CAMERON UNIT 1

Operated by R. LACY SERVICES, LTD. (P-5 687208) in the CARTHAGE (COTTON VALLEY) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 224038District 06Field 160321742 tax incentive programmesCondensateGasSaveExport
Value, all time
$7.4 M
Dec 2006 – May 2026
Value, last 12 filed months
$83 k
at the published price for each month
Months reported
234
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 4,104 leases and 4,104 wells, and the rule below applies to all of them.

Discovered
1968-05-01
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2011-02-08.

The Commission's schedule remark for this field reads: FIELD. EFFECTIVE 4/12/16.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112007-02-16172556
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition17,329 bbl$1,196,035
GasProduction1,203,005 Mcf$6,209,442
Total$7,405,477

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.2663, -94.3259. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.26628, -94.32586 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
9,725 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 9,725 ft.

Completions filed
Dec 2006
1 of 1 wells

1 well

42-36536390139,725 ftDec 2006

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (234)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

234 months

May 2026172,132106.413.05$8,303
Apr 2026201,86998.932.87$7,342
Mar 2026131,33889.753.15$5,381
Feb 2026161,79963.503.75$7,763
Jan 2026121,29959.138.00$11,099
Dec 2025151,66956.664.41$8,216
Nov 2025131,88658.593.93$8,167
Oct 202501,43459.383.30$4,739
Sep 202501,73062.743.08$5,323
Aug 202501,60163.933.01$4,827
Jul 202502,07166.743.32$6,866
Jun 202531,39966.483.13$4,577
May 2025181,95060.553.23$7,393
Apr 2025191,90762.363.54$7,942
Mar 2025252,26167.704.27$11,343
Feb 2025191,78570.884.34$9,095
Jan 2025121,22974.324.28$6,150
Dec 2024121,26668.993.12$4,780
Nov 2024101,32169.052.20$3,595
Oct 2024111,92271.372.28$5,170
Sep 202491,85869.612.36$5,019
Aug 202491,83475.632.06$4,465
Jul 2024111,98379.932.15$5,136
Jun 2024101,73978.082.63$5,361
May 2024121,76978.812.20$4,835
Apr 202401,59884.451.66$2,651
Mar 202401,38280.301.55$2,135
Feb 202401,72976.091.78$3,084
Jan 202401,67873.023.30$5,533
Dec 202301,90671.262.61$4,976
Nov 202301,78177.892.81$5,000
Oct 202301,91585.443.09$5,912
Sep 202301,77989.042.74$4,866
Aug 202301,60580.522.67$4,290
Jul 202301,74274.852.64$4,602
Jun 202301,43168.962.26$3,232
May 202301,44970.622.23$3,228
Apr 202301,64578.122.24$3,681
Mar 202301,92872.852.39$4,614
Feb 202301,60875.112.47$3,965
Jan 202301,96176.533.39$6,643
Dec 202201,40376.415.73$8,038
Nov 202201,90885.005.65$10,773
Oct 202201,97287.185.86$11,563
Sep 202212,21584.888.16$18,167
Aug 202202,43594.529.13$22,225
Jul 202202,149101.587.54$16,208
Jun 202201,783115.097.98$14,223
May 2022482,301109.378.43$24,654
Apr 202201,582104.226.84$10,817
Mar 202201,992108.885.08$10,112
Feb 2022312,15391.054.86$13,284
Jan 2022932,61281.844.54$19,464
Dec 2021312,16271.323.90$10,641
Nov 2021612,04177.435.24$15,412
Oct 2021582,43479.795.71$18,535
