IRVIN, E.L. GAS UNIT

Operated by XTO ENERGY INC. (P-5 945936) in the TEAGUE (PETTIT B) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 178968District 05Field 88576330CondensateGasSaveExport
Value, all time
$207 k
Aug 2000 – Jun 2012
Value, last 12 filed months
$5 k
at the published price for each month
Months reported
143
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 24 leases and 24 wells, and the rule below applies to all of them.

Discovered
1997-01-03
as the register files it
Field class
Gas
the register's own label
Between wells
no field rule filed
From a lease line
no field rule filed

The Commission's schedule remark for this field reads: PURPOSES.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition3 bbl$69
GasProduction34,836 Mcf$206,432
Total$206,501

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 31.6035, -96.2298. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

31.60353, -96.22983 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
8,168 ft
1 wells filed one
Completion to plug
10.4 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 8,168 ft.

Completions filed
Jan 2002
1 of 1 wells
Plug dates filed
Jun 2012
1 of 1 wells

Last completion to plug: a median of 10.4 years across the 1 well that filed both dates, with the middle half between 10.4 years and 10.4 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-1610053618,168 ftJan 2002Jun 2012Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (143)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

143 months

Jun 20120079.822.52$0
May 2012018191.612.49$450
Apr 20120210101.652.00$419
Mar 20120297105.052.22$660
Feb 20120266101.102.57$684
Jan 2012022398.092.73$610
Dec 2011012096.873.24$389
Nov 2011014495.723.31$477
Oct 2011022984.983.65$836
Sep 2011017883.623.99$709
Aug 201102083.404.15$83
Jul 201102994.144.52$131
Jun 2011011592.904.64$534
May 201108898.134.40$388
Apr 20110120105.964.33$520
Mar 2011020696.364.06$836
Feb 2011022485.644.18$936
Jan 2011023386.504.59$1,069
Dec 2010023785.734.35$1,030
Nov 2010023480.843.80$888
Oct 2010024778.103.51$867
Sep 2010028472.633.98$1,130
Aug 2010024873.684.42$1,096
Jul 2010025072.554.74$1,184
Jun 2010024970.364.91$1,223
May 2010025871.124.24$1,093
Apr 2010024881.694.12$1,022
Mar 2010026178.394.39$1,145
Feb 2010024373.585.44$1,322
Jan 2010027174.365.96$1,616
Dec 2009026371.445.48$1,442
Nov 2009025674.593.75$960
Oct 2009026872.544.11$1,102
Sep 2009026365.543.06$806
Aug 2009027367.423.22$879
Jul 2009029161.133.46$1,008
Jun 2009029766.163.90$1,157
May 2009041154.743.93$1,613
Apr 2009018646.773.59$667
Mar 2009029042.144.06$1,177
Feb 2009026332.814.63$1,218
Jan 2009029635.865.37$1,590
Dec 2008029237.105.98$1,745
Nov 2008030255.496.86$2,072
Oct 2008031275.246.92$2,160
Sep 20080298101.767.88$2,347
Aug 20080314114.228.48$2,664
Jul 20080340131.0811.39$3,872
Jun 20080363131.3313.03$4,731
May 20080762123.1711.57$8,820
Apr 20080327110.3110.45$3,419
Mar 20080394101.909.66$3,808
Feb 2008023392.538.77$2,044
Jan 2008032290.388.21$2,642
Dec 2007031888.337.30$2,322
Nov 2007031791.677.29$2,311
Oct 2007034382.856.92$2,374
Sep 2007036575.846.24$2,279
Aug 2007027269.066.39$1,738
Jul 2007033170.906.39$2,114
Jun 2007029362.007.55$2,212
May 2007027458.747.85$2,150
Apr 2007035859.617.81$2,794
Mar 2007035656.927.30$2,600
Feb 2007027955.108.22$2,292
Jan 2007025850.306.73$1,736
Dec 2006032956.656.92$2,276
Nov 2006042054.207.62$3,199
Oct 2006032554.906.01$1,954
Sep 2006030960.085.04$1,556
Aug 2006038968.717.34$2,855
Jul 2006043069.376.34$2,727
Jun 2006022466.286.38$1,430
May 2006021866.016.42$1,401
Apr 2006020164.397.36$1,479
Mar 2006021356.707.08$1,509
Feb 2006018457.597.75$1,426
Jan 2006020160.598.93$1,796
Dec 2005019054.9413.42$2,549
Nov 2005021854.6910.59$2,308
Oct 2005023658.3413.80$3,256
Sep 2005017761.4512.08$2,138
Aug 2005025761.519.80$2,518
Jul 2005021555.697.84$1,686
Jun 2005021852.337.38$1,609
May 2005036045.226.65$2,394
Apr 2005029049.207.36$2,135
Mar 2005026950.377.15$1,925
Feb 2005025145.226.31$1,584
Jan 2005028643.166.32$1,808
Dec 2004028239.866.75$1,904
Nov 2004027345.286.33$1,728
Oct 2004025449.706.52$1,655
Sep 2004021343.245.28$1,125
Aug 2004042142.375.55$2,337
Jul 2004024938.286.08$1,515
Jun 2004020736.106.43$1,332
May 2004032137.486.49$2,085
Apr 2004033034.475.86$1,933
Mar 2004024934.365.53$1,377
Feb 2004019432.455.51$1,069
Jan 2004021632.036.30$1,361
Dec 2003016330.266.30$1,027
Nov 2003027328.804.60$1,254
Oct 200302228.174.76$105
Sep 2003017526.314.75$831
Aug 2003029529.765.13$1,513
Jul 2003048329.415.17$2,498
Jun 2003023228.565.98$1,388
May 2003019826.595.97$1,183
Apr 2003021026.675.41$1,136
Mar 2003034831.146.10$2,121
Feb 2003020433.487.93$1,617
Jan 2003039730.315.58$2,216
Dec 2002042526.914.85$2,063
Nov 2002055324.664.14$2,288
Oct 2002026626.464.23$1,125
Sep 2002019327.443.64$702
Aug 2002015825.963.16$500
Jul 20021024.583.06$25
Jun 2002017423.733.34$581
May 2002034324.663.58$1,229
Apr 2002044823.653.51$1,574
Mar 2002298222.003.10$3,091
Feb 2002098018.222.38$2,328
Jan 2002040217.172.38$955
Dec 20010016.932.36$0
Nov 20010018.072.41$0
Oct 20010019.782.53$0
Sep 20010024.262.25$0
Aug 20010024.873.05$0
Jul 20010023.933.20$0
Jun 20010024.563.82$0
May 20010025.524.31$0
Apr 20010024.685.34$0
Mar 20010024.545.38$0
Feb 20010027.755.77$0
Jan 20010027.478.40$0
Dec 20000026.889.12$0
Nov 20000032.215.66$0
Oct 20000031.235.15$0
Sep 20000031.875.19$0
Aug 20000029.644.54$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2012 — as filed, then multipliedworked
Condensate             0 bbl  × $ 91.61 =         $0
Gas                  181 Mcf  × $  2.49 =       $450

────────────────────────────────────────────────────
Month total                                     $450

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 05/G/178968 is the state's own key, not one this site invented.