ABNEY, R. K.

Operated by BROOKSTON ENERGY, INC. (P-5 97353) in the WASKOM (TRAVIS PEAK 7) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 198003District 06Field 95369872CondensateGasSaveExport
Value, all time
$6.6 M
Oct 2003 – May 2026
Value, last 12 filed months
$132 k
at the published price for each month
Months reported
272
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 64 leases and 64 wells, and the rule below applies to all of them.

Discovered
1987-08-07
as the register files it
Field class
Gas
the register's own label
Between wells
no field rule filed
From a lease line
no field rule filed

The Commission's schedule remark for this field reads: EFFECTIVE AUGUST.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition1,427 bbl$77,522
GasProduction1,001,772 Mcf$6,564,073
Total$6,641,594

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.4231, -94.1039. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.42311, -94.10390 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
6,500 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 6,500 ft.

Completions filed
Oct 2003
1 of 1 wells

1 well

42-2033124936,500 ftOct 2003

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (272)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

272 months

May 202602,836106.413.05$8,638
Apr 202602,65998.932.87$7,631
Mar 202603,03889.753.15$9,568
Feb 202602,71263.503.75$10,171
Jan 202603,17759.138.00$25,409
Dec 202502,97556.664.41$13,130
Nov 202502,95758.593.93$11,610
Oct 202503,33259.383.30$11,012
Sep 202503,34562.743.08$10,292
Aug 202501,69663.933.01$5,113
Jul 202502,57466.743.32$8,533
Jun 202503,52666.483.13$11,032
May 2025018460.553.23$595
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20190056.803.06$0
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 20180059.543.11$0
Aug 20180059.403.07$0
Jul 20180065.142.93$0
Jun 20180060.183.08$0
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 20170045.373.00$0
Jul 20170043.873.09$0
Jun 20170042.493.09$0
May 20170045.373.26$0
Apr 20170047.933.21$0
Mar 20170046.772.98$0
Feb 20170050.452.95$0
Jan 20170049.413.42$0
Dec 20160048.763.72$0
Nov 20160042.492.64$0
Oct 20160046.193.09$0
Sep 20160041.553.10$0
Aug 20160041.442.92$0
Jul 20160041.622.92$0
Jun 20160045.352.69$0
May 20160042.521.99$0
Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 20160026.472.06$0
Jan 20160027.352.36$0
Dec 20150032.362.00$0
Nov 20150038.792.17$0
Oct 20150043.552.43$0
Sep 20150042.992.76$0
Aug 20150040.162.87$0
Jul 20150048.152.95$0
Jun 20150056.152.88$0
May 20150055.212.96$0
Apr 20150049.822.71$0
Mar 20150042.892.93$0
Feb 20150044.662.98$0
Jan 20150043.433.10$0
Dec 20140054.693.59$0
Nov 20140070.464.25$0
Oct 20140078.303.90$0
Sep 20140086.164.05$0
Aug 20140089.394.04$0
Jul 20140096.564.18$0
Jun 20140098.164.74$0
May 20140094.734.73$0
Apr 20140095.944.81$0
Mar 20140095.895.06$0
Feb 20140097.406.19$0
Jan 20141190.404.86$95
Dec 20130091.824.35$0
Nov 20130088.853.74$0
Oct 20130097.423.78$0
Sep 201300104.113.72$0
Aug 201300104.253.52$0
Jul 201300102.523.72$0
Jun 20130094.403.93$0
May 20130094.834.15$0
Apr 2013251493.964.28$2,409
Mar 20130093.623.91$0
Feb 20130091.233.42$0
Jan 20130091.603.42$0
Dec 20120086.773.42$0
Nov 20120086.953.62$0
Oct 20120089.383.40$0
Sep 20120094.672.92$0
Aug 20120092.662.91$0
Jul 20120085.133.02$0
Jun 20120079.822.52$0
May 2012121091.612.49$11,085
