WYLIE

Operated by SABINE OIL & GAS CORPORATION (P-5 742143) in the MINDEN (COTTON VALLEY CONS.) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 222377District 06Field 617921112 tax incentive programmesCondensateGasSaveExport
Value, all time
$3.6 M
Jul 2006 – Oct 2025
Value, last 12 filed months
$24 k
at the published price for each month
Months reported
232
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 456 leases and 456 wells, and the rule below applies to all of them.

Discovered
2005-09-27
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2018-03-20.

The Commission's schedule remark for this field reads: EXCEPTION TO SWR51(A) 30 DAY RULE.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112006-12-15171959
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition1,579 bbl$119,992
GasProduction671,547 Mcf$3,466,836
Total$3,586,828

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.1392, -94.7744. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.13917, -94.77442 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
10,950 ft
1 wells filed one
Completion to plug
19.3 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 10,950 ft.

Completions filed
Jul 2006
1 of 1 wells
Plug dates filed
Nov 2025
1 of 1 wells

Last completion to plug: a median of 19.3 years across the 1 well that filed both dates, with the middle half between 19.3 years and 19.3 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-40133952610,950 ftJul 2006Nov 2025Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (232)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

232 months

Oct 2025056359.383.30$1,861
Sep 2025057962.743.08$1,782
Aug 2025058163.933.01$1,752
Jul 2025060866.743.32$2,016
Jun 2025058266.483.13$1,821
May 2025060760.553.23$1,962
Apr 2025059662.363.54$2,112
Mar 2025060067.704.27$2,561
Feb 2025054870.884.34$2,379
Jan 2025062474.324.28$2,670
Dec 2024062868.993.12$1,960
Nov 2024065269.052.20$1,433
Oct 2024067971.372.28$1,549
Sep 2024066669.612.36$1,575
Aug 2024069975.632.06$1,442
Jul 2024070579.932.15$1,513
Jun 2024069378.082.63$1,825
May 202401,24278.812.20$2,730
Apr 202401,60584.451.66$2,663
Mar 202401,50380.301.55$2,322
Feb 202401,48776.091.78$2,652
Jan 2024086173.023.30$2,839
Dec 2023071671.262.61$1,869
Nov 2023070277.892.81$1,971
Oct 2023074085.443.09$2,285
Sep 2023068789.042.74$1,879
Aug 2023072480.522.67$1,935
Jul 2023073674.852.64$1,944
Jun 2023071568.962.26$1,615
May 2023075170.622.23$1,673
Apr 2023077378.122.24$1,730
Mar 2023081072.852.39$1,938
Feb 2023075475.112.47$1,859
Jan 2023084476.533.39$2,859
Dec 2022082476.415.73$4,721
Nov 2022081385.005.65$4,590
Oct 2022083087.185.86$4,867
Sep 2022084284.888.16$6,874
Aug 2022086194.529.13$7,858
Jul 20220894101.587.54$6,743
Jun 20220830115.097.98$6,621
May 20220863109.378.43$7,278
Apr 20220813104.226.84$5,559
Mar 20220829108.885.08$4,208
Feb 2022078191.054.86$3,795
Jan 2022089981.844.54$4,079
Dec 2021089771.323.90$3,498
Nov 2021093477.435.24$4,891
Oct 2021092179.795.71$5,262
Sep 202101,30669.865.35$6,988
