PAGE, L.E.

Operated by DIVERSIFIED PRODUCTION LLC (P-5 220903) in the CARTHAGE (COTTON VALLEY) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 224031District 06Field 160321742 tax incentive programmesCondensateGasSaveExport
Value, all time
$6.8 M
Nov 2006 – May 2026
Value, last 12 filed months
$113 k
at the published price for each month
Months reported
235
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 4,104 leases and 4,104 wells, and the rule below applies to all of them.

Discovered
1968-05-01
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2011-02-08.

The Commission's schedule remark for this field reads: FIELD. EFFECTIVE 4/12/16.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112007-06-25172610
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition11,427 bbl$860,929
GasProduction1,190,720 Mcf$5,944,535
Total$6,805,464

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.0801, -94.4298. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.08011, -94.42983 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
9,650 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 9,650 ft.

Completions filed
Nov 2006
1 of 1 wells

1 well

42-3653585879,650 ftNov 2006

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (235)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

235 months

May 2026622,100106.413.05$12,994
Apr 2026652,16598.932.87$12,643
Mar 2026712,12889.753.15$13,074
Feb 2026722,03263.503.75$12,193
Jan 2026691,73959.138.00$17,988
Dec 2025851,95556.664.41$13,444
Nov 2025721,94558.593.93$11,855
Oct 2025301,58659.383.30$7,023
Sep 2025466762.743.08$2,303
Aug 2025267463.933.01$2,160
Jul 2025597066.743.32$3,549
Jun 202571,03266.483.13$3,694
May 2025121,08760.553.23$4,240
Apr 20251289262.363.54$3,909
Mar 2025131,43067.704.27$6,984
Feb 2025111,06870.884.34$5,416
Jan 2025151,73174.324.28$8,521
Dec 2024132,29868.993.12$8,070
Nov 202491,66469.052.20$4,280
Oct 20241195771.372.28$2,968
Sep 2024111,57569.612.36$4,490
Aug 2024101,24375.632.06$3,321
Jul 2024132,10179.932.15$5,549
Jun 2024111,76778.082.63$5,513
May 2024112,12078.812.20$5,528
Apr 2024111,93684.451.66$4,141
Mar 2024142,21280.301.55$4,542
Feb 2024131,84376.091.78$4,276
Jan 2024112,06773.023.30$7,619
Dec 2023132,75771.262.61$8,124
Nov 2023122,65777.892.81$8,394
Oct 2023122,51885.443.09$8,799
Sep 2023102,36089.042.74$7,345
Aug 2023111,74080.522.67$5,537
Jul 2023101,85074.852.64$5,636
Jun 2023102,07068.962.26$5,365
May 2023112,10370.622.23$5,461
Apr 2023111,96378.122.24$5,252
Mar 2023152,18572.852.39$6,322
Feb 2023132,12775.112.47$6,221
Jan 2023152,48476.533.39$9,563
Dec 2022152,15176.415.73$13,469
Nov 2022142,28685.005.65$14,097
Oct 2022141,86987.185.86$12,180
Sep 2022132,32184.888.16$20,051
Aug 2022162,71994.529.13$26,329
Jul 2022222,825101.587.54$23,541
Jun 2022212,772115.097.98$24,530
May 2022232,824109.378.43$26,330
Apr 2022252,878104.226.84$22,284
Mar 2022283,009108.885.08$18,324
Feb 2022252,69891.054.86$15,385
Jan 2022272,91981.844.54$15,455
Dec 2021273,25771.323.90$14,625
Nov 2021252,73077.435.24$16,232
Oct 2021233,22579.795.71$20,262
