DUNN, MARY

Operated by FIDELITY EXPLOR. & PROD. CO. (P-5 266782) in the MINDEN (TRAVIS PEAK CONS.) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 166582District 06Field 61792380CondensateGasSaveExport
Value, all time
$308 k
Aug 1997 – Feb 2012
Value, last 12 filed months
$0
at the published price for each month
Months reported
175
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 304 leases and 325 wells, and the rule below applies to all of them.

Discovered
2006-03-28
as the register files it
Field class
Oil and gas
the register's own label
Between wells
660 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2008-11-12.

The Commission's schedule remark for this field reads: EFF. 11-12-08. ALLOCATION FORMULA REMAINS SUSPENDED.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition997 bbl$22,345
GasProduction93,786 Mcf$286,034
Total$308,379

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.0169, -94.6547. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.01690, -94.65474 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
7,465 ft
1 wells filed one
Completion to plug
14.5 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,465 ft.

Completions filed
Aug 1997
1 of 1 wells
Plug dates filed
Feb 2012
1 of 1 wells

Last completion to plug: a median of 14.5 years across the 1 well that filed both dates, with the middle half between 14.5 years and 14.5 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-4010033317,465 ftAug 1997Feb 2012Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (175)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

175 months

Feb 201200101.102.57$0
Jan 20120098.092.73$0
Dec 20110096.873.24$0
Nov 20110095.723.31$0
Oct 20110084.983.65$0
Sep 20110083.623.99$0
Aug 20110083.404.15$0
Jul 20110094.144.52$0
Jun 20110092.904.64$0
May 20110098.134.40$0
Apr 201100105.964.33$0
Mar 20110096.364.06$0
Feb 201169085.644.18$5,909
Jan 20110086.504.59$0
Dec 20100085.734.35$0
Nov 20100080.843.80$0
Oct 20100078.103.51$0
Sep 20100072.633.98$0
Aug 20100073.684.42$0
Jul 20100072.554.74$0
Jun 20100070.364.91$0
May 20100071.124.24$0
Apr 20100081.694.12$0
Mar 20100078.394.39$0
Feb 20100073.585.44$0
Jan 20100074.365.96$0
Dec 20090071.445.48$0
Nov 20090074.593.75$0
Oct 200903972.544.11$160
Sep 200908165.543.06$248
Aug 200906667.423.22$212
Jul 200908061.133.46$277
Jun 200909066.163.90$351
May 200907254.743.93$283
Apr 200909646.773.59$344
Mar 2009011642.144.06$471
Feb 2009012532.814.63$579
Jan 200906335.865.37$338
Dec 20080037.105.98$0
Nov 20080055.496.86$0
Oct 200807375.246.92$505
Sep 2008053101.767.88$417
Aug 2008032114.228.48$271
Jul 2008053131.0811.39$604
Jun 2008044131.3313.03$573
May 20081119123.1711.57$1,501
Apr 2008070110.3110.45$732
Mar 2008039101.909.66$377
Feb 200808492.538.77$737
Jan 200805590.388.21$451
Dec 200703788.337.30$270
Nov 200707891.677.29$569
Oct 2007010482.856.92$720
Sep 20070075.846.24$0
Aug 200705269.066.39$332
Jul 200708470.906.39$537
Jun 2007021962.007.55$1,653
May 200706558.747.85$510
Apr 2007011359.617.81$882
Mar 2007014556.927.30$1,059
Feb 200705455.108.22$444
Jan 200701950.306.73$128
Dec 2006013756.656.92$948
Nov 2006010154.207.62$769
Oct 200606854.906.01$409
Sep 200608860.085.04$443
Aug 200607968.717.34$580