Aug 2021092266.024.22$3,891
Jul 2021012470.783.98$494
Jun 2021021669.493.38$730
May 2021037363.483.02$1,126
Apr 2021055960.362.76$1,542
Mar 2021093761.302.72$2,546
Feb 2021021657.805.55$1,198
Jan 2021067950.412.81$1,908
Dec 202001,05744.642.68$2,828
Nov 202001,04638.772.71$2,831
Oct 202001,11036.972.48$2,751
Sep 202001,12237.091.99$2,234
Aug 202001,26439.982.39$3,015
Jul 202001,23138.371.83$2,247
Jun 202001,18034.901.69$1,995
May 202001,30816.921.81$2,374
Apr 202001,55014.751.80$2,797
Mar 202001,48630.341.86$2,758
Feb 202001,48849.881.98$2,947
Jan 202001,71357.252.09$3,588
Dec 201901,72959.012.30$3,984
Nov 201901,20555.302.75$3,315
Oct 201901,27053.472.42$3,072
Sep 201901,47255.052.66$3,912
Aug 201901,73853.112.30$4,005
Jul 201901,73756.272.46$4,273
Jun 201901,61452.782.49$4,021
May 201901,71758.482.74$4,705
Apr 201901,59262.632.75$4,379
Mar 201901,61056.803.06$4,930
Feb 201901,48250.852.79$4,138
Jan 201911,61646.033.23$5,263
Dec 201801,65246.594.19$6,914
Nov 201801,61052.934.24$6,822
Oct 201801,67261.443.40$5,682
Sep 201801,61359.543.11$5,013
Aug 201801,68959.403.07$5,179
Jul 201801,80265.142.93$5,283
Jun 201801,73660.183.08$5,342
May 201801,63165.382.90$4,731
Apr 201801,70563.842.90$4,946
Mar 201801,80561.222.79$5,030
Feb 201811,58261.782.77$4,438
Jan 201801,87462.874.01$7,513
Dec 201701,70057.272.92$4,967
Nov 201702,07955.423.12$6,483
Oct 201702,07749.292.98$6,197
Sep 201701,83447.523.09$5,662
Aug 201702,24345.373.00$6,739
Jul 201702,40743.873.09$7,431
Jun 201702,42442.493.09$7,484
May 201702,55145.373.26$8,325
Apr 201702,34447.933.21$7,528
Mar 201702,43046.772.98$7,250
Feb 201702,30650.452.95$6,809
Jan 201702,23249.413.42$7,631
Dec 201601,95348.763.72$7,271
Nov 201601,94342.492.64$5,138
Oct 201602,09546.193.09$6,474
Sep 201602,10341.553.10$6,521
Aug 201602,16241.442.92$6,322
Jul 201602,06941.622.92$6,050
Jun 201602,03545.352.69$5,466
May 201602,17242.521.99$4,325
Apr 201602,12636.561.99$4,233
Mar 201602,37433.011.79$4,259
Feb 201602,66126.472.06$5,491
Jan 201602,12127.352.36$5,015
Dec 2015069932.362.00$1,399
Nov 201501,22638.792.17$2,657
Oct 201501,32543.552.43$3,215
Sep 20151761,34342.992.76$11,271
Aug 201501,44240.162.87$4,142
Jul 201501,44848.152.95$4,264
Jun 201501,35856.152.88$3,915
May 201501,50555.212.96$4,448
Apr 201501,55549.822.71$4,209
Mar 201501,62442.892.93$4,766
Feb 201501,49644.662.98$4,452
Jan 201501,72843.433.10$5,358
Dec 201401,81554.693.59$6,518
Nov 201401,88170.464.25$7,998
Oct 201401,97178.303.90$7,689
Sep 201402,04986.164.05$8,289
Aug 201402,30789.394.04$9,309
Jul 201402,45096.564.18$10,240
Jun 201402,41198.164.74$11,421
May 201402,54594.734.73$12,029
Apr 201432,54295.944.81$12,513
Mar 201402,72595.895.06$13,780
Feb 201412,54297.406.19$15,837
Jan 201403,69990.404.86$17,980
Dec 201301,28991.824.35$5,613
Nov 201312,53588.853.74$9,565
Oct 201302,65697.423.78$10,038
Sep 201302,600104.113.72$9,666
Aug 201302,855104.253.52$10,057
Jul 201302,949102.523.72$10,964
Jun 201322,76594.403.93$11,065
May 201302,94394.834.15$12,211
