BARBEE

Operated by SHERIDAN PRODUCTION CO III, LLC (P-5 775851) in the STOCKMAN, SOUTH (TRAVIS PEAK) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 230576District 06Field 862345002 tax incentive programmesCondensateGasSaveExport
Value, all time
$4.5 M
Jun 2007 – May 2026
Value, last 12 filed months
$24 k
at the published price for each month
Months reported
228
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 26 leases and 26 wells, and the rule below applies to all of them.

Discovered
1984-07-13
as the register files it
Field class
Gas
the register's own label
Between wells
no field rule filed
From a lease line
no field rule filed

The Commission's schedule remark for this field reads: FROM OCTOBER TO DECEMBER.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112008-08-05183062
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition4,068 bbl$302,488
GasProduction772,704 Mcf$4,219,830
Total$4,522,318

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 31.7103, -94.2046. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

31.71031, -94.20462 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
9,300 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 9,300 ft.

Completions filed
Jul 2007
1 of 1 wells

1 well

42-4193114519,300 ftJul 2007

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (228)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

228 months

May 20260414106.413.05$1,261
Apr 2026053798.932.87$1,541
Mar 2026059689.753.15$1,877
Feb 2026050563.503.75$1,894
Jan 2026050859.138.00$4,063
Dec 2025159556.664.41$2,683
Nov 2025158558.593.93$2,356
Oct 2025258659.383.30$2,055
Sep 2025362762.743.08$2,117
Aug 2025050563.933.01$1,522
Jul 2025270366.743.32$2,464
Jun 202526366.483.13$330
May 2025376260.553.23$2,645
Apr 2025272562.363.54$2,693
Mar 2025372067.704.27$3,276
Feb 20251251570.884.34$3,086
Jan 2025052674.324.28$2,251
Dec 2024555868.993.12$2,087
Nov 2024665169.052.20$1,845
Oct 2024977671.372.28$2,413
Sep 2024951969.612.36$1,854
Aug 2024054475.632.06$1,123
Jul 20241150279.932.15$1,957
Jun 20241245178.082.63$2,125
May 2024746978.812.20$1,583
Apr 2024746984.451.66$1,369
Mar 20241650680.301.55$2,067
Feb 20241049276.091.78$1,638
Jan 20241957673.023.30$3,287
Dec 2023551971.262.61$1,711
Nov 2023855877.892.81$2,190
Oct 20233458185.443.09$4,699
Sep 2023851389.042.74$2,115
Aug 2023736380.522.67$1,534
Jul 2023643974.852.64$1,609
Jun 20231649168.962.26$2,212
May 2023452670.622.23$1,454
Apr 2023346578.122.24$1,275
Mar 2023451272.852.39$1,517
Feb 2023942475.112.47$1,721
Jan 2023448276.533.39$1,939
Dec 2022448476.415.73$3,079
Nov 2022434485.005.65$2,282
Oct 2022440187.185.86$2,700
Sep 2022437584.888.16$3,401
Aug 2022842694.529.13$4,644
Jul 20228456101.587.54$4,252
Jun 202210411115.097.98$4,430
May 20225457109.378.43$4,401
Apr 2022684104.226.84$1,200
Mar 202219385108.885.08$4,023
Feb 2022639591.054.86$2,466
Jan 20221244381.844.54$2,992
Dec 20211246271.323.90$2,657
Nov 2021557877.435.24$3,414
Oct 20211443579.795.71$3,603
Sep 2021941569.865.35$2,849
Aug 2021548766.024.22$2,386
Jul 2021656670.783.98$2,679
Jun 20211249769.493.38$2,514
May 2021659163.483.02$2,164
Apr 20212257760.362.76$2,920
Mar 2021064661.302.72$1,755
Feb 20211159457.805.55$3,931
Jan 2021657350.412.81$1,913
Dec 2020660044.642.68$1,873
Nov 20201361038.772.71$2,155
Oct 2020558836.972.48$1,642
Sep 20202056437.091.99$1,865
Aug 20201961139.982.39$2,217
Jul 20201270938.371.83$1,754
Jun 20201761234.901.69$1,628
May 20201678016.921.81$1,686
Apr 20202359714.751.80$1,416
Mar 20202171830.341.86$1,970
Feb 2020221,08749.881.98$3,250
Jan 2020201,57757.252.09$4,448
Dec 20192128459.012.30$1,894
Nov 2019261,14955.302.75$4,598
Oct 2019171,01853.472.42$3,371
Sep 20191178755.052.66$2,697
Aug 201981,06853.112.30$2,886
Jul 20191097856.272.46$2,969
Jun 2019482952.782.49$2,276
May 2019673958.482.74$2,376
Apr 2019470062.632.75$2,176
Mar 2019151756.803.06$1,640
Feb 2019328150.852.79$937
Jan 2019334346.033.23$1,245
Dec 2018535246.594.19$1,706
Nov 201851,15352.934.24$5,150
Oct 201861,57361.443.40$5,714
Sep 201861,12359.543.11$3,848
Aug 2018141,79659.403.07$6,339
Jul 201842,53965.142.93$7,705
Jun 201841,52160.183.08$4,921
May 201802,44665.382.90$7,095
Apr 201842,18263.842.90$6,585
Mar 201852,28661.222.79$6,677
Feb 2018211,88361.782.77$6,506
Jan 201852,45162.874.01$10,141