Sep 2021262,61069.865.35$15,782
Aug 2021441,70066.024.22$10,080
Jul 2021472,21770.783.98$12,155
Jun 2021252,03269.493.38$8,607
May 20211022,21663.483.02$13,162
Apr 2021392,49660.362.76$9,239
Mar 2021302,32461.302.72$8,153
Feb 2021381,43057.805.55$10,130
Jan 2021382,59250.412.81$9,200
Dec 2020362,47944.642.68$8,240
Nov 2020382,12538.772.71$7,225
Oct 2020202,49736.972.48$6,928
Sep 2020522,82437.091.99$7,551
Aug 2020592,79339.982.39$9,020
Jul 2020582,93838.371.83$7,588
Jun 2020592,93434.901.69$7,018
May 2020483,14616.921.81$6,521
Apr 2020722,22614.751.80$5,079
Mar 2020482,81730.341.86$6,685
Feb 2020502,77049.881.98$7,980
Jan 2020863,04957.252.09$11,310
Dec 2019332,69959.012.30$8,167
Nov 2019122,46555.302.75$7,444
Oct 201912,77053.472.42$6,753
Sep 201902,13355.052.66$5,668
Aug 201901,81053.112.30$4,171
Jul 201902,39256.272.46$5,884
Jun 201903,27452.782.49$8,156
May 201913,33658.482.74$9,200
Apr 2019403,16862.632.75$11,219
Mar 2019593,24356.803.06$13,282
Feb 2019382,24250.852.79$8,192
Jan 2019412,34446.033.23$9,454
Dec 20181122,86246.594.19$17,197
Nov 2018443,09152.934.24$15,426
Oct 2018433,57561.443.40$14,790
Sep 2018433,58359.543.11$13,696
Aug 2018153,90159.403.07$12,854
Jul 2018103,24365.142.93$10,159
Jun 2018163,13760.183.08$10,615
May 2018123,57265.382.90$11,146
Apr 2018112,82763.842.90$8,903
Mar 2018251,27161.222.79$5,073
Feb 2018472,24061.782.77$9,100
Jan 2018341,97062.874.01$10,036
Dec 2017482,25257.272.92$9,328
Nov 2017653,39555.423.12$14,189
Oct 2017593,14049.292.98$12,277
Sep 2017593,11847.523.09$12,430
Aug 2017242,91545.373.00$9,847
Jul 201702,78543.873.09$8,598
Jun 201702,40442.493.09$7,422
May 201702,66545.373.26$8,697
Apr 201702,79547.933.21$8,976
Mar 201702,78246.772.98$8,301
Feb 2017172,55850.452.95$8,410
Jan 2017843,57249.413.42$16,362
Dec 2016542,56748.763.72$12,190
Nov 2016512,60742.492.64$9,061
Oct 2016512,77546.193.09$10,931
Sep 2016832,81141.553.10$12,165
Aug 20161003,21541.442.92$13,546
Jul 2016372,08341.622.92$7,631
Jun 2016273,52145.352.69$10,681
May 2016171,79142.521.99$4,289
Apr 2016213,18936.561.99$7,117
Mar 201642,45833.011.79$4,542
Feb 2016153,54526.472.06$7,713
Jan 2016522,18727.352.36$6,593
Dec 20151293,55132.362.00$11,281
Nov 20151213,37538.792.17$12,008
Oct 2015953,62043.552.43$12,921
Sep 2015323,03242.992.76$9,739
Aug 2015243,20040.162.87$10,156
Jul 2015153,76448.152.95$11,808
Jun 2015133,18056.152.88$9,897
May 2015123,91255.212.96$12,224
Apr 2015264,10449.822.71$12,403
Mar 2015292,80842.892.93$9,484
Feb 2015222,26444.662.98$7,721
Jan 2015102,91643.433.10$9,476
Dec 201412,96354.693.59$10,696
Nov 2014102,74370.464.25$12,367
Oct 2014313,70278.303.90$16,869
Sep 2014184,45486.164.05$19,569
Aug 2014143,88189.394.04$16,912
Jul 2014332,88696.564.18$15,249
Jun 2014414,38298.164.74$24,782
May 2014444,80194.734.73$26,860
Apr 2014251,43895.944.81$9,314
Mar 2014564,37195.895.06$27,473
Feb 2014544,02697.406.19$30,189
Jan 2014324,08790.404.86$22,759
Dec 2013323,83691.824.35$19,642
Nov 2013123,98788.853.74$15,971
Oct 201355,20797.423.78$20,166
Sep 201332,689104.113.72$10,309
