WEBB COUNTY SCHOOL LAND 1384

Operated by LEWIS PETRO PROPERTIES, INC. (P-5 499978) in the OWEN (OLMOS) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 197776District 04Field 678854002 tax incentive programmesCondensateGasSaveExport
Value, all time
$1.1 M
Aug 2003 – May 2026
Value, last 12 filed months
$3 k
at the published price for each month
Months reported
274
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 811 leases and 811 wells, and the rule below applies to all of them.

Discovered
1971-11-11
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2015-03-24.

The Commission's schedule remark for this field reads: LATERALS. EFFECTIVE 3/24/15;

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112004-09-14158507
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition196 bbl$7,419
GasProduction197,798 Mcf$1,135,991
Total$1,143,410

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 28.0727, -99.5363. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

28.07274, -99.53627 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
7,200 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,200 ft.

Completions filed
Aug 2003
1 of 1 wells

1 well

42-4793847857,200 ftAug 2003

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (274)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

274 months

May 2026093106.413.05$283
Apr 2026011198.932.87$319
Mar 2026017689.753.15$554
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 2025018756.664.41$825
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 2025015462.743.08$474
Aug 20250063.933.01$0
Jul 2025011166.743.32$368
Jun 202502466.483.13$75
May 2025015360.553.23$495
Apr 202502362.363.54$81
Mar 2025015367.704.27$653
Feb 20250070.884.34$0
Jan 2025017274.324.28$736
Dec 20240068.993.12$0
Nov 2024016869.052.20$369
Oct 20240071.372.28$0
Sep 2024018369.612.36$433
Aug 20240075.632.06$0
Jul 2024019479.932.15$416
Jun 20240078.082.63$0
May 2024025678.812.20$563
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 202409676.091.78$171
Jan 2024010873.023.30$356
Dec 2023011671.262.61$303
Nov 2023011277.892.81$314
Oct 2023011985.443.09$367
Sep 2023011089.042.74$301
Aug 2023011180.522.67$297
Jul 2023013274.852.64$349
Jun 2023012068.962.26$271
May 2023015870.622.23$352
Apr 2023012178.122.24$271
Mar 2023012872.852.39$306
Feb 2023010675.112.47$261
Jan 2023012376.533.39$417
Dec 2022013776.415.73$785
Nov 2022014885.005.65$836
Oct 2022020187.185.86$1,179
Sep 2022019484.888.16$1,584
Aug 20220094.529.13$0
Jul 2022093101.587.54$701
Jun 20220147115.097.98$1,173
May 20220163109.378.43$1,375
Apr 20220148104.226.84$1,012
Mar 20220154108.885.08$782
Feb 2022016691.054.86$807
Jan 2022012481.844.54$563
Dec 2021015971.323.90$620
Nov 2021015577.435.24$812
Oct 2021017879.795.71$1,017
Sep 2021016969.865.35$904
Aug 2021017566.024.22$739
Jul 2021018670.783.98$741
Jun 2021018069.493.38$609
May 2021018763.483.02$564
Apr 2021018160.362.76$499
Mar 2021018961.302.72$514
Feb 2021016957.805.55$938
Jan 2021017850.412.81$500
Dec 2020018744.642.68$500
Nov 2020018238.772.71$493
Oct 2020018936.972.48$468
