JAGUAR GAS UNIT 1

Operated by ROCKCLIFF ENERGY OPERATING LLC (P-5 722890) in the RED LAND,NORTH (TRAVIS PEAK) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 253356District 06Field 753255002 tax incentive programmesCondensateGasSaveExport
Value, all time
$3.2 M
Sep 2009 – Jan 2022
Value, last 12 filed months
$0
at the published price for each month
Months reported
147
2 months not filed
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 24 leases and 24 wells, and the rule below applies to all of them.

Discovered
1980-12-29
as the register files it
Field class
Gas
the register's own label
Between wells
1,200 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2006-01-10.

The Commission's schedule remark for this field reads: ALLOCATION FORMULA REMAINS SUSPENDED.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112011-02-28201508
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition346 bbl$25,792
GasProduction766,611 Mcf$3,137,079
Total$3,162,871

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 31.5065, -94.6984. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

31.50652, -94.69837 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
11,515 ft
1 wells filed one
Completion to plug
12.1 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 11,515 ft.

Completions filed
Sep 2009
1 of 1 wells
Plug dates filed
Oct 2021
1 of 1 wells

Last completion to plug: a median of 12.1 years across the 1 well that filed both dates, with the middle half between 12.1 years and 12.1 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-34733101111,515 ftSep 2009Oct 2021Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (147)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

147 months

Jan 20220081.844.54$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20190056.803.06$0
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 20180059.543.11$0
Aug 20180059.403.07$0
Jul 20180065.142.93$0
Jun 20180060.183.08$0
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 201713047.523.09$618
Aug 20170045.373.00$0
Jul 20170043.873.09$0
Jun 20170042.493.09$0
May 20170045.373.26$0
Apr 20170047.933.21$0
Mar 20170046.772.98$0
Feb 20170050.452.95$0
Jan 20170049.413.42$0
Dec 20160048.763.72$0
Nov 20160042.492.64$0
Oct 20160046.193.09$0
Sep 20160041.553.10$0
Aug 20160041.442.92$0
Jul 20160041.622.92$0
Jun 20160045.352.69$0
May 20160042.521.99$0
Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 20160026.472.06$0
Jan 20160027.352.36$0
Dec 20150032.362.00$0
Nov 20150038.792.17$0
Oct 20150043.552.43$0
Sep 20150042.992.76$0
Aug 20150040.162.87$0
Jul 20150048.152.95$0
Jun 20150056.152.88$0
May 201527455.212.96$1,502
Apr 20150049.822.71$0
Mar 20150042.892.93$0
Feb 20150044.662.98$0
Jan 20150043.433.10$0
Dec 20140054.693.59$0
Nov 20140070.464.25$0
Oct 20140078.303.90$0
Sep 20140086.164.05$0
Aug 20140089.394.04$0
Jul 20140096.564.18$0
Jun 20140098.164.74$0
May 20140094.734.73$0
Apr 20140095.944.81$0
Mar 20140195.895.06$5
Feb 20140097.406.19$0
Jan 20140690.404.86$29
Dec 20130091.824.35$0
Nov 20130088.853.74$0
Oct 20130097.423.78$0
Sep 201300104.113.72$0
Aug 201301104.253.52$4
Jul 2013036102.523.72$134
Jun 201303894.403.93$149
May 20130094.834.15$0
Apr 20130093.964.28$0
Mar 201301393.623.91$51
Feb 20130091.233.42$0
Jan 2013013691.603.42$465
Dec 201205,72986.773.42$19,594
Nov 201209,74686.953.62$35,329
Oct 2012011,52189.383.40$39,168
Sep 201206,38794.672.92$18,640
Aug 201209,89792.662.91$28,782
Jul 2012011,75885.133.02$35,519
Jun 201208,59679.822.52$21,654
May 2012010,11691.612.49$25,172
Apr 2012012,960101.652.00$25,879
Mar 201208,252105.052.22$18,337
Feb 2012012,449101.102.57$31,997
Jan 2012010,50298.092.73$28,713
Dec 2011012,39496.873.24$40,153
Nov 2011012,17895.723.31$40,325
Oct 2011013,13484.983.65$47,920
Sep 2011013,16583.623.99$52,473
Aug 201111914,71483.404.15$70,978
Jul 2011014,51894.144.52$65,581
Jun 2011014,01792.904.64$65,037
May 2011015,46998.134.40$68,138
Apr 2011015,893105.964.33$68,869
Mar 2011016,10596.364.06$65,343
Feb 2011013,18085.644.18$55,092
Jan 2011016,65086.504.59$76,403
Dec 2010016,05185.734.35$69,786
Nov 2010018,59480.843.80$70,570
Oct 2010019,17978.103.51$67,297
Sep 2010021,23272.633.98$84,492
Aug 2010022,38573.684.42$98,927
Jul 2010023,64772.554.74$112,004
Jun 2010027,28170.364.91$133,961
May 2010025,87871.124.24$109,599
Apr 2010023,12481.694.12$95,333
Mar 2010026,47578.394.39$116,190
Feb 201018719,16273.585.44$118,046
Jan 2010030,63474.365.96$182,704
Dec 2009036,88371.445.48$202,257
Nov 2009052,05574.593.75$195,284
Oct 20090102,87872.544.11$422,854
Sep 2009011,58865.543.06$35,514

Not filed, and not zero: Nov 2021 – Dec 2021 (2 months). The Railroad Commission holds no report for those months, so this page shows none — a zero would state that the lease produced nothing.

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Sep 2017 — as filed, then multipliedworked
Condensate            13 bbl  × $ 47.52 =       $618
Gas                    0 Mcf  × $  3.09 =         $0

────────────────────────────────────────────────────
Month total                                     $618

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 06/G/253356 is the state's own key, not one this site invented.