Operated by BROOKSTON ENERGY, INC. (P-5 97353) in the CARTHAGE, NORTH (COTTON VALLEY) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 228006District 06Field 160342502 tax incentive programmesCondensateGasSaveExport
Value, all time
$2.2 M
Feb 2007 – May 2026
Value, last 12 filed months
$58 k
at the published price for each month
Months reported
232
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 568 leases and 570 wells, and the rule below applies to all of them.

Discovered
1981-11-18
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2010-12-14.

The Commission's schedule remark for this field reads: EFFECTIVE AUGUST.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112007-12-07179361
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition5,254 bbl$433,780
GasProduction306,053 Mcf$1,749,770
Total$2,183,550

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.5050, -94.2188. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.50495, -94.21879 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
10,080 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 10,080 ft.

Completions filed
Feb 2007
1 of 1 wells

1 well

42-20333782310,080 ftFeb 2007

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (232)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

232 months

May 202631,286106.413.05$4,236
Apr 202601,19998.932.87$3,441
Mar 2026531,22289.753.15$8,605
Feb 202601,09163.503.75$4,092
Jan 202601,16759.138.00$9,334
Dec 2025086356.664.41$3,809
Nov 20255997458.593.93$7,281
Oct 202501,21059.383.30$3,999
Sep 202501,02962.743.08$3,166
Aug 202501,18763.933.01$3,579
Jul 2025096366.743.32$3,193
Jun 2025088866.483.13$2,778
May 2025094060.553.23$3,038
Apr 202501,01162.363.54$3,582
Mar 202511,01667.704.27$4,404
Feb 2025087670.884.34$3,803
Jan 2025080774.324.28$3,453
Dec 2024089068.993.12$2,778
Nov 2024075369.052.20$1,655
Oct 2024098571.372.28$2,247
Sep 2024069469.612.36$1,641
Aug 2024070975.632.06$1,463
Jul 2024069079.932.15$1,481
Jun 2024061978.082.63$1,630
May 2024040278.812.20$884
Apr 20240184.451.66$2
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230180.522.67$3
Jul 20233074.852.64$225
Jun 20230168.962.26$2
May 20230170.622.23$2
Apr 20230078.122.24$0
Mar 2023020272.852.39$483
Feb 2023057775.112.47$1,423
Jan 2023156776.533.39$1,997
Dec 2022166876.415.73$3,903
Nov 20221170485.005.65$4,910
Oct 2022051887.185.86$3,037
Sep 202219784.888.16$877
Aug 20221094.529.13$95
Jul 202210101.587.54$102
Jun 202209115.097.98$72
May 2022064109.378.43$540
Apr 2022090104.226.84$615
Mar 20220107108.885.08$543
Feb 2022237791.054.86$2,468
Jan 2022012081.844.54$545
Dec 202107671.323.90$296
Nov 202108677.435.24$450
Oct 2021012479.795.71$709
Sep 2021012269.865.35$653
Aug 2021012666.024.22$532
Jul 2021017070.783.98$677
Jun 2021015969.493.38$538
May 2021018063.483.02$543
Apr 2021015160.362.76$417
Mar 20212015261.302.72$1,639
Feb 2021012757.805.55$705
Jan 2021014250.412.81$399
Dec 2020012044.642.68$321
Nov 2020012838.772.71$346
Oct 2020012636.972.48$312
Sep 2020011537.091.99$229
Aug 2020012339.982.39$293
Jul 2020012838.371.83$234
Jun 2020011734.901.69$198
May 2020013816.921.81$250
Apr 2020011914.751.80$215
Mar 2020012430.341.86$230
Feb 2020014749.881.98$291
Jan 2020018157.252.09$379
Dec 2019013459.012.30$309
Nov 201904155.302.75$113
Oct 2019014853.472.42$358
Sep 2019010355.052.66$274
Aug 2019018353.112.30$422
Jul 2019010856.272.46$266
Jun 201903652.782.49$90
May 201903258.482.74$88
Apr 201907962.632.75$217
Mar 20191014656.803.06$1,015
Feb 2019014050.852.79$391
Jan 2019020246.033.23$652
Dec 2018018546.594.19$774
Nov 2018022952.934.24$970
Oct 2018017861.443.40$605
Sep 2018021159.543.11$656
Aug 2018014759.403.07$451
Jul 2018018065.142.93$528
Jun 20181018460.183.08$1,168
May 2018020965.382.90$606
Apr 2018018963.842.90$548
Mar 2018020561.222.79$571
Feb 2018016161.782.77$445
Jan 2018015662.874.01$625
Dec 2017022457.272.92$654
Nov 2017022155.423.12$689
Oct 2017012849.292.98$382
Sep 2017218247.523.09$657
Aug 2017020745.373.00$622
Jul 2017019943.873.09$614
Jun 2017015342.493.09$472
May 2017019745.373.26$643
Apr 2017017747.933.21$568
