POOLE

Operated by VALENCE OPERATING COMPANY (P-5 881167) in the MARTHA ANN (TRAVIS PEAK) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 142226District 06Field 577624002 tax incentive programmesCondensateGasSaveExport
Value, all time
$969 k
Jan 1993 – Jun 2007
Value, last 12 filed months
$0
at the published price for each month
Months reported
174
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 4 leases and 4 wells, and the rule below applies to all of them.

Discovered
1990-04-25
as the register files it
Field class
Oil and gas
the register's own label
Between wells
2,640 ft
minimum
From a lease line
1,320 ft
minimum

A drilling unit in this field needs at least 320 acres. The field rule took effect on 1992-11-23.

The Commission's schedule remark for this field reads: ALLOCATION FORMULA SUSPENDED ADMINISTRATIVELY EFF. 5-1-95.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas111992-12-31124564
NGPA2none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition13,997 bbl$259,514
GasProduction632,037 Mcf$709,170
Total$968,684

405,750 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.1499, -95.0483. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.14991, -95.04828 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
8,390 ft
1 wells filed one
Completion to plug
1 well filed both, dated out of order

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 8,390 ft.

Completions filed
Mar 2016
1 of 1 wells
Plug dates filed
Aug 1989
1 of 1 wells

Last completion to plug: no median is published. 1 well on this lease filed both dates, and on that one the last completion is dated after the plug date, so there is no interval to take a median of. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-4233120718,390 ftMar 2016Aug 1989Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (174)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

