Operated by WAGNER OIL COMPANY (P-5 891175) in the MESTENA GRANDE (QUEEN CITY CONS) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 233206District 04Field 608235012 tax incentive programmesCondensateGasSaveExport
Value, all time
$1.1 M
Dec 2007 – Mar 2023
Value, last 12 filed months
$0
at the published price for each month
Months reported
184
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 58 leases and 58 wells, and the rule below applies to all of them.

Discovered
2003-07-08
as the register files it
Field class
Gas
the register's own label
Between wells
0 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 80 acres. The field rule took effect on 2003-08-19.

The Commission's schedule remark for this field reads: BETWEEN WELL SPACING.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112009-05-01189893
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition3,424 bbl$291,823
GasProduction127,724 Mcf$827,405
Total$1,119,228

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 27.3170, -98.5529. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

27.31702, -98.55289 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
9,768 ft
1 wells filed one
Completion to plug
14.1 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 9,768 ft.

Completions filed
Feb 2009
1 of 1 wells
Plug dates filed
Mar 2023
1 of 1 wells

Last completion to plug: a median of 14.1 years across the 1 well that filed both dates, with the middle half between 14.1 years and 14.1 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-2473241219,768 ftFeb 2009Mar 2023Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (184)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

184 months

Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20190056.803.06$0
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 20180059.543.11$0
Aug 20180059.403.07$0
Jul 20180065.142.93$0
Jun 20180060.183.08$0
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 20170045.373.00$0
Jul 20170043.873.09$0
Jun 20170042.493.09$0
May 20170045.373.26$0
Apr 20170047.933.21$0
Mar 20170046.772.98$0
Feb 20170050.452.95$0
Jan 20170049.413.42$0
Dec 20160048.763.72$0
Nov 20160042.492.64$0
Oct 20160046.193.09$0
Sep 20160041.553.10$0
Aug 20160041.442.92$0
Jul 20160041.622.92$0
Jun 20160045.352.69$0
May 20160042.521.99$0
Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 20160026.472.06$0
Jan 20160027.352.36$0
Dec 20150032.362.00$0
Nov 20150038.792.17$0
Oct 20150043.552.43$0
Sep 20150042.992.76$0
Aug 201581040.162.87$3,253
Jul 20150048.152.95$0
Jun 2015332056.152.88$1,091
May 2015032655.212.96$963
Apr 2015020549.822.71$555
Mar 2015314942.892.93$566
Feb 2015020744.662.98$616
Jan 2015034043.433.10$1,054
Dec 201418034454.693.59$11,080
Nov 2014140670.464.25$1,797
Oct 201405478.303.90$211
Sep 2014022986.164.05$926
Aug 2014239489.394.04$1,769
Jul 2014039096.564.18$1,630
Jun 2014341798.164.74$2,270
May 2014326694.734.73$1,541
Apr 2014029595.944.81$1,419
Mar 2014434495.895.06$2,123
Feb 2014533697.406.19$2,568
Jan 2014026490.404.86$1,283
Dec 2013131291.824.35$1,450
Nov 2013033588.853.74$1,252
Oct 2013220497.423.78$966
Sep 201365291104.113.72$7,849
Aug 20130283104.253.52$997
Jul 20130351102.523.72$1,305
Jun 2013033094.403.93$1,298
May 2013044494.834.15$1,842
Apr 2013038793.964.28$1,657
Mar 2013062593.623.91$2,446
Feb 2013042791.233.42$1,460
Jan 2013052991.603.42$1,809
Dec 2012063086.773.42$2,155
Nov 2012048986.953.62$1,773
Oct 2012046789.383.40$1,588
Sep 2012047994.672.92$1,398
Aug 2012030692.662.91$890
Jul 2012052685.133.02$1,589
Jun 2012055379.822.52$1,393
May 20127357491.612.49$8,116
Apr 20120585101.652.00$1,168
Mar 20121673105.052.22$1,601
Feb 20123638101.102.57$1,943
Jan 2012168898.092.73$1,979
Dec 2011266796.873.24$2,355
Nov 2011061495.723.31$2,033
Oct 2011164584.983.65$2,438
Sep 2011033083.623.99$1,315
Aug 2011464283.404.15$2,997
Jul 201131,11294.144.52$5,306
Jun 2011288792.904.64$4,301
May 201111,06598.134.40$4,789
Apr 201121,030105.964.33$4,675
Mar 2011194596.364.06$3,931
Feb 201121,03385.644.18$4,489
Jan 2011592886.504.59$4,691
Dec 201001,17885.734.35$5,122
Nov 201011,11480.843.80$4,309
Oct 201011,14878.103.51$4,106
Sep 201001,08172.633.98$4,302
Aug 201011,32273.684.42$5,916
Jul 201021,03472.554.74$5,043
Jun 201031,14270.364.91$5,819
May 201051,38071.124.24$6,200
Apr 201031,53181.694.12$6,557
Mar 20101861,49378.394.39$21,133
Feb 201051,59373.585.44$9,038
Jan 201041,74774.365.96$10,717
Dec 200951,78371.445.48$10,135
Nov 20091631,35674.593.75$17,245
Oct 200941,41172.544.11$6,090
Sep 200971,38065.543.06$4,688
Aug 200931,74867.423.22$5,828
Jul 20091791,81461.133.46$17,227
Jun 200921,91966.163.90$7,607
May 200932,35854.743.93$9,421
Apr 20093362,33046.773.59$24,074
Mar 200962,85342.144.06$11,833
Feb 200953,58832.814.63$16,787
Jan 2009124935.865.37$1,373
Dec 2008521037.105.98$1,441
Nov 20081782,35855.496.86$26,054
Oct 20081854,07275.246.92$42,106
Sep 200813,235101.767.88$25,584
Aug 20081813,784114.228.48$52,774
Jul 20081804,102131.0811.39$70,314
Jun 200884,212131.3313.03$55,944
May 20083524,561123.1711.57$96,146
Apr 20081934,690110.3110.45$70,323
Mar 2008125,334101.909.66$52,771
Feb 20081884,93892.538.77$60,705
Jan 20083788,97390.388.21$107,794
Dec 200718412,39388.337.30$106,746

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Aug 2015 — as filed, then multipliedworked
Condensate            81 bbl  × $ 40.16 =     $3,253
Gas                    0 Mcf  × $  2.87 =         $0

────────────────────────────────────────────────────
Month total                                   $3,253

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 04/G/233206 is the state's own key, not one this site invented.