Operated by DIVERSIFIED PRODUCTION LLC (P-5 220903) in the WASKOM (COTTON VALLEY) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 244091District 06Field 953691602 tax incentive programmesCondensateGasSaveExport
Value, all time
$13.0 M
Jul 2008 – May 2026
Value, last 12 filed months
$296 k
at the published price for each month
Months reported
215
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 473 leases and 477 wells, and the rule below applies to all of them.

Discovered
1955-09-19
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2012-11-06.

The Commission's schedule remark for this field reads: DESIGNATED AS UFT FIELD PER DOCKET 01-0299858

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112009-02-10187872
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition9,140 bbl$596,922
GasProduction2,838,602 Mcf$12,394,522
Total$12,991,443

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.4490, -94.0791. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.44898, -94.07913 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
9,329 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 9,329 ft.

Completions filed
Aug 2008
1 of 1 wells

1 well

42-2033415911H9,329 ftAug 2008

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (215)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

215 months

May 202607,244106.413.05$22,064
Apr 202606,50998.932.87$18,679
Mar 202606,42589.753.15$20,235
Feb 202605,96663.503.75$22,374
Jan 202606,65859.138.00$53,250
Dec 202506,02356.664.41$26,582
Nov 202506,30058.593.93$24,737
Oct 202507,25159.383.30$23,963
Sep 202506,93362.743.08$21,332
Aug 202506,70963.933.01$20,226
Jul 202506,61366.743.32$21,923
Jun 202506,51366.483.13$20,377
May 202506,58860.553.23$21,295
Apr 202506,70762.363.54$23,764
Mar 202506,78067.704.27$28,939
Feb 202505,79870.884.34$25,168
Jan 202507,48774.324.28$32,034
Dec 202407,12068.993.12$22,224
Nov 202406,14369.052.20$13,505
Oct 202406,78871.372.28$15,486
Sep 202406,92769.612.36$16,378
Aug 202406,79775.632.06$14,026
Jul 202406,71679.932.15$14,417
Jun 202406,38578.082.63$16,818
May 202407,82178.812.20$17,194
Apr 202407,44984.451.66$12,359
Mar 202408,19080.301.55$12,655
Feb 202407,36676.091.78$13,138
Jan 202407,73873.023.30$25,517
Dec 202307,41671.262.61$19,361
Nov 202307,64777.892.81$21,469
Oct 202308,31785.443.09$25,677
Sep 202307,36189.042.74$20,133
Aug 202308,20780.522.67$21,936
Jul 202308,49474.852.64$22,439
Jun 202307,96168.962.26$17,980
May 202308,61970.622.23$19,198
Apr 202307,85578.122.24$17,578
Mar 202309,15672.852.39$21,912
Feb 202308,58875.112.47$21,175
Jan 202309,68776.533.39$32,817
Dec 202208,78476.415.73$50,324
Nov 202208,89985.005.65$50,246
Oct 202209,15587.185.86$53,683
Sep 202208,68284.888.16$70,877
Aug 202208,90494.529.13$81,268
Jul 202208,960101.587.54$67,577
Jun 202208,714115.097.98$69,513
May 202208,953109.378.43$75,501
Apr 202208,743104.226.84$59,781
Mar 202209,075108.885.08$46,068
Feb 202208,14791.054.86$39,585
Jan 202209,64281.844.54$43,752
Dec 202109,30271.323.90$36,270
Nov 202108,96077.435.24$46,922
Oct 202108,98579.795.71$51,339
Sep 202109,24169.865.35$49,448
Aug 202109,69966.024.22$40,936
Jul 202108,70170.783.98$34,648
Jun 202108,52769.493.38$28,827
May 202108,92063.483.02$26,918
Apr 202109,11660.362.76$25,146
Mar 202109,79861.302.72$26,621
Feb 202107,54257.805.55$41,843
Jan 202109,25450.412.81$26,006
Dec 202009,41944.642.68$25,200
Nov 202008,79738.772.71$23,810
Oct 202009,47936.972.48$23,493
Sep 202008,23437.091.99$16,394
Aug 202008,63039.982.39$20,583
Jul 202007,44838.371.83$13,593
Jun 202006,87734.901.69$11,624
May 202006,95616.921.81$12,623
Apr 202006,69814.751.80$12,086
Mar 202006,82430.341.86$12,667
Feb 202006,40949.881.98$12,694
Jan 202004,22957.252.09$8,859
Dec 201904,40159.012.30$10,141
Nov 201904,27655.302.75$11,762
Oct 201904,43553.472.42$10,726
Sep 201904,34855.052.66$11,554
Aug 201904,54353.112.30$10,469
Jul 201904,67156.272.46$11,491
Jun 201904,55552.782.49$11,347
May 201904,68658.482.74$12,841
Apr 201904,51762.632.75$12,425
Mar 201904,57756.803.06$14,015
Feb 201904,37450.852.79$12,213
Jan 201904,99446.033.23$16,122
Dec 201804,79446.594.19$20,065
Nov 201804,85452.934.24$20,568
Oct 201815,18161.443.40$17,667
Sep 201804,89359.543.11$15,207
Aug 2018284,97959.403.07$16,932
Jul 2018205,01665.142.93$16,009