Aug 2013234,236104.253.52$17,320
Jul 2013415,111102.523.72$23,205
Jun 2013334,00094.403.93$18,849
May 2013686,30594.834.15$32,608
Apr 2013605,03193.964.28$27,183
Mar 2013645,17593.623.91$26,241
Feb 2013555,88391.233.42$25,137
Jan 20131035,25491.603.42$27,403
Dec 20121086,55586.773.42$31,790
Nov 2012756,27786.953.62$29,275
Oct 2012172,93689.383.40$11,501
Sep 2012325,33894.672.92$18,608
Aug 2012366,13992.662.91$21,189
Jul 2012446,62385.133.02$23,752
Jun 2012436,64979.822.52$20,181
May 2012545,22391.612.49$17,943
Apr 2012447,202101.652.00$18,854
Mar 2012675,788105.052.22$19,900
Feb 2012656,548101.102.57$23,401
Jan 2012626,90398.092.73$24,955
Dec 2011377,87196.873.24$29,084
Nov 2011307,15195.723.31$26,551
Oct 201108,34984.983.65$30,462
Sep 201104,49283.623.99$17,904
Aug 2011136,77883.404.15$29,208
Jul 2011527,66094.144.52$39,497
Jun 2011876,59092.904.64$38,659
May 20111147,78998.134.40$45,496
Apr 20111378,922105.964.33$53,178
Mar 20111567,77096.364.06$46,558
Feb 20111577,64885.644.18$45,414
Jan 20111999,74386.504.59$61,922
Dec 20101998,58785.734.35$54,394
Nov 20102058,40580.843.80$48,472
Oct 20101315,83378.103.51$30,698
Sep 2010935,87472.633.98$30,130
Aug 20101327,20073.684.42$41,545
Jul 20101707,48172.554.74$47,767
Jun 20101756,75070.364.91$45,458
May 20101767,07671.124.24$42,486
Apr 2010896,61081.694.12$34,521
Mar 20101017,47678.394.39$40,727
Feb 20101267,04873.585.44$47,629
Jan 20101458,64274.365.96$62,324
Dec 20091589,25171.445.48$62,018
Nov 20091418,49374.593.75$42,379
Oct 200917510,74072.544.11$56,839
Sep 200914810,99965.543.06$43,409
Aug 200913310,02567.423.22$41,232
Jul 20091376,63361.133.46$31,355
Jun 20091516,47566.163.90$35,210
May 20091537,31854.743.93$37,104
Apr 20091254,60446.773.59$22,363
Mar 20091978,69242.144.06$43,582
Feb 2009432,51932.814.63$13,081
Jan 20096710,74335.865.37$60,103
Dec 20087811,13537.105.98$69,449
Nov 200816110,35255.496.86$79,952
Oct 200816412,39075.246.92$98,103
Sep 20081178,851101.767.88$81,626
Aug 20089911,293114.228.48$107,107
Jul 200813813,708131.0811.39$174,215
Jun 200812912,565131.3313.03$180,697
May 200814813,741123.1711.57$177,271
Apr 200810413,985110.3110.45$157,683
Mar 200814211,952101.909.66$129,975
Feb 200816313,51892.538.77$133,643
Jan 200826315,31790.388.21$149,457
Dec 200726615,96888.337.30$140,094
Nov 200719216,01291.677.29$134,355
Oct 200720417,33682.856.92$136,901
Sep 200719017,81375.846.24$125,637
Aug 200726919,38869.066.39$142,427
Jul 200728019,96370.906.39$147,374
Jun 200745020,73662.007.55$184,425
May 200750422,94758.747.85$209,654
Apr 200764525,08559.617.81$234,242
Mar 200788329,64556.927.30$266,727
Feb 200795829,05755.108.22$291,518
Jan 200797536,74050.306.73$296,187
Dec 20062939,09356.656.92$79,508

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate            17 bbl  × $106.41 =     $1,809
Gas                2,132 Mcf  × $  3.05 =     $6,494

────────────────────────────────────────────────────
Month total                                   $8,303

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/224038 is the state's own key, not one this site invented.