Sep 2020019137.091.99$380
Aug 2020019739.982.39$470
Jul 2020019838.371.83$361
Jun 2020018634.901.69$314
May 2020021716.921.81$394
Apr 2020026314.751.80$475
Mar 2020012830.341.86$238
Feb 2020018649.881.98$368
Jan 2020020557.252.09$429
Dec 2019021359.012.30$491
Nov 2019026255.302.75$721
Oct 2019012753.472.42$307
Sep 2019021755.052.66$577
Aug 2019021053.112.30$484
Jul 2019023456.272.46$576
Jun 2019023552.782.49$585
May 2019024758.482.74$677
Apr 2019022462.632.75$616
Mar 2019022856.803.06$698
Feb 2019021350.852.79$595
Jan 2019024046.033.23$775
Dec 2018024746.594.19$1,034
Nov 2018023952.934.24$1,013
Oct 2018023861.443.40$809
Sep 2018023159.543.11$718
Aug 2018024859.403.07$761
Jul 2018025265.142.93$739
Jun 2018026260.183.08$806
May 2018028465.382.90$824
Apr 2018023863.842.90$690
Mar 2018027561.222.79$766
Feb 2018025061.782.77$692
Jan 2018024262.874.01$970
Dec 2017027857.272.92$812
Nov 2017027755.423.12$864
Oct 2017033249.292.98$991
Sep 2017032847.523.09$1,013
Aug 2017033845.373.00$1,015
Jul 2017031643.873.09$976
Jun 2017031342.493.09$966
May 2017033145.373.26$1,080
Apr 2017030447.933.21$976
Mar 2017031046.772.98$925
Feb 2017027750.452.95$818
Jan 2017028249.413.42$964
Dec 2016031248.763.72$1,162
Nov 2016031442.492.64$830
Oct 2016034446.193.09$1,063
Sep 2016032941.553.10$1,020
Aug 2016034041.442.92$994
Jul 2016038541.622.92$1,126
Jun 2016034145.352.69$916
May 2016031842.521.99$633
Apr 2016030436.561.99$605
Mar 2016039533.011.79$709
Feb 2016026026.472.06$537
Jan 2016032127.352.36$759
Dec 2015029332.362.00$586
Nov 2015032138.792.17$696
Oct 2015028243.552.43$684
Sep 2015133242.992.76$959
Aug 2015033340.162.87$957
Jul 2015032048.152.95$942
Jun 2015024056.152.88$692
May 2015033955.212.96$1,002
Apr 2015032649.822.71$882
Mar 2015037542.892.93$1,101
Feb 2015034744.662.98$1,033
Jan 2015039543.433.10$1,225
Dec 2014143154.693.59$1,603
Nov 2014043070.464.25$1,828
Oct 2014034278.303.90$1,334
Sep 2014032486.164.05$1,311
Aug 2014033589.394.04$1,352
Jul 2014034396.564.18$1,434
Jun 2014036498.164.74$1,724
May 2014031594.734.73$1,489
Apr 2014033195.944.81$1,592
Mar 2014036595.895.06$1,846
Feb 2014033297.406.19$2,056
Jan 2014038690.404.86$1,876
Dec 2013033991.824.35$1,476
Nov 2013036488.853.74$1,361
Oct 2013037697.423.78$1,421
Sep 20130354104.113.72$1,316
Aug 20130367104.253.52$1,293
Jul 20130380102.523.72$1,413
Jun 2013038794.403.93$1,522
May 2013038894.834.15$1,610
Apr 2013037293.964.28$1,593
Mar 2013039693.623.91$1,550
Feb 2013035991.233.42$1,228
Jan 2013039691.603.42$1,354
Dec 2012041986.773.42$1,433
Nov 2012044386.953.62$1,606
Oct 2012041189.383.40$1,397
Sep 2012042694.672.92$1,243
Aug 2012043292.662.91$1,256
Jul 2012045385.133.02$1,368
Jun 2012044079.822.52$1,108
May 2012046391.612.49$1,152
Apr 20120469101.652.00$937
Mar 20120499105.052.22$1,109
Feb 20120484101.102.57$1,244
Jan 2012054198.092.73$1,479
Dec 2011054896.873.24$1,775
Nov 2011053995.723.31$1,785
Oct 2011059384.983.65$2,164
Sep 2011056683.623.99$2,256
Aug 2011043683.404.15$1,809
Jul 2011056894.144.52$2,566
Jun 2011053792.904.64$2,492
May 2011058698.134.40$2,581
Apr 20110566105.964.33$2,453