Mar 2017112946.772.98$432
Feb 2017116350.452.95$532
Jan 2017019049.413.42$650
Dec 2016020548.763.72$763
Nov 2016219942.492.64$611
Oct 2016026446.193.09$816
Sep 2016035641.553.10$1,104
Aug 2016042841.442.92$1,252
Jul 2016041241.622.92$1,205
Jun 2016045345.352.69$1,217
May 20161040742.521.99$1,236
Apr 2016036436.561.99$725
Mar 20161024333.011.79$766
Feb 2016022826.472.06$471
Jan 2016028027.352.36$662
Dec 2015037632.362.00$753
Nov 2015045938.792.17$995
Oct 20151056843.552.43$1,814
Sep 2015222342.992.76$1,009
Aug 20151592040.162.87$3,245
Jul 2015093148.152.95$2,742
Jun 2015593156.152.88$2,965
May 2015153,90855.212.96$12,378
Apr 20151083549.822.71$2,758
Mar 20153732942.892.93$2,552
Feb 2015092144.662.98$2,741
Jan 2015161,09943.433.10$4,102
Dec 2014795754.693.59$3,820
Nov 20141295170.464.25$4,889
Oct 20141297078.303.90$4,724
Sep 20142189286.164.05$5,418
Aug 20144291489.394.04$7,442
Jul 20141985796.564.18$5,417
Jun 20141777298.164.74$5,326
May 20141380694.734.73$5,041
Apr 20142294195.944.81$6,636
Mar 2014171,03795.895.06$6,874
Feb 20142893997.406.19$8,541
Jan 2014890390.404.86$5,112
Dec 2013790291.824.35$4,570
Nov 20131892888.853.74$5,068
Oct 2013131,05497.423.78$5,250
Sep 2013361,100104.113.72$7,837
Aug 2013191,105104.253.52$5,873
Jul 2013141,083102.523.72$5,462
Jun 20131364594.403.93$3,764
May 20131190894.834.15$4,810
Apr 20133296093.964.28$7,118
Mar 2013251,14993.623.91$6,836
Feb 2013231,09391.233.42$5,836
Jan 2013251,18991.603.42$6,356
Dec 2012421,24186.773.42$7,889
Nov 2012391,22786.953.62$7,839
Oct 2012241,32089.383.40$6,633
Sep 2012201,20194.672.92$5,398
Aug 2012371,23692.662.91$7,023
Jul 2012371,26585.133.02$6,971
Jun 2012411,24079.822.52$6,396
May 2012241,39091.612.49$5,657
Apr 2012471,343101.652.00$7,459
Mar 2012231,351105.052.22$5,418
Feb 2012431,267101.102.57$7,604
Jan 2012421,42998.092.73$8,027
Dec 2011271,69596.873.24$8,107
Nov 2011401,51795.723.31$8,852
Oct 2011271,20284.983.65$6,680
Sep 2011251,09983.623.99$6,471
Aug 2011301,36483.404.15$8,162
Jul 2011391,37494.144.52$9,878
Jun 2011381,39492.904.64$9,998
May 2011401,44998.134.40$10,308
Apr 2011381,546105.964.33$10,726
Mar 2011491,71696.364.06$11,684
Feb 2011201,36985.644.18$7,435
Jan 2011201,57586.504.59$8,957
Dec 2010591,76285.734.35$12,719
Nov 2010481,49780.843.80$9,562
Oct 2010431,43778.103.51$8,401
Sep 2010191,37572.633.98$6,852
Aug 2010371,63173.684.42$9,934
Jul 2010361,58772.554.74$10,129
Jun 2010351,67770.364.91$10,697
May 2010201,99071.124.24$9,850
Apr 2010511,93781.694.12$12,152
Mar 2010372,35178.394.39$13,218
Feb 2010522,05873.585.44$15,027
Jan 2010342,18874.365.96$15,578
Dec 2009341,69171.445.48$11,702
Nov 2009472,03474.593.75$11,136
Oct 2009421,17672.544.11$7,880
Sep 2009302,50665.543.06$9,646
Aug 2009303,14067.423.22$12,129
Jul 2009523,02461.133.46$13,655
Jun 2009632,49366.163.90$13,878
May 2009483,17454.743.93$15,088
Apr 2009762,81746.773.59$13,661
Mar 2009883,14542.144.06$16,474
Feb 2009633,00532.814.63$15,989
Jan 2009683,39635.865.37$20,678
Dec 2008693,79737.105.98$25,255
Nov 2008913,57155.496.86$29,548
Oct 2008783,76975.246.92$31,958
Sep 2008573,744101.767.88$35,292
Aug 20081044,084114.228.48$46,524
Jul 20081084,543131.0811.39$65,899
Jun 2008833,988131.3313.03$62,875
May 20081304,791123.1711.57$71,465
Apr 20081445,203110.3110.45$70,281
Mar 20081376,203101.909.66$73,907
Feb 20081206,22992.538.77$65,736
Jan 20081166,56390.388.21$64,338
Dec 20071177,83488.337.30$67,538
Nov 20071906,85891.677.29$67,424
Oct 20072469,06782.856.92$83,143
Sep 200723310,84875.846.24$85,407
Aug 200718010,88769.066.39$81,976
Jul 200721710,47870.906.39$82,318
Jun 20073112,12162.007.55$93,417
May 2007305,59258.747.85$45,639
Apr 2007347,18059.617.81$58,068
Mar 200778,39656.927.30$61,706
Feb 20070055.108.22$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             3 bbl  × $106.41 =       $319
Gas                1,286 Mcf  × $  3.05 =     $3,917

────────────────────────────────────────────────────
Month total                                   $4,236

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/228006 is the state's own key, not one this site invented.