HALL

Operated by ROSBOTTOM PRODUCTION CORP (P-5 727740) in the LONGWOOD (TRAVIS PEAK) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 137482District 06Field 54807800CondensateGasSaveExport
Value, all time
$17 k
Jan 1993 – Jan 2002
Value, last 12 filed months
$2 k
at the published price for each month
Months reported
109
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 30 leases and 31 wells, and the rule below applies to all of them.

Discovered
1951-11-16
as the register files it
Field class
Oil and gas
the register's own label
Between wells
933 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 80 acres. The field rule took effect on 1990-02-26.

The Commission's schedule remark for this field reads: AOF-1 AND AOF-2 EFFECTIVE 11/01/96.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition78 bbl$1,940
GasProduction6,616 Mcf$15,185
Total$17,125

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.6200, -94.0548. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.62000, -94.05482 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
6,400 ft
1 wells filed one
Completion to plug
4.4 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 6,400 ft.

Completions filed
Feb 1997
1 of 1 wells
Plug dates filed
Jul 2001
1 of 1 wells

Last completion to plug: a median of 4.4 years across the 1 well that filed both dates, with the middle half between 4.4 years and 4.4 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-2033186516,400 ftFeb 1997Jul 2001Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (109)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

109 months

Jan 20020017.172.38$0
Dec 20010016.932.36$0
Nov 20010018.072.41$0
Oct 20010019.782.53$0
Sep 20010024.262.25$0
Aug 200178024.873.05$1,940
Jul 20010023.933.20$0
Jun 20010024.563.82$0
May 20010025.524.31$0
Apr 20010024.685.34$0
Mar 20010024.545.38$0
Feb 20010027.755.77$0
Jan 20010027.478.40$0
Dec 20000526.889.12$46
Nov 20000632.215.66$34
Oct 200001331.235.15$67
Sep 200003731.875.19$192
Aug 20000029.644.54$0
Jul 20000028.534.09$0
Jun 20000229.304.40$9
May 20000027.263.68$0
Apr 20000324.513.12$9
Mar 20000028.422.86$0
Feb 20000027.622.73$0
Jan 20000025.272.48$0
Dec 19990024.282.42$0
Nov 19990023.192.43$0
Oct 19990020.982.80$0
Sep 199904221.752.62$110
Aug 19990019.262.88$0
Jul 19990017.892.37$0
Jun 19990015.942.36$0
May 19990015.792.32$0
Apr 1999019515.102.21$431
Mar 199901012.471.84$18
Feb 19990629.981.82$113
Jan 199903610.381.90$68
Dec 1998009.201.77$0
Nov 199801410.892.19$31
Oct 19980512.421.97$10
Sep 199804912.592.08$102
Aug 19980011.301.91$0
Jul 199806811.742.24$152
Jun 199806711.242.24$150
May 199808512.622.21$188
Apr 1998012813.042.51$321
Mar 199807312.802.31$169
Feb 19980013.952.30$0
Jan 199805614.702.15$121
Dec 1997028216.322.41$680
Nov 199701318.193.09$40
Oct 199705219.253.15$164
Sep 1997020817.742.95$615
Aug 1997027917.862.55$713
Jul 1997088417.582.25$1,986
Jun 1997073017.242.26$1,648
May 199701,88818.972.31$4,358
Apr 1997052417.882.08$1,091
Mar 1997080018.951.94$1,551
Feb 19970020.492.21$0
Jan 19970023.483.54$0
Dec 19960023.32$0
Nov 19960021.97$0
Oct 19960023.31$0
Sep 19960022.22$0
Aug 19960020.26$0
Jul 19960019.55$0
Jun 19960018.73$0
May 19960019.43$0
Apr 19960021.51$0
Mar 19960019.38$0
Feb 19960016.98$0
Jan 19960017.07$0
Dec 19950017.19$0
Nov 19950016.00$0
Oct 19950015.43$0
Sep 19950016.18$0
Aug 19950015.92$0
Jul 19950015.24$0
Jun 19950016.41$0
May 19950017.56$0
Apr 19950017.73$0
Mar 19950016.44$0
Feb 19950016.58$0
Jan 19950015.92$0
Dec 19940015.03$0
Nov 19940015.90$0
Oct 19940015.58$0
Sep 19940015.29$0
Aug 19940016.13$0
Jul 19940017.56$0
Jun 19940017.09$0
May 19940015.88$0
Apr 19940014.14$0
Mar 19940012.46$0
Feb 19940012.50$0
Jan 19940012.66$0
Dec 19930012.33$0
Nov 19930014.49$0
Oct 19930015.85$0
Sep 19930015.03$0
Aug 19930015.66$0
Jul 19930015.46$0
Jun 19930016.79$0
May 19930017.68$0
Apr 19930018.05$0
Mar 19930018.14$0
Feb 19930017.90$0
Jan 19930016.93$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Aug 2001 — as filed, then multipliedworked
Condensate            78 bbl  × $ 24.87 =     $1,940
Gas                    0 Mcf  × $  3.05 =         $0

────────────────────────────────────────────────────
Month total                                   $1,940

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/137482 is the state's own key, not one this site invented.