Apr 201302,81393.964.28$12,047
Mar 201302,89293.623.91$11,316
Feb 201302,64891.233.42$9,056
Jan 201302,96291.603.42$10,130
Dec 201202,94886.773.42$10,083
Nov 201202,99586.953.62$10,857
Oct 201203,12889.383.40$10,634
Sep 201202,95494.672.92$8,621
Aug 201203,03692.662.91$8,829
Jul 201202,95085.133.02$8,911
Jun 201203,06879.822.52$7,728
May 201203,10791.612.49$7,731
Apr 201202,758101.652.00$5,507
Mar 201222,839105.052.22$6,519
Feb 201212,968101.102.57$7,730
Jan 201203,09698.092.73$8,465
Dec 201103,07196.873.24$9,949
Nov 201103,00795.723.31$9,957
Oct 201103,07684.983.65$11,223
Sep 20111913,02883.623.99$28,040
Aug 2011123,09483.404.15$13,839
Jul 2011263,13094.144.52$16,587
Jun 2011153,05192.904.64$15,550
May 2011133,21798.134.40$15,446
Apr 2011173,137105.964.33$15,395
Mar 2011153,28496.364.06$14,770
Feb 2011192,96585.644.18$14,021
Jan 2011183,30886.504.59$16,737
Dec 201083,37785.734.35$15,368
Nov 2010163,33080.843.80$13,932
Oct 2010153,51378.103.51$13,498
Sep 2010163,34272.633.98$14,461
Aug 2010133,54173.684.42$16,607
Jul 2010123,54072.554.74$17,638
Jun 2010193,43370.364.91$18,194
May 2010143,69271.124.24$16,632
Apr 2010193,75281.694.12$17,020
Mar 2010263,98778.394.39$19,536
Feb 2010193,63673.585.44$21,186
Jan 2010194,07574.365.96$25,717
Dec 2009154,09271.445.48$23,511
Nov 2009103,82574.593.75$15,095
Oct 2009144,02072.544.11$17,539
Sep 20091774,02765.543.06$23,942
Aug 2009234,24367.423.22$15,207
Jul 2009184,13561.133.46$15,426
Jun 2009214,18766.163.90$17,698
May 2009204,40054.743.93$18,368
Apr 2009284,41446.773.59$17,145
Mar 2009264,81742.144.06$20,648
Feb 2009204,39132.814.63$21,000
Jan 2009265,03135.865.37$27,954
Dec 2008345,02937.105.98$31,320
Nov 2008225,13955.496.86$36,476
Oct 2008275,43475.246.92$39,646
Sep 2008305,138101.767.88$43,525
Aug 2008335,525114.228.48$50,638
Jul 2008315,693131.0811.39$68,904
Jun 2008365,858131.3313.03$81,073
May 2008405,936123.1711.57$73,632
Apr 2008315,698110.3110.45$62,991
Mar 2008356,020101.909.66$61,744
Feb 2008195,48592.538.77$49,865
Jan 2008286,49890.388.21$55,851
Dec 2007175,54988.337.30$42,020
Nov 2007126,05891.677.29$45,273
Oct 2007136,44282.856.92$45,668
Sep 2007176,46275.846.24$41,639
Aug 2007166,96769.066.39$45,610
Jul 2007147,47770.906.39$48,755
Jun 2007167,99662.007.55$61,349
May 200708,63858.747.85$67,776
Apr 200708,83459.617.81$68,951
Mar 200709,84856.927.30$71,910
Feb 200709,50555.108.22$78,093
Jan 2007011,52750.306.73$77,540
Dec 2006012,65456.656.92$87,546
Nov 2006013,90954.207.62$105,952
Oct 2006017,56054.906.01$105,602
Sep 2006022,98860.085.04$115,795
Aug 2006035,08468.717.34$257,514
Jul 200609,41669.376.34$59,723

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Oct 2025 — as filed, then multipliedworked
Condensate             0 bbl  × $ 59.38 =         $0
Gas                  563 Mcf  × $  3.30 =     $1,861

────────────────────────────────────────────────────
Month total                                   $1,861

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/222377 is the state's own key, not one this site invented.