Operated by PROLINE ENERGY RESOURCES INC (P-5 681327) in the BECKVILLE (TRAVIS PEAK) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 222183District 06Field 066495002 tax incentive programmesCondensateGasSaveExport
Value, all time
$2.0 M
Jun 2006 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
240
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 74 leases and 74 wells, and the rule below applies to all of them.

Discovered
1979-10-26
as the register files it
Field class
Oil and gas
the register's own label
Between wells
660 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2011-01-13.

The Commission's schedule remark for this field reads: NO MAXIMUM DIAGONAL, CORRELATIVE INTERVAL 6820-8770 FT.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112009-07-10192313
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition1,984 bbl$141,362
GasProduction283,374 Mcf$1,811,762
Total$1,953,124

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.1525, -94.6310. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.15250, -94.63098 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
10,580 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 10,580 ft.

Completions filed
Jun 2006
1 of 1 wells

1 well

42-401335731-U10,580 ftJun 2006

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (240)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

240 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240484.451.66$7
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 202101279.795.71$69
Sep 20210769.865.35$37
Aug 202103266.024.22$135
Jul 202102070.783.98$80
Jun 202101769.493.38$57
May 202101363.483.02$39
Apr 202108660.362.76$237
Mar 20210261.302.72$5
Feb 202103057.805.55$166
Jan 202101850.412.81$51
Dec 202007244.642.68$193
Nov 202004838.772.71$130
Oct 2020012236.972.48$302
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200138.371.83$2
Jun 202003234.901.69$54
May 202004216.921.81$76
Apr 202005014.751.80$90
Mar 202001230.341.86$22
Feb 202002049.881.98$40
Jan 202002357.252.09$48
Dec 201902359.012.30$53
Nov 201901355.302.75$36
Oct 20190253.472.42$5
Sep 201901255.052.66$32
Aug 201903153.112.30$71
Jul 20190756.272.46$17
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190962.632.75$25
Mar 20190856.803.06$25
Feb 201901050.852.79$28
Jan 201901946.033.23$61
Dec 201802046.594.19$84
Nov 20180752.934.24$30
Oct 20180661.443.40$20
Sep 20180459.543.11$12
Aug 20180959.403.07$28
Jul 201801265.142.93$35
Jun 20180160.183.08$3
May 20180865.382.90$23
Apr 20180163.842.90$3
Mar 20180661.222.79$17
Feb 201801061.782.77$28
Jan 201803762.874.01$148
Dec 201703757.272.92$108
Nov 201707055.423.12$218
Oct 20170749.292.98$21
Sep 201701947.523.09$59
Aug 20170045.373.00$0
Jul 201705243.873.09$161
Jun 20170242.493.09$6
May 20170645.373.26$20
Apr 20170247.933.21$6
Mar 20170146.772.98$3
Feb 201701050.452.95$30
Jan 201704149.413.42$140
Dec 201602848.763.72$104
Nov 201602342.492.64$61
Oct 201606746.193.09$207
Sep 2016010041.553.10$310
Aug 201605041.442.92$146
Jul 201603841.622.92$111
Jun 201603845.352.69$102
May 20160042.521.99$0
Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 201601126.472.06$23
Jan 20160427.352.36$9
Dec 201501132.362.00$22
Nov 20150838.792.17$17
Oct 20150343.552.43$7
Sep 201501042.992.76$28
Aug 20150340.162.87$9
Jul 20150048.152.95$0
Jun 201503056.152.88$86
May 20150055.212.96$0
Apr 201504349.822.71$116