Jun 2018314,96260.183.08$17,133
May 2018195,24465.382.90$16,454
Apr 201805,15963.842.90$14,965
Mar 2018615,53561.222.79$19,160
Feb 2018455,27261.782.77$17,363
Jan 2018375,72362.874.01$25,272
Dec 2017246,13757.272.92$19,304
Nov 2017155,89055.423.12$19,198
Oct 20171036,62349.292.98$24,838
Sep 2017426,44247.523.09$21,884
Aug 2017356,88645.373.00$22,276
Jul 2017325,52843.873.09$18,470
Jun 201701,80642.493.09$5,576
May 201704,86345.373.26$15,870
Apr 201704,81547.933.21$15,464
Mar 201734,82546.772.98$14,537
Feb 2017134,83750.452.95$14,938
Jan 2017225,46549.413.42$19,771
Dec 2016135,53648.763.72$21,243
Nov 2016205,20842.492.64$14,622
Oct 2016205,22546.193.09$17,070
Sep 2016145,29641.553.10$17,003
Aug 2016146,58741.442.92$19,843
Jul 2016216,86641.622.92$20,953
Jun 201606,94045.352.69$18,640
May 2016297,75142.521.99$16,666
Apr 2016277,43236.561.99$15,785
Mar 2016367,76633.011.79$15,121
Feb 2016557,41226.472.06$16,751
Jan 2016688,28427.352.36$21,446
Dec 2015678,34532.362.00$18,870
Nov 2015698,17338.792.17$20,390
Oct 2015758,56343.552.43$24,045
Sep 2015758,20342.992.76$25,852
Aug 2015698,33740.162.87$26,719
Jul 201508,63348.152.95$25,425
Jun 2015638,62556.152.88$28,402
May 20155818,05255.212.96$56,554
Apr 20154916,77749.822.71$47,849
Mar 20154317,28242.892.93$52,562
Feb 20155715,61544.662.98$49,019
Jan 20156714,82243.433.10$48,867
Dec 20147315,28754.693.59$58,893
Nov 20147014,56370.464.25$66,852
Oct 20148013,78878.303.90$60,050
Sep 20148512,59186.164.05$58,260
Aug 20147913,33789.394.04$60,878
Jul 20146313,53596.564.18$62,654
Jun 20146313,35898.164.74$69,459
May 201413014,11894.734.73$79,044
Apr 2014012,95495.944.81$62,297
Mar 201411215,40995.895.06$88,660
Feb 20144111,31097.406.19$74,025
Jan 20145817,78890.404.86$91,706
Dec 20133118,08291.824.35$81,584
Nov 20133116,32988.853.74$63,797
Oct 20135616,33497.423.78$67,188
Sep 20133014,656104.113.72$57,611
Aug 20134214,578104.253.52$55,731
Jul 20133115,377102.523.72$60,346
Jun 20133313,73394.403.93$57,133
May 20136415,46994.834.15$70,251
Apr 20133510,37393.964.28$47,712
Mar 20135510,79293.623.91$47,377
Feb 20131910,87691.233.42$38,928
Jan 20133910,70991.603.42$40,196
Dec 20122110,83586.773.42$38,880
Nov 20124311,79086.953.62$46,477
Oct 20122116,34289.383.40$57,435
Sep 20125913,16294.672.92$43,998
Aug 20127012,87592.662.91$43,929
Jul 20123919,87785.133.02$63,365
Jun 20124121,47079.822.52$57,356
May 20127825,24891.612.49$69,971
Apr 20128021,892101.652.00$51,846
Mar 20124219,341105.052.22$47,389
Feb 20122317,285101.102.57$46,752
Jan 201212098.092.73$1,177
Dec 2011288,85096.873.24$31,384
Nov 20113713,22295.723.31$47,323
Oct 20114215,54584.983.65$60,286
Sep 20119814,54183.623.99$66,152
Aug 20118215,18383.404.15$69,838
Jul 2011014,14394.144.52$63,887
Jun 201109,61392.904.64$44,603
May 20115813,07998.134.40$63,302
Apr 201104,706105.964.33$20,392
Mar 20115413,31896.364.06$59,239
Feb 20116117,61885.644.18$78,867
Jan 20117621,12386.504.59$103,503
Dec 2010019,91785.734.35$86,594
Nov 201013019,23380.843.80$83,505
Oct 201014220,03378.103.51$81,384
Sep 2010018,99472.633.98$75,586
Aug 2010021,84573.684.42$96,541
Jul 201030819,70772.554.74$115,687
Jun 2010021,94270.364.91$107,744
May 201014823,30071.124.24$109,206
Apr 201014723,18581.694.12$107,593
Mar 201013224,37278.394.39$117,308
Feb 201012423,01173.585.44$134,358
Jan 201025026,03574.365.96$173,865
Dec 200925927,53971.445.48$169,520
Nov 200921326,46074.593.75$115,152
Oct 200921629,32272.544.11$136,189
Sep 2009029,89665.543.06$91,624
Aug 20099832,50767.423.22$111,231
Jul 200916034,02461.133.46$127,657
Jun 200947034,54366.163.90$165,640
May 2009036,48454.743.93$143,227
Apr 200917638,23846.773.59$145,410
Mar 200946542,00242.144.06$190,081
Feb 200934340,63132.814.63$199,497
Jan 200934649,30935.865.37$277,246
Dec 200846354,90237.105.98$345,334
Nov 200845058,33555.496.86$425,170
Oct 200811877,79475.246.92$547,367
Sep 20085799,531101.767.88$789,815
Aug 20080173,962114.228.48$1,475,723
Jul 200801,354131.0811.39$15,421

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                7,244 Mcf  × $  3.05 =    $22,064

────────────────────────────────────────────────────
Month total                                  $22,064

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/244091 is the state's own key, not one this site invented.