INGRAM 2 UNIT

Operated by DIVERSIFIED PRODUCTION LLC (P-5 220903) in the CARTHAGE (COTTON VALLEY) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 237977District 06Field 160321742 tax incentive programmesCondensateGasSaveExport
Value, all time
$3.4 M
May 2008 – May 2026
Value, last 12 filed months
$92 k
at the published price for each month
Months reported
217
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 4,104 leases and 4,104 wells, and the rule below applies to all of them.

Discovered
1968-05-01
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2011-02-08.

The Commission's schedule remark for this field reads: FIELD. EFFECTIVE 4/12/16.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112008-09-17185673
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition7,432 bbl$572,537
GasProduction661,805 Mcf$2,855,410
Total$3,427,947

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.0572, -94.2906. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.05716, -94.29056 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
9,460 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 9,460 ft.

Completions filed
May 2008
1 of 1 wells

1 well

42-36536870109,460 ftMay 2008

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (217)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

217 months

May 202661,815106.413.05$6,167
Apr 202601,85598.932.87$5,323
Mar 2026441,81689.753.15$9,668
Feb 202671,71163.503.75$6,861
Jan 202601,72959.138.00$13,828
Dec 2025221,62056.664.41$8,396
Nov 202501,57958.593.93$6,200
Oct 202501,49659.383.30$4,944
Sep 2025361,96862.743.08$8,314
Aug 202502,04263.933.01$6,156
Jul 202502,03366.743.32$6,740
Jun 2025481,85766.483.13$9,001
May 202501,95760.553.23$6,326
Apr 202501,91862.363.54$6,796
Mar 2025381,96967.704.27$10,977
Feb 202501,78270.884.34$7,735
Jan 2025191,88974.324.28$9,495
Dec 2024392,00568.993.12$8,949
Nov 202401,91669.052.20$4,212
Oct 2024281,96271.372.28$6,474
Sep 202401,91669.612.36$4,530
Aug 2024251,91975.632.06$5,851
Jul 202401,93379.932.15$4,149
Jun 2024911,86978.082.63$12,028
May 202471,70378.812.20$4,296
Apr 2024851,53484.451.66$9,723
Mar 202491,88580.301.55$3,635
Feb 2024141,17476.091.78$3,159
Jan 202401,46973.023.30$4,844
Dec 202301,89071.262.61$4,934
Nov 2023422,01777.892.81$8,934
Oct 202301,55385.443.09$4,795
Sep 202301,74789.042.74$4,778
Aug 202301,38680.522.67$3,705
Jul 2023452,11974.852.64$8,966
Jun 202302,14268.962.26$4,838
May 202302,21770.622.23$4,938
Apr 202302,14178.122.24$4,791
Mar 2023842,19272.852.39$11,365
Feb 202301,96775.112.47$4,850
Jan 202302,26476.533.39$7,670
Dec 202202,39576.415.73$13,721
Nov 202202,30785.005.65$13,026
Oct 202202,29987.185.86$13,481
Sep 202202,30884.888.16$18,842
Aug 202202,51294.529.13$22,927
Jul 202202,582101.587.54$19,474
Jun 2022432,268115.097.98$23,041
May 202202,543109.378.43$21,445
Apr 202202,374104.226.84$16,232
Mar 2022532,472108.885.08$18,320
Feb 2022502,25491.054.86$15,504
Jan 202202,52481.844.54$11,453
Dec 2021302,61271.323.90$12,324
Nov 2021492,49877.435.24$16,876
Oct 202112,44979.795.71$14,073
Sep 202102,38469.865.35$12,757
Aug 2021462,40666.024.22$13,192
Jul 202102,43870.783.98$9,708
Jun 2021412,36469.493.38$10,841
May 202112,39363.483.02$7,285
Apr 2021412,33560.362.76$8,916
Mar 202102,38461.302.72$6,477
Feb 202102,30857.805.55$12,805
Jan 202102,59650.412.81$7,295
Dec 2020392,55644.642.68$8,579
Nov 202002,41138.772.71$6,526
Oct 202002,49836.972.48$6,191
Sep 2020392,56237.091.99$6,548
Aug 202002,77839.982.39$6,626
Jul 202002,54438.371.83$4,643
Jun 202002,42034.901.69$4,091
May 2020342,49416.921.81$5,101
Apr 202002,75714.751.80$4,975
Mar 2020352,85130.341.86$6,354
Feb 202002,71849.881.98$5,383
Jan 2020332,89457.252.09$7,951
Dec 2019342,84859.012.30$8,569
Nov 201902,75155.302.75$7,567
Oct 2019332,78053.472.42$8,488
Sep 201902,05955.052.66$5,471
Aug 201902,02953.112.30$4,676
Jul 2019272,27756.272.46$7,121
Jun 201901,88952.782.49$4,706
May 2019291,92258.482.74$6,963
Apr 2019302,27162.632.75$8,126
Mar 201902,49456.803.06$7,637
Feb 2019282,13050.852.79$7,371
Jan 2019242,34346.033.23$8,668
Dec 2018221,93446.594.19$9,120
Nov 201802,57952.934.24$10,928
Oct 2018262,71061.443.40$10,806
Sep 201802,26059.543.11$7,024
Aug 2018212,85459.403.07$9,999
Jul 201803,03765.142.93$8,904