Mar 20150642.892.93$18
Feb 201502244.662.98$65
Jan 20150043.433.10$0
Dec 2014015954.693.59$571
Nov 20140670.464.25$26
Oct 20140578.303.90$20
Sep 20140286.164.05$8
Aug 20140389.394.04$12
Jul 20140596.564.18$21
Jun 201401398.164.74$62
May 20140294.734.73$9
Apr 201402995.944.81$139
Mar 20140195.895.06$5
Feb 20140497.406.19$25
Jan 20140090.404.86$0
Dec 20130291.824.35$9
Nov 20130288.853.74$7
Oct 201302297.423.78$83
Sep 201301104.113.72$4
Aug 201301104.253.52$4
Jul 201308102.523.72$30
Jun 20130094.403.93$0
May 201301294.834.15$50
Apr 2013013293.964.28$565
Mar 20130093.623.91$0
Feb 20130691.233.42$21
Jan 201302591.603.42$86
Dec 201203086.773.42$103
Nov 2012039786.953.62$1,439
Oct 20120089.383.40$0
Sep 20120094.672.92$0
Aug 201201392.662.91$38
Jul 20120085.133.02$0
Jun 201202079.822.52$50
May 201205391.612.49$132
Apr 20122621101.652.00$2,685
Mar 201205105.052.22$11
Feb 201201101.102.57$3
Jan 201201098.092.73$27
Dec 201101396.873.24$42
Nov 2011022895.723.31$755
Oct 201101,14884.983.65$4,189
Sep 201101,67583.623.99$6,676
Aug 201101,35883.404.15$5,635
Jul 201103,13094.144.52$14,139
Jun 201112133192.904.64$12,777
May 2011074098.134.40$3,260
Apr 201108105.964.33$35
Mar 201102,38996.364.06$9,693
Feb 2011091985.644.18$3,841
Jan 2011072686.504.59$3,331
Dec 2010089385.734.35$3,883
Nov 2010097880.843.80$3,712
Oct 201001,86678.103.51$6,548
Sep 201001,18772.633.98$4,724
Aug 201001,51073.684.42$6,673
Jul 201001,79072.554.74$8,478
Jun 201001,63670.364.91$8,033
May 20101882,23471.124.24$22,832
Apr 201001,37881.694.12$5,681
Mar 201001,89678.394.39$8,321
Feb 2010066873.585.44$3,636
Jan 201001,70874.365.96$10,187
Dec 200901,96271.445.48$10,759
Nov 200901,67474.593.75$6,280
Oct 200902,42872.544.11$9,980
Sep 200901,95165.543.06$5,979
Aug 200903,11167.423.22$10,013
Jul 200903,50461.133.46$12,140
Jun 2009055666.163.90$2,166
May 20091872,99254.743.93$21,982
Apr 200903,31346.773.59$11,885
Mar 200904,08742.144.06$16,589
Feb 200903,87832.814.63$17,967
Jan 200904,92135.865.37$26,431
Dec 200804,98137.105.98$29,772
Nov 200804,10355.496.86$28,148
Oct 2008029075.246.92$2,007
Sep 200800101.767.88$0
Aug 2008015114.228.48$127
Jul 200802,272131.0811.39$25,877
Jun 200802,093131.3313.03$27,277
May 20081751,634123.1711.57$40,467
Apr 200803,917110.3110.45$40,952
Mar 200805,029101.909.66$48,601
Feb 200803,14492.538.77$27,575
Jan 200802,79090.388.21$22,894
Dec 20071595,18988.337.30$51,934
Nov 200703,63591.677.29$26,505
Oct 200705,08782.856.92$35,212
Sep 200704,72175.846.24$29,479
Aug 200705,60569.066.39$35,804
Jul 200705,82970.906.39$37,235
Jun 20071726,36062.007.55$58,672
May 200706,92258.747.85$54,312
Apr 200707,28959.617.81$56,892
Mar 200708,29956.927.30$60,599
Feb 20071887,57255.108.22$72,570
Jan 200708,86350.306.73$59,620
Dec 2006010,94756.656.92$75,736
Nov 200620012,59754.207.62$106,797
Oct 200618514,51754.906.01$97,459
Sep 2006013,72260.085.04$69,120
Aug 200635712,71668.717.34$117,864
Jul 2006019,97569.376.34$126,697
Jun 20062625,82566.286.38$166,587

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Apr 2024 — as filed, then multipliedworked
Condensate             0 bbl  × $ 84.45 =         $0
Gas                    4 Mcf  × $  1.66 =         $7

────────────────────────────────────────────────────
Month total                                       $7

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/222183 is the state's own key, not one this site invented.