Sep 2021202,94169.865.35$17,134
Aug 2021243,50866.024.22$16,390
Jul 2021243,61670.783.98$16,098
Jun 2021233,53169.493.38$13,535
May 2021263,57863.483.02$12,448
Apr 2021243,53160.362.76$11,189
Mar 2021192,96061.302.72$9,207
Feb 2021682757.805.55$4,935
Jan 2021131,76450.412.81$5,613
Dec 2020131,63244.642.68$4,947
Nov 2020111,40338.772.71$4,224
Oct 2020111,72336.972.48$4,677
Sep 2020101,60637.091.99$3,569
Aug 2020101,37039.982.39$3,667
Jul 2020111,69538.371.83$3,516
Jun 2020132,46734.901.69$4,624
May 2020132,26116.921.81$4,323
Apr 2020292,31314.751.80$4,601
Mar 2020282,33830.341.86$5,189
Feb 2020251,51349.881.98$4,244
Jan 2020301,99257.252.09$5,890
Dec 2019272,75759.012.30$7,946
Nov 2019252,43355.302.75$8,075
Oct 2019252,71453.472.42$7,901
Sep 2019222,79855.052.66$8,646
Aug 2019272,78353.112.30$7,847
Jul 2019282,85056.272.46$8,587
Jun 2019282,84652.782.49$8,568
May 2019302,95758.482.74$9,858
Apr 2019302,84962.632.75$9,716
Mar 2019232,73056.803.06$9,666
Feb 2019132,35650.852.79$7,240
Jan 2019152,85646.033.23$9,910
Dec 2018152,81346.594.19$12,472
Nov 2018122,79552.934.24$12,478
Oct 2018133,33661.443.40$12,135
Sep 2018113,41559.543.11$11,269
Aug 2018123,34659.403.07$10,974
Jul 2018132,99765.142.93$9,634
Jun 2018113,07360.183.08$10,117
May 2018113,12565.382.90$9,784
Apr 2018113,08063.842.90$9,637
Mar 2018113,18061.222.79$9,536
Feb 201882,74961.782.77$8,098
Jan 2018102,89562.874.01$12,236
Dec 201792,74557.272.92$8,535
Nov 2017103,09455.423.12$10,202
Oct 201793,49549.292.98$10,872
Sep 201783,44147.523.09$11,003
Aug 201792,92745.373.00$9,202
Jul 2017312,83043.873.09$10,097
Jun 2017113,60442.493.09$11,594
May 2017173,49845.373.26$12,187
Apr 2017243,37847.933.21$11,999
Mar 2017263,42546.772.98$11,435
Feb 2017233,27250.452.95$10,821
Jan 2017264,02449.413.42$15,042
Dec 2016243,38948.763.72$13,787
Nov 2016223,42942.492.64$10,002
Oct 2016183,55246.193.09$11,808
Sep 2016163,34441.553.10$11,033
Aug 2016393,79841.442.92$12,723
Jul 2016253,90541.622.92$12,460
Jun 2016223,82145.352.69$11,260
May 2016223,90142.521.99$8,702
Apr 2016214,03636.561.99$8,804
Mar 2016224,24033.011.79$8,333
Feb 2016213,97326.472.06$8,755
Jan 2016214,18727.352.36$10,474
Dec 2015224,54632.362.00$9,810
Nov 2015183,67738.792.17$8,667
Oct 2015153,50643.552.43$9,161
Sep 2015184,30942.992.76$12,660
Aug 2015194,55840.162.87$13,856
Jul 2015214,77548.152.95$15,074
Jun 2015214,56256.152.88$14,331
May 2015234,96455.212.96$15,941
Apr 2015254,82849.822.71$14,313
Mar 2015265,00442.892.93$15,800
Feb 2015454,02044.662.98$13,974
Jan 2015585,06043.433.10$18,208
Dec 2014545,16454.693.59$21,499
Nov 2014464,85970.464.25$23,901
Oct 2014475,31478.303.90$24,410
Sep 2014455,27586.164.05$25,217
Aug 2014465,70989.394.04$27,148
Jul 2014535,61296.564.18$28,574
Jun 2014464,33098.164.74$25,026
May 2014705,20194.734.73$31,214
Apr 2014764,01995.944.81$26,619
Mar 2014834,99495.895.06$33,213
Feb 2014714,05497.406.19$32,018
Jan 2014764,41490.404.86$28,326
Dec 2013875,23491.824.35$30,780
Nov 2013724,53588.853.74$23,350
Oct 2013664,34197.423.78$22,836
Sep 2013644,319104.113.72$22,720