Dec 2017142,51257.272.92$8,141
Nov 201761,96455.423.12$6,457
Oct 201731,04149.292.98$3,254
Sep 2017421847.523.09$863
Aug 2017291,30545.373.00$5,236
Jul 2017152,86443.873.09$9,500
Jun 2017161,66842.493.09$5,829
May 2017142,46645.373.26$8,683
Apr 2017172,32147.933.21$8,269
Mar 2017162,32246.772.98$7,676
Feb 2017172,13150.452.95$7,150
Jan 2017232,81549.413.42$10,760
Dec 2016232,84348.763.72$11,705
Nov 2016131,70142.492.64$5,050
Oct 2016343,84846.193.09$13,462
Sep 2016223,63141.553.10$12,172
Aug 201601,75941.442.92$5,144
Jul 2016093041.622.92$2,720
Jun 201601,00545.352.69$2,699
May 2016086542.521.99$1,722
Apr 2016073636.561.99$1,465
Mar 2016081833.011.79$1,468
Feb 2016081826.472.06$1,688
Jan 2016092327.352.36$2,182
Dec 201502,14732.362.00$4,297
Nov 201502,85638.792.17$6,190
Oct 201502,68743.552.43$6,520
Sep 201503,29742.992.76$9,095
Aug 201502,36740.162.87$6,799
Jul 201502,60448.152.95$7,669
Jun 201503,79856.152.88$10,949
May 201503,25455.212.96$9,617
Apr 201503,14049.822.71$8,499
Mar 201503,06042.892.93$8,980
Feb 201503,39244.662.98$10,095
Jan 201504,46843.433.10$13,854
Dec 201403,99154.693.59$14,333
Nov 201401,87370.464.25$7,964
Oct 201402,65378.303.90$10,349
Sep 201401,76286.164.05$7,128
Aug 201401,50389.394.04$6,065
Jul 201401,99596.564.18$8,338
Jun 201402,62398.164.74$12,425
May 201402,65094.734.73$12,525
Apr 201402,80895.944.81$13,504
Mar 201403,13595.895.06$15,853
Feb 201401,02297.406.19$6,328
Jan 201401,95490.404.86$9,498
Dec 201303,16191.824.35$13,765
Nov 201303,18088.853.74$11,888
Oct 201303,06697.423.78$11,588
Sep 201302,874104.113.72$10,685
Aug 201302,898104.253.52$10,209
Jul 201303,249102.523.72$12,079
Jun 201302,98494.403.93$11,737
May 201303,21694.834.15$13,343
Apr 201302,81993.964.28$12,073
Mar 201303,32393.623.91$13,002
Feb 201303,13591.233.42$10,721
Jan 201303,31291.603.42$11,327
Dec 201203,50286.773.42$11,977
Nov 201203,29986.953.62$11,959
Oct 201203,88589.383.40$13,208
Sep 201204,00094.672.92$11,674
Aug 201204,48492.662.91$13,040
Jul 201204,19585.133.02$12,672
Jun 201202,32279.822.52$5,849
May 201203,97291.612.49$9,884
Apr 201204,309101.652.00$8,604
Mar 201204,592105.052.22$10,204
Feb 201204,810101.102.57$12,363
Jan 201205,76498.092.73$15,759
Dec 201105,78896.873.24$18,752
Nov 201103,58095.723.31$11,854
Oct 201102,85484.983.65$10,413
Sep 201106,55183.623.99$26,111
Aug 201106,12083.404.15$25,394
Jul 201102,41294.144.52$10,896
Jun 201102,83792.904.64$13,163
May 201103,39398.134.40$14,946
Apr 201102,153105.964.33$9,330
Mar 201101,75696.364.06$7,125
Feb 201104,16285.644.18$17,397
Jan 201105,00186.504.59$22,948
Dec 201004,10585.734.35$17,848
Nov 201006,62380.843.80$25,136
Oct 201004,69178.103.51$16,460
Sep 201003,89672.633.98$15,504
Aug 201003,36473.684.42$14,867
Jul 201004,16972.554.74$19,746
Jun 201001,46070.364.91$7,169
May 2010442,17971.124.24$12,358
Apr 201002,82881.694.12$11,659
Mar 20101315,75578.394.39$35,526
Feb 201005,51773.585.44$30,026
Jan 20101836,28274.365.96$51,074
Dec 200904,80971.445.48$26,371
Nov 200905,51774.593.75$20,697
Oct 200907,03872.544.11$28,928
Sep 200907,14065.543.06$21,882
Aug 20091707,81267.423.22$36,604
Jul 200907,59661.133.46$26,316
Jun 200908,38966.163.90$32,675
May 20091808,77154.743.93$44,286
Apr 20091799,11246.773.59$41,061
Mar 2009010,16442.144.06$41,256
Feb 2009010,00732.814.63$46,362
Jan 2009012,16135.865.37$65,317
Dec 200818912,47337.105.98$81,565
Nov 2008012,58355.496.86$86,324
Oct 200817615,32175.246.92$119,294
Sep 2008016,777101.767.88$132,154
Aug 200818214,272114.228.48$141,858
Jul 2008013,826131.0811.39$157,470
Jun 2008014,561131.3313.03$189,768
May 200818315,311123.1711.57$199,754
Apr 20082314,116110.3110.45$150,118
Mar 20082517,204101.909.66$168,808
Feb 200838515,62592.538.77$172,664
Jan 20083723,97390.388.21$200,060
Dec 200717425,93088.337.30$204,710
Nov 200714817,20891.677.29$139,043
Oct 200719122,40882.856.92$170,932
Sep 200736735,62775.846.24$250,294
Aug 2007013,69769.066.39$87,496
Jul 200708,59470.906.39$54,898
Jun 2007032162.007.55$2,423

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                  414 Mcf  × $  3.05 =     $1,261

────────────────────────────────────────────────────
Month total                                   $1,261

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/230576 is the state's own key, not one this site invented.