174 months

Jun 20070062.007.55$0
May 20070058.747.85$0
Apr 20070059.617.81$0
Mar 20070056.927.30$0
Feb 20070055.108.22$0
Jan 20070050.306.73$0
Dec 20060056.656.92$0
Nov 20060054.207.62$0
Oct 20060054.906.01$0
Sep 20060060.085.04$0
Aug 20060068.717.34$0
Jul 20060069.376.34$0
Jun 20060066.286.38$0
May 20060066.016.42$0
Apr 20060064.397.36$0
Mar 20060056.707.08$0
Feb 20060057.597.75$0
Jan 20060060.598.93$0
Dec 20050054.9413.42$0
Nov 200501354.6910.59$138
Oct 200502758.3413.80$372
Sep 20050061.4512.08$0
Aug 20050061.519.80$0
Jul 200509455.697.84$737
Jun 200505252.337.38$384
May 200509645.226.65$639
Apr 2005020549.207.36$1,509
Mar 2005079850.377.15$5,710
Feb 2005084545.226.31$5,334
Jan 2005892543.166.32$6,193
Dec 2004033439.866.75$2,255
Nov 2004045145.286.33$2,855
Oct 2004101,85149.706.52$12,556
Sep 200401,62643.245.28$8,592
Aug 200408242.375.55$455
Jul 2004092738.286.08$5,640
Jun 200422,11036.106.43$13,646
May 2004511,54337.486.49$11,933
Apr 2004411,45434.475.86$9,931
Mar 2004371,62034.365.53$10,230
Feb 2004371,48532.455.51$9,382
Jan 2004391,15732.036.30$8,538
Dec 2003251,90430.266.30$12,755
Nov 2003325028.804.60$1,235
Oct 2003145228.174.76$642
Sep 2003491,48026.314.75$8,318
Aug 2003221,67029.765.13$9,221
Jul 20031241,39329.415.17$10,850
Jun 200321,25028.565.98$7,536
May 2003316226.595.97$1,047
Apr 20031418826.675.41$1,390
Mar 2003361,28131.146.10$8,930
Feb 2003441,36933.487.93$12,324
Jan 2003341,95130.315.58$11,921
Dec 20023296926.914.85$5,564
Nov 20021320424.664.14$1,165
Oct 200221081726.464.23$9,012
Sep 200281,91627.443.64$7,185
Aug 200272,01225.963.16$6,548
Jul 200292,14224.583.06$6,780
Jun 20023022,58623.733.34$15,799
May 2002102,72724.663.58$10,020
Apr 20021872,60523.653.51$13,572
Mar 2002102,58622.003.10$8,244
Feb 2002112,75018.222.38$6,734
Jan 2002122,98317.172.38$7,293
Dec 2001132,68216.932.36$6,561
Nov 200141,18418.072.41$2,920
Oct 200192,38519.782.53$6,209
Sep 2001102,74424.262.25$6,420
Aug 20011842,94424.873.05$13,565
Jul 2001122,36723.933.20$7,855
Jun 200161,08624.563.82$4,300
May 200101025.524.31$43
Apr 200101024.685.34$53
Mar 200111924.545.38$127
Feb 2001323127.755.77$1,415
Jan 2001311827.478.40$1,073
Dec 20001026.889.12$27
Nov 200062,55932.215.66$14,672
Oct 2000486131.235.15$4,555
Sep 20001912,10031.875.19$16,979
Aug 200042,24729.644.54$10,322
Jul 200052,57928.534.09$10,690
Jun 20001891,04629.304.40$10,137
May 200043,42927.263.68$12,727
Apr 200043,06224.513.12$9,639
Mar 200043,32728.422.86$9,628
Feb 20001953,25827.622.73$14,269
Jan 200042,80425.272.48$7,056
Dec 199952,56024.282.42$6,326
Nov 199942,27123.192.43$5,620
Oct 199921,24820.982.80$3,541
Sep 199911,31521.752.62$3,466
Aug 19993591,83919.262.88$12,203
Jul 199973,10117.892.37$7,482
Jun 199983,75215.942.36$8,990
May 199973,75815.792.32$8,833
Apr 19991994,20415.102.21$12,288
Mar 199963,30812.471.84$6,156
Feb 199964,0119.981.82$7,351
Jan 199954,15910.381.90$7,954
Dec 199842,8679.201.77$5,121
Nov 199854,05010.892.19$8,907
Oct 19981842,95212.421.97$8,098
Sep 199843,76212.592.08$7,885
Aug 199873,47211.301.91$6,701
Jul 199873,51111.742.24$7,937
Jun 19983612,90511.242.24$10,557
May 199873,93912.622.21$8,779
Apr 199873,88813.042.51$9,832
Mar 19981933,58312.802.31$10,745
Feb 199873,43013.952.30$7,984
Jan 199864,72414.702.15$10,267
Dec 199764,20616.322.41$10,239
Nov 199783,71418.193.09$11,615
Oct 199784,33819.253.15$13,818
Sep 19971954,04517.742.95$15,412
Aug 199783,74817.862.55$9,718
Jul 199764,44517.582.25$10,093
Jun 199753,76317.242.26$8,580
May 19973314,21718.972.31$16,014
Apr 199774,86117.882.08$10,250
Mar 199764,33218.951.94$8,514
Feb 199763,89620.492.21$8,717
Jan 19971974,11923.483.54$19,206
Dec 19961993,96723.32$4,641
Nov 19962013,84421.97$4,416
Oct 199674,48523.31$163
Sep 199674,07822.22$156
Aug 199675,41520.26$142
Jul 19963565,66119.55$6,960
Jun 199686,65818.73$150
May 1996117,38719.43$214
Apr 19961977,23521.51$4,237
Mar 19961956,33619.38$3,779
Feb 19962042,94216.98$3,464
Jan 199634217.07$51
Dec 1995252517.19$34
Nov 1995277816.00$32
Oct 199555,37915.43$77
Sep 199566,17316.18$97
Aug 199563,69415.92$96
Jul 19951901,10115.24$2,896
Jun 199554,12916.41$82
May 199506,50117.56$0
Apr 19951903,71417.73$3,369
Mar 19951935,92616.44$3,173
Feb 199503,00116.58$0
Jan 19951957,07615.92$3,104
Dec 199405,51115.03$0
Nov 19943506,20815.90$5,565
Oct 199408,95215.58$0
Sep 19943498,27915.29$5,336
Aug 199408,74016.13$0
Jul 19942085,54417.56$3,652
Jun 19943202,09117.09$5,469
May 199407,71015.88$0
Apr 19945698,75214.14$8,046
Mar 199407,27912.46$0
Feb 199402,07112.50$0
Jan 199401,70412.66$0
Dec 19933574,23312.33$4,402
Nov 199335711,79314.49$5,173
Oct 1993016,41815.85$0
Sep 199335819,88815.03$5,381
Aug 199339121,02615.66$6,123
Jul 199369923,97315.46$10,807
Jun 199335321,36516.79$5,927
May 199335521,44817.68$6,276
Apr 199370621,18218.05$12,743
Mar 199371021,55318.14$12,879
Feb 199335820,53717.90$6,408
Jan 199392223,44616.93$15,609

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Nov 2005 — as filed, then multipliedworked
Condensate             0 bbl  × $ 54.69 =         $0
Gas                   13 Mcf  × $ 10.59 =       $138

────────────────────────────────────────────────────
Month total                                     $138

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well