Jun 2018262,92760.183.08$10,571
May 201803,15965.382.90$9,164
Apr 2018273,10363.842.90$10,725
Mar 2018263,19161.222.79$10,485
Feb 201802,93661.782.77$8,121
Jan 2018262,50962.874.01$11,694
Dec 2017273,09757.272.92$10,594
Nov 2017103,04555.423.12$10,050
Oct 201703,35349.292.98$10,004
Sep 201763,18247.523.09$10,109
Aug 201703,30145.373.00$9,918
Jul 201713,22743.873.09$10,007
Jun 201733,12742.493.09$9,781
May 201733,13545.373.26$10,367
Apr 201732,43047.933.21$7,948
Mar 201733,03646.772.98$9,199
Feb 201762,70050.452.95$8,275
Jan 2017153,11049.413.42$11,374
Dec 2016143,24948.763.72$12,778
Nov 201601,71642.492.64$4,538
Oct 20162099246.193.09$3,989
Sep 201601,28141.553.10$3,972
Aug 2016083941.442.92$2,454
Jul 2016642,84341.622.92$10,978
Jun 201633,04545.352.69$8,314
May 2016933,22342.521.99$10,371
Apr 201623,20536.561.99$6,454
Mar 2016863,09933.011.79$8,399
Feb 201633,22126.472.06$6,726
Jan 2016833,52227.352.36$10,597
Dec 2015793,49632.362.00$9,553
Nov 201533,57038.792.17$7,854
Oct 2015713,57943.552.43$11,777
Sep 201523,53842.992.76$9,845
Aug 2015653,62740.162.87$13,029
Jul 201553,33848.152.95$10,071
Jun 201563,09856.152.88$9,268
May 2015593,27155.212.96$12,925
Apr 2015443,23249.822.71$10,940
Mar 201593,52342.892.93$10,725
Feb 2015473,40544.662.98$12,233
Jan 2015533,32143.433.10$12,599
Dec 2014113,10154.693.59$11,738
Nov 2014452,69570.464.25$14,629
Oct 201461,90478.303.90$7,897
Sep 2014382,23486.164.05$12,312
Aug 201422,65889.394.04$10,904
Jul 2014372,36696.564.18$13,462
Jun 201411,83098.164.74$8,767
May 2014412,02094.734.73$13,432
Apr 2014432,07695.944.81$14,109
Mar 201422,26695.895.06$11,650
Feb 2014421,92497.406.19$16,004
Jan 2014382,11490.404.86$13,711
Dec 2013462,06291.824.35$13,203
Nov 2013472,34088.853.74$12,924
Oct 201372,29197.423.78$9,340
Sep 2013432,442104.113.72$13,555
Aug 2013472,680104.253.52$14,340
Jul 201362,025102.523.72$8,144
Jun 2013461,73994.403.93$11,183
May 201381,92594.834.15$8,746
Apr 2013351,95193.964.28$11,644
Mar 2013351,38893.623.91$8,708
Feb 2013431,64891.233.42$9,559
Jan 2013442,38991.603.42$12,201
Dec 2012432,78986.773.42$13,270
Nov 2012382,17686.953.62$11,192
Oct 201252,27789.383.40$8,188
Sep 2012352,24794.672.92$9,871
Aug 2012343,53992.662.91$13,442
Jul 2012392,52385.133.02$10,942
Jun 201262,98479.822.52$7,996
May 201292,84691.612.49$7,906
Apr 2012671,807101.652.00$10,419
Mar 2012733,359105.052.22$15,133
Feb 2012783,192101.102.57$16,090
Jan 20121472,25898.092.73$20,593
Dec 201182,59796.873.24$9,189
Nov 20111052,97995.723.31$19,915
Oct 201153,32284.983.65$12,545
Sep 2011463,17683.623.99$16,505
Aug 2011413,98983.404.15$19,971
Jul 2011353,71094.144.52$20,054
Jun 201143,90192.904.64$18,472
May 201144,02998.134.40$18,140
Apr 2011253,699105.964.33$18,678
Mar 2011253,93796.364.06$18,383
Feb 2011253,04685.644.18$14,873
Jan 2011273,46586.504.59$18,236
Dec 2010723,85285.734.35$22,920
Nov 201043,74680.843.80$14,541
Oct 20101434,22778.103.51$26,000
Sep 2010724,27172.633.98$22,226
Aug 2010765,14273.684.42$28,324
Jul 2010734,89272.554.74$28,467
Jun 2010653,46070.364.91$21,563
May 20101003,32771.124.24$21,203
Apr 2010885,66981.694.12$30,560
Mar 2010325,79078.394.39$27,919
Feb 2010875,30773.585.44$35,284
Jan 2010675,25174.365.96$36,300
Dec 2009726,50971.445.48$40,837
Nov 2009895,59974.593.75$27,643
Oct 2009935,49572.544.11$29,332
Sep 2009875,46565.543.06$22,451
Aug 20091626,24567.423.22$31,022
Jul 2009563,77661.133.46$16,505
Jun 2009635,83566.163.90$26,895
May 2009626,22454.743.93$27,828
Apr 20091076,51446.773.59$28,373
Mar 2009993,39242.144.06$17,940
Feb 20091146,06332.814.63$31,830
Jan 20091237,08735.865.37$42,475
Dec 2008716,69137.105.98$42,627
Nov 20081287,40655.496.86$57,911
Oct 2008688,45675.246.92$63,649
Sep 20081196,064101.767.88$59,876
Aug 20081259,515114.228.48$94,993
Jul 200817610,985131.0811.39$148,183
Jun 200835614,035131.3313.03$229,666
May 200825515,188123.1711.57$207,199

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             6 bbl  × $106.41 =       $638
Gas                1,815 Mcf  × $  3.05 =     $5,528

────────────────────────────────────────────────────
Month total                                   $6,167

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/237977 is the state's own key, not one this site invented.