Mar 2011063796.364.06$2,585
Feb 2011055085.644.18$2,299
Jan 2011061286.504.59$2,808
Dec 2010058285.734.35$2,530
Nov 2010062880.843.80$2,383
Oct 2010067278.103.51$2,358
Sep 2010064872.633.98$2,579
Aug 2010069073.684.42$3,049
Jul 2010067872.554.74$3,211
Jun 2010065370.364.91$3,206
May 2010069471.124.24$2,939
Apr 2010066981.694.12$2,758
Mar 2010070378.394.39$3,085
Feb 2010063273.585.44$3,440
Jan 2010067774.365.96$4,038
Dec 2009072471.445.48$3,970
Nov 2009071774.593.75$2,690
Oct 2009073172.544.11$3,005
Sep 2009071965.543.06$2,204
Aug 2009076167.423.22$2,449
Jul 2009078161.133.46$2,706
Jun 2009075366.163.90$2,933
May 2009078254.743.93$3,070
Apr 2009076746.773.59$2,752
Mar 2009081542.144.06$3,308
Feb 2009076632.814.63$3,549
Jan 2009086635.865.37$4,651
Dec 2008085537.105.98$5,110
Nov 2008086455.496.86$5,927
Oct 2008090175.246.92$6,237
Sep 20080870101.767.88$6,853
Aug 20080896114.228.48$7,601
Jul 20080941131.0811.39$10,717
Jun 20080944131.3313.03$12,303
May 20080930123.1711.57$10,764
Apr 20080974110.3110.45$10,183
Mar 200801,003101.909.66$9,693
Feb 2008096292.538.77$8,437
Jan 200801,05290.388.21$8,632
Dec 200701,06888.337.30$7,799
Nov 200701,06991.677.29$7,795
Oct 200701,12082.856.92$7,753
Sep 200701,10475.846.24$6,894
Aug 200701,15569.066.39$7,378
Jul 200701,16870.906.39$7,461
Jun 200701,17362.007.55$8,854
May 200701,21458.747.85$9,525
Apr 200701,07559.617.81$8,391
Mar 200701,24756.927.30$9,106
Feb 200701,09155.108.22$8,964
Jan 200701,26250.306.73$8,489
Dec 200611,28156.656.92$8,919
Nov 200601,26154.207.62$9,606
Oct 200601,32554.906.01$7,968
Sep 200601,31760.085.04$6,634
Aug 200601,42768.717.34$10,474
Jul 2006291,44969.376.34$11,202
Jun 200601,44066.286.38$9,193
May 200601,44966.016.42$9,310
Apr 200601,43464.397.36$10,555
Mar 200601,53256.707.08$10,851
Feb 200601,38157.597.75$10,704
Jan 200601,58360.598.93$14,141
Dec 200501,62154.9413.42$21,746
Nov 200501,63554.6910.59$17,312
Oct 200501,75558.3413.80$24,212
Sep 200501,76361.4512.08$21,295
Aug 200501,90061.519.80$18,614
Jul 200501,93455.697.84$15,170
Jun 200501,94452.337.38$14,349
May 200502,10645.226.65$14,007
Apr 200502,12449.207.36$15,634
Mar 200502,15050.377.15$15,383
Feb 200502,04145.226.31$12,883
Jan 200502,29143.166.32$14,484
Dec 200402,43439.866.75$16,432
Nov 200402,36945.286.33$14,997
Oct 200402,29049.706.52$14,920
Sep 200402,27343.245.28$12,010
Aug 200402,71042.375.55$15,042
Jul 200402,64538.286.08$16,093
Jun 200402,91036.106.43$18,720
May 200403,25837.486.49$21,159
Apr 200403,32134.475.86$19,456
Mar 200403,63634.365.53$20,108
Feb 200403,78532.455.51$20,854
Jan 20041644,20932.036.30$31,768
Dec 200304,20230.266.30$26,479
Nov 200304,69528.804.60$21,574
Oct 200306,00628.174.76$28,586
Sep 200308,03826.314.75$38,175
Aug 200308,69829.765.13$44,618

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                   93 Mcf  × $  3.05 =       $283

────────────────────────────────────────────────────
Month total                                     $283

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 04/G/197776 is the state's own key, not one this site invented.