Apr 201200101.652.00$0
Mar 201200105.052.22$0
Feb 201200101.102.57$0
Jan 20120098.092.73$0
Dec 20110096.873.24$0
Nov 20110095.723.31$0
Oct 20110084.983.65$0
Sep 20110083.623.99$0
Aug 201103883.404.15$158
Jul 201107894.144.52$352
Jun 2011024792.904.64$1,146
May 2011823498.134.40$1,816
Apr 20110187105.964.33$810
Mar 2011023496.364.06$949
Feb 2011029385.644.18$1,225
Jan 2011035386.504.59$1,620
Dec 2010036885.734.35$1,600
Nov 2010033180.843.80$1,256
Oct 2010035478.103.51$1,242
Sep 2010035772.633.98$1,421
Aug 2010038873.684.42$1,715
Jul 2010043672.554.74$2,065
Jun 2010039570.364.91$1,940
May 2010049371.124.24$2,088
Apr 2010047781.694.12$1,967
Mar 2010048778.394.39$2,137
Feb 2010344673.585.44$2,648
Jan 2010053274.365.96$3,173
Dec 2009069071.445.48$3,784
Nov 2009066774.593.75$2,502
Oct 2009076072.544.11$3,124
Sep 2009071265.543.06$2,182
Aug 2009077567.423.22$2,494
Jul 2009079961.133.46$2,768
Jun 2009082666.163.90$3,217
May 2009091654.743.93$3,596
Apr 2009076546.773.59$2,744
Mar 200901,29442.144.06$5,252
Feb 200901,06632.814.63$4,939
Jan 2009053435.865.37$2,868
Dec 2008070537.105.98$4,214
Nov 2008059755.496.86$4,096
Oct 200801,57875.246.92$10,923
Sep 200805,989101.767.88$47,176
Aug 200803,938114.228.48$33,406
Jul 200805,495131.0811.39$62,585
Jun 200806,904131.3313.03$89,977
May 200807,417123.1711.57$85,847
Apr 200803,021110.3110.45$31,584
Mar 200803,569101.909.66$34,491
Feb 200807,10392.538.77$62,297
Jan 2008012,29290.388.21$100,865
Dec 200714415,94088.337.30$129,113
Nov 2007015891.677.29$1,152
Oct 2007018,71682.856.92$129,552
Sep 2007015,56275.846.24$97,172
Aug 2007013,27469.066.39$84,794
Jul 2007016,25370.906.39$103,823
Jun 200707,00162.007.55$52,847
May 20070058.747.85$0
Apr 20070059.617.81$0
Mar 20070056.927.30$0
Feb 2007035355.108.22$2,900
Jan 2007091350.306.73$6,142
Dec 200603,63656.656.92$25,155
Nov 200603,29954.207.62$25,130
Oct 200603,41054.906.01$20,507
Sep 200603,76660.085.04$18,970
Aug 200603,72568.717.34$27,341
Jul 200603,91269.376.34$24,813
Jun 200604,36966.286.38$27,891
May 200605,26566.016.42$33,828
Apr 200606,15064.397.36$45,267
Mar 200606,77856.707.08$48,008
Feb 200607,12157.597.75$55,196
Jan 200607,74460.598.93$69,180
Dec 200508,15154.9413.42$109,349
Nov 2005808,41654.6910.59$93,487
Oct 200509,38058.3413.80$129,404
Sep 200508,78161.4512.08$106,066
Aug 2005010,76561.519.80$105,463
Jul 2005012,42255.697.84$97,434
Jun 2005012,03852.337.38$88,853
May 200518215,65045.226.65$112,321
Apr 2005021,18249.207.36$155,910
Mar 2005025,60350.377.15$183,186
Feb 200518824,51445.226.31$163,232
Jan 2005025,18143.166.32$159,199
Dec 200419327,37539.866.75$192,504
Nov 20047127,75145.286.33$178,890
Oct 200416830,55549.706.52$207,418
Sep 2004032,15143.245.28$169,883
Aug 200417038,73442.375.55$222,202
Jul 20043233,60838.286.08$205,702
Jun 20044130,89136.106.43$200,203
May 2004037,00137.486.49$240,306
Apr 2004038,83634.475.86$227,519
Mar 2004042,54834.365.53$235,296
Feb 2004043,46732.455.51$239,487
Jan 2004051,28532.036.30$323,077
Dec 2003052,98030.266.30$333,861
Nov 2003054,55628.804.60$250,694
Oct 2003020,44028.174.76$97,287

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                2,836 Mcf  × $  3.05 =     $8,638

────────────────────────────────────────────────────
Month total                                   $8,638

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/198003 is the state's own key, not one this site invented.