016048533.011.79$870
Feb 20160026.472.06$0
Jan 20160027.352.36$0
Dec 20150032.362.00$0
Nov 20150038.792.17$0
Oct 20150043.552.43$0
Sep 20150042.992.76$0
Aug 2015017040.162.87$488
Jul 2015022448.152.95$660
Jun 2015022956.152.88$660
May 2015018955.212.96$559
Apr 2015025549.822.71$690
Mar 2015056042.892.93$1,643
Feb 2015012944.662.98$384
Jan 2015026343.433.10$815
Dec 2014026054.693.59$934
Nov 2014022770.464.25$965
Oct 2014028778.303.90$1,120
Sep 2014092886.164.05$3,754
Aug 201401,42289.394.04$5,738
Jul 201403,72996.564.18$15,586
Jun 201406,53098.164.74$30,932
May 201404,24694.734.73$20,069
Apr 2014024295.944.81$1,164
Mar 2014026495.895.06$1,335
Feb 2014028697.406.19$1,771
Jan 2014031590.404.86$1,531
Dec 2013030091.824.35$1,306
Nov 2013013988.853.74$520
Oct 2013011697.423.78$438
Sep 20130109104.113.72$405
Aug 2013061104.253.52$215
Jul 20130125102.523.72$465
Jun 201308994.403.93$350
May 201307294.834.15$299
Apr 201306793.964.28$287
Mar 201303593.623.91$137
Feb 201305191.233.42$174
Jan 201305191.603.42$174
Dec 201209886.773.42$335
Nov 2012010586.953.62$381
Oct 2012036489.383.40$1,237
Sep 2012022794.672.92$662
Aug 2012021692.662.91$628
Jul 2012010585.133.02$317
Jun 2012015079.822.52$378
May 2012023991.612.49$595
Apr 20120600101.652.00$1,198
Mar 201200105.052.22$0
Feb 2012093101.102.57$239
Jan 201201,08398.092.73$2,961
Dec 201104,85196.873.24$15,716
Nov 201105,00795.723.31$16,580
Oct 201102,14384.983.65$7,819
Sep 20110083.623.99$0
Aug 201106983.404.15$286
Jul 2011012494.144.52$560
Jun 2011010492.904.64$483
May 201108098.134.40$352
Apr 20110195105.964.33$845
Mar 201106296.364.06$252
Feb 201105385.644.18$222
Jan 20110086.504.59$0
Dec 2010047085.734.35$2,043
Nov 2010020480.843.80$774
Oct 2010114278.103.51$576
Sep 201001,24772.633.98$4,962
Aug 2010073973.684.42$3,266
Jul 2010121,33372.554.74$7,184
Jun 201003,07770.364.91$15,109
May 2010173,60471.124.24$16,473
Apr 201024,96181.694.12$20,616
Mar 201007,17678.394.39$31,493
Feb 201007,61973.585.44$41,465
Jan 201006,24474.365.96$37,240
Dec 200909271.445.48$505
Nov 200909474.593.75$353
Oct 2009014572.544.11$596
Sep 200905165.543.06$156
Aug 2009022067.423.22$708
Jul 2009056661.133.46$1,961
Jun 2009036066.163.90$1,402
May 200906054.743.93$236
Apr 2009018946.773.59$678
Mar 2009014442.144.06$585
Feb 2009015732.814.63$727
Jan 2009015835.865.37$849
Dec 2008017437.105.98$1,040
Nov 2008020155.496.86$1,379
Oct 2008029075.246.92$2,007
Sep 20080340101.767.88$2,678
Aug 20080350114.228.48$2,969
Jul 20080427131.0811.39$4,863
Jun 20080604131.3313.03$7,872
May 200801,798123.1711.57$20,811
Apr 200803,177110.3110.45$33,215
Mar 200802,705101.909.66$26,141
Feb 200803,15592.538.77$27,671
Jan 200804,32690.388.21$35,498
Dec 2007074688.337.30$5,447
Nov 200705,64191.677.29$41,132
Oct 200707,31582.856.92$50,634
Sep 200707,84275.846.24$48,967
Aug 200705,41769.066.39$34,603
Jul 2007047370.906.39$3,022
Jun 200701,20662.007.55$9,103
May 200702,05858.747.85$16,148
Apr 200702,09559.617.81$16,352
Mar 2007031156.927.30$2,271
Feb 2007066755.108.22$5,480
Jan 2007049350.306.73$3,316
Dec 2006037856.656.92$2,615
Nov 2006033654.207.62$2,559
Oct 2006024054.906.01$1,443
Sep 2006018760.085.04$942
Aug 2006020868.717.34$1,527
Jul 2006018369.376.34$1,161
Jun 2006026866.286.38$1,711
May 2006044966.016.42$2,885
Apr 2006048764.397.36$3,585
Mar 2006046256.707.08$3,272
Feb 2006055857.597.75$4,325
Jan 2006047360.598.93$4,225
Dec 2005059454.9413.42$7,969
Nov 2005041054.6910.59$4,341
Oct 2005050358.3413.80$6,939
Sep 2005272161.4512.08$8,832
Aug 2005561261.519.80$6,303
Jul 200561,12355.697.84$9,143
Jun 200501,41352.337.38$10,429
May 20051790945.226.65$6,815
Apr 2005162,49849.207.36$19,174
Mar 2005144,18450.377.15$30,641
Feb 2005252,62945.226.31$17,725
Jan 200502,69943.166.32$17,064
Dec 200402,33839.866.75$15,784
Nov 200403,05545.286.33$19,339
Oct 200401,82649.706.52$11,897
Sep 200401,85343.245.28$9,791
Aug 200403,41042.375.55$18,928
Jul 200405,10138.286.08$31,035
Jun 200403,47236.106.43$22,335
May 200406,03737.486.49$39,208
Apr 200406,05734.475.86$35,485
Mar 200404,39534.365.53$24,305
Feb 20041062232.455.51$3,751
Jan 2004254,76032.036.30$30,787
Dec 2003277,39730.266.30$47,430
Nov 2003224,93928.804.60$23,329
Oct 2003132,82628.174.76$13,817
Sep 2003114,46326.314.75$21,486
Aug 200393,31329.765.13$17,263
Jul 2003125,10129.415.17$26,729
Jun 200302,62328.565.98$15,693
May 200304,35126.595.97$25,987
Apr 200304,13126.675.41$22,337
Mar 200309,41531.146.10$57,394
Feb 2003011,82033.487.93$93,684
Jan 200309,11530.315.58$50,880
Dec 2002142126.914.85$2,070
Nov 2002436124.664.14$1,592
Oct 20022510,98426.464.23$47,114
Sep 20022914,82727.443.64$54,695
Aug 20026427,70225.963.16$89,315
Jul 200212438,84724.583.06$121,988
Jun 200216341,71423.733.34$143,119
May 200216843,41324.663.58$159,735
Apr 200219840,42223.653.51$146,658
Mar 200231454,56622.003.10$176,211
Feb 200229462,79018.222.38$154,526
Jan 200255995,26917.172.38$235,927
Dec 2001666122,07516.932.36$299,910
Nov 200108,46918.072.41$20,372

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                6,340 Mcf  × $  3.05 =    $19,311

────────────────────────────────────────────────────
Month total                                  $19,311

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 04/G/186016 is the state's own key, not one this site invented.