Aug 2013714,983104.253.52$24,955
Jul 2013815,018102.523.72$26,960
Jun 2013724,63694.403.93$25,032
May 2013835,46094.834.15$30,525
Apr 2013784,38793.964.28$26,117
Mar 2013935,25093.623.91$29,249
Feb 2013814,56191.233.42$22,988
Jan 2013885,23991.603.42$25,978
Dec 2012905,76586.773.42$27,527
Nov 2012805,21586.953.62$25,860
Oct 2012493,02589.383.40$14,664
Sep 2012724,91794.672.92$21,166
Aug 2012725,19592.662.91$21,779
Jul 2012725,28785.133.02$22,100
Jun 2012775,14779.822.52$19,112
May 2012835,52191.612.49$21,342
Apr 2012895,520101.652.00$20,069
Mar 2012384,230105.052.22$13,391
Feb 2012244,726101.102.57$14,573
Jan 2012245,02998.092.73$16,104
Dec 2011234,81396.873.24$17,821
Nov 2011214,94595.723.31$18,384
Oct 2011205,27784.983.65$20,953
Sep 2011205,38683.623.99$23,140
Aug 2011205,68583.404.15$25,257
Jul 2011225,71394.144.52$27,878
Jun 2011235,63692.904.64$28,287
May 2011275,98298.134.40$28,999
Apr 201100105.964.33$0
Mar 2011845,91796.364.06$32,102
Feb 2011825,46885.644.18$29,879
Jan 2011786,14486.504.59$34,940
Dec 2010876,30085.734.35$34,849
Nov 2010786,04780.843.80$29,256
Oct 2010766,59278.103.51$29,066
Sep 2010576,52272.633.98$30,094
Aug 2010476,92673.684.42$34,071
Jul 2010486,92372.554.74$36,273
Jun 2010506,74370.364.91$36,629
May 2010657,15871.124.24$34,939
Apr 2010717,45781.694.12$36,543
Mar 2010967,88378.394.39$42,121
Feb 20101147,19973.585.44$47,568
Jan 20101168,24274.365.96$57,782
Dec 20091197,85371.445.48$51,565
Nov 20091007,89174.593.75$37,062
Oct 20091048,41272.544.11$42,120
Sep 20091208,46965.543.06$33,820
Aug 20091328,47867.423.22$36,186
Jul 20091449,13761.133.46$40,458
Jun 20091709,16566.163.90$46,945
May 20091598,74354.743.93$43,026
Apr 20091899,49546.773.59$42,903
Mar 200925211,07042.144.06$55,552
Feb 20091214,57732.814.63$25,175
Jan 200922110,16735.865.37$62,532
Dec 200824211,24437.105.98$76,185
Nov 200821511,56955.496.86$91,298
Oct 200813912,76675.246.92$98,824
Sep 2008949,171101.767.88$81,806
Aug 2008788,214114.228.48$78,589
Jul 2008737,727131.0811.39$97,575
Jun 2008757,617131.3313.03$109,119
May 200810210,065123.1711.57$129,059
Apr 200813410,748110.3110.45$127,150
Mar 200828512,453101.909.66$149,388
Feb 20082469,32992.538.77$104,583
Jan 200830912,81790.388.21$133,100
Dec 200731513,37588.337.30$125,488
Nov 200726913,56191.677.29$123,542
Oct 20073414,49882.856.92$103,172
Sep 20073115,23975.846.24$97,506
Aug 20073316,75369.066.39$109,296
Jul 20073318,25570.906.39$118,952
Jun 20073318,77762.007.55$143,783
May 20073620,08058.747.85$159,668
Apr 20072518,05359.617.81$142,398
Mar 20075020,99756.927.30$156,165
Feb 20075323,45755.108.22$195,643
Jan 20077734,13150.306.73$233,467
Dec 20066437,72056.656.92$264,589
Nov 200605,50454.207.62$41,927

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate            62 bbl  × $106.41 =     $6,597
Gas                2,100 Mcf  × $  3.05 =     $6,396

────────────────────────────────────────────────────
Month total                                  $12,994

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/224031 is the state's own key, not one this site invented.