Jul 200609569.376.34$603
Jun 200605666.286.38$358
May 2006010966.016.42$700
Apr 2006015264.397.36$1,119
Mar 200604656.707.08$326
Feb 2006015257.597.75$1,178
Jan 2006017660.598.93$1,572
Dec 2005015554.9413.42$2,079
Nov 2005056654.6910.59$5,993
Oct 2005028758.3413.80$3,959
Sep 20050061.4512.08$0
Aug 20050061.519.80$0
Jul 20050055.697.84$0
Jun 20050052.337.38$0
May 20050045.226.65$0
Apr 20050049.207.36$0
Mar 20050050.377.15$0
Feb 20050045.226.31$0
Jan 20050043.166.32$0
Dec 20040039.866.75$0
Nov 20040045.286.33$0
Oct 20040049.706.52$0
Sep 20040043.245.28$0
Aug 20040042.375.55$0
Jul 20040038.286.08$0
Jun 20040036.106.43$0
May 20040037.486.49$0
Apr 20040034.475.86$0
Mar 20040034.365.53$0
Feb 20040032.455.51$0
Jan 20040032.036.30$0
Dec 20030030.266.30$0
Nov 20030028.804.60$0
Oct 20030028.174.76$0
Sep 20030026.314.75$0
Aug 20030029.765.13$0
Jul 20030029.415.17$0
Jun 20030028.565.98$0
May 20030026.595.97$0
Apr 20030026.675.41$0
Mar 20030031.146.10$0
Feb 20030033.487.93$0
Jan 20030030.315.58$0
Dec 20020026.914.85$0
Nov 20020024.664.14$0
Oct 20020026.464.23$0
Sep 20020027.443.64$0
Aug 20020025.963.16$0
Jul 20020024.583.06$0
Jun 200279023.733.34$1,875
May 20020024.663.58$0
Apr 20020023.653.51$0
Mar 20020022.003.10$0
Feb 20020018.222.38$0
Jan 20020017.172.38$0
Dec 20010016.932.36$0
Nov 20010018.072.41$0
Oct 2001030719.782.53$776
Sep 2001043124.262.25$970
Aug 20013422424.873.05$1,529
Jul 2001023523.933.20$751
Jun 2001034924.563.82$1,335
May 20019118325.524.31$3,111
Apr 2001014724.685.34$784
Mar 2001018324.545.38$984
Feb 2001020327.755.77$1,171
Jan 2001050927.478.40$4,275
Dec 2000039226.889.12$3,576
Nov 2000058332.215.66$3,299
Oct 2000095531.235.15$4,914
Sep 2000024031.875.19$1,245
Aug 2000023629.644.54$1,072
Jul 2000037928.534.09$1,550
Jun 200001,50329.304.40$6,609
May 20000027.263.68$0
Apr 200001,35524.513.12$4,222
Mar 200001,38428.422.86$3,958
Feb 2000901,08427.622.73$5,441
Jan 200001,11825.272.48$2,773
Dec 199901,21724.282.42$2,950
Nov 199901,22023.192.43$2,969
Oct 199901,51920.982.80$4,259
Sep 199901,28621.752.62$3,368
Aug 199901,68119.262.88$4,834
Jul 199901,65117.892.37$3,917
Jun 19991072,03115.942.36$6,503
May 199902,10515.792.32$4,886
Apr 199902,12615.102.21$4,694
Mar 199902,22612.471.84$4,092
Feb 199902,0449.981.82$3,716
Jan 1999083110.381.90$1,579
Dec 199802,9259.201.77$5,187
Nov 1998033010.892.19$721
Oct 199801012.421.97$20
Sep 199817534512.592.08$2,922
Aug 199801,39911.301.91$2,668
Jul 199802,43611.742.24$5,450
Jun 199802,82711.242.24$6,325
May 199802,98012.622.21$6,575
Apr 19981714,67613.042.51$13,945
Mar 199802,31912.802.31$5,356
Feb 1998075313.952.30$1,731
Jan 19981801,35714.702.15$5,570
Dec 199702,87116.322.41$6,922
Nov 199704,67618.193.09$14,441
Oct 1997013,00719.253.15$40,970
Sep 1997014,25117.742.95$42,110
Aug 19970017.862.55$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Feb 2011 — as filed, then multipliedworked
Condensate            69 bbl  × $ 85.64 =     $5,909
Gas                    0 Mcf  × $  4.18 =         $0

────────────────────────────────────────────────────
Month total                                   $5,909

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/166582 is the state's own key, not one this site invented.