UNIVERSITY 12-14

Operated by BIG D ENERGY COMPANY (P-5 69344) in the SHAFTER LAKE (YATES) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 153217District 08Field 82570700CondensateGasSaveExport
Value, all time
$118 k
Jul 1994 – Dec 2008
Value, last 12 filed months
$7 k
at the published price for each month
Months reported
174
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 136 leases and 215 wells, and the rule below applies to all of them.

Discovered
1952-03-16
as the register files it
Field class
Oil and gas
the register's own label
Between wells
no field rule filed
From a lease line
no field rule filed

The Commission's schedule remark for this field reads: 9/30/97

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition68 bbl$7,237
GasProduction34,931 Mcf$110,912
Total$118,149

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 32.3412, -102.6887. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

32.34119, -102.68868 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
3,220 ft
1 wells filed one
Completion to plug
10.4 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 3,220 ft.

Completions filed
Jun 1997
1 of 1 wells
Plug dates filed
Nov 2007
1 of 1 wells

Last completion to plug: a median of 10.4 years across the 1 well that filed both dates, with the middle half between 10.4 years and 10.4 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-0033749813,220 ftJun 1997Nov 2007Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (174)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

174 months

Dec 20080037.105.98$0
Nov 20080055.496.86$0
Oct 20080075.246.92$0
Sep 200800101.767.88$0
Aug 2008590114.228.48$6,739
Jul 200800131.0811.39$0
Jun 200800131.3313.03$0
May 200800123.1711.57$0
Apr 200800110.3110.45$0
Mar 200800101.909.66$0
Feb 20080092.538.77$0
Jan 20080090.388.21$0
Dec 20070088.337.30$0
Nov 20075691.677.29$502
Oct 20070082.856.92$0
Sep 20070075.846.24$0
Aug 20070069.066.39$0
Jul 20070070.906.39$0
Jun 20070062.007.55$0
May 20070058.747.85$0
Apr 20070059.617.81$0
Mar 20070056.927.30$0
Feb 20070055.108.22$0
Jan 20070050.306.73$0
Dec 2006018556.656.92$1,280
Nov 2006019954.207.62$1,516
Oct 2006012554.906.01$752
Sep 2006013860.085.04$695
Aug 2006010668.717.34$778
Jul 2006013169.376.34$831
Jun 2006010766.286.38$683
May 200609466.016.42$604
Apr 200603764.397.36$272
Mar 200602056.707.08$142
Feb 200608257.597.75$636
Jan 200602460.598.93$214
Dec 200507854.9413.42$1,046
Nov 200505554.6910.59$582
Oct 200508258.3413.80$1,131
Sep 200503561.4512.08$423
Aug 200502561.519.80$245
Jul 200505055.697.84$392
Jun 200505252.337.38$384
May 200507645.226.65$505
Apr 200503249.207.36$236
Mar 200504150.377.15$293
Feb 20050345.226.31$19
Jan 200503243.166.32$202
Dec 200405839.866.75$392
Nov 200406245.286.33$392
Oct 200405649.706.52$365
Sep 200406843.245.28$359
Aug 200406742.375.55$372
Jul 200407338.286.08$444
Jun 200407036.106.43$450
May 2004010937.486.49$708
Apr 200406634.475.86$387
Mar 2004012034.365.53$664
Feb 200409432.455.51$518
Jan 2004011732.036.30$737
Dec 200302230.266.30$139
Nov 200303928.804.60$179
Oct 200307128.174.76$338
Sep 200309926.314.75$470
Aug 2003012129.765.13$621
Jul 2003012929.415.17$667
Jun 200307928.565.98$473
May 200308426.595.97$502
Apr 2003014326.675.41$773
Mar 200307631.146.10$463
Feb 2003016833.487.93$1,332
Jan 2003010730.315.58$597
Dec 2002029826.914.85$1,446
Nov 2002028224.664.14$1,167
Oct 2002023626.464.23$998
Sep 2002024927.443.64$905
Aug 2002024525.963.16$775
Jul 2002022024.583.06$674
Jun 2002014423.733.34$481
May 2002019324.663.58$692
Apr 2002020423.653.51$717
Mar 2002015822.003.10$490
Feb 2002015118.222.38$359
Jan 200209617.172.38$228
Dec 2001016516.932.36$390
Nov 2001012818.072.41$308
Oct 2001011919.782.53$301
Sep 2001012824.262.25$288
Aug 2001018724.873.05$571
Jul 20010023.933.20$0
Jun 200106224.563.82$237
May 2001010925.524.31$470
Apr 200109824.685.34$523
Mar 200107024.545.38$376
Feb 200105627.755.77$323
Jan 200107227.478.40$605
Dec 2000015726.889.12$1,432
Nov 2000012232.215.66$690
Oct 2000019031.235.15$978
Sep 2000014231.875.19$736
Aug 200007029.644.54$318
Jul 2000012228.534.09$499
Jun 200008529.304.40$374
May 20000027.263.68$0
Apr 200005624.513.12$175
Mar 200002128.422.86$60
Feb 200001527.622.73$41
Jan 200001,23725.272.48$3,068
Dec 199901324.282.42$32
Nov 1999014823.192.43$360
Oct 199907020.982.80$196
Sep 199907621.752.62$199
Aug 1999016519.262.88$474
Jul 1999010517.892.37$249
Jun 1999014515.942.36$343
May 1999012315.792.32$285
Apr 1999013615.102.21$300
Mar 1999018612.471.84$342
Feb 199942699.981.82$529
Jan 1999027410.381.90$521
Dec 199804049.201.77$716
Nov 199802310.892.19$50
Oct 1998014412.421.97$284
Sep 1998020712.592.08$431
Aug 1998032511.301.91$620
Jul 1998075411.742.24$1,687
Jun 1998056311.242.24$1,260
May 199801,25012.622.21$2,758
Apr 199801,47913.042.51$3,705
Mar 199802,22712.802.31$5,143
Feb 199801,35613.952.30$3,118
Jan 1998071114.702.15$1,532
Dec 1997066416.322.41$1,601
Nov 199702,52318.193.09$7,792
Oct 199702,32219.253.15$7,314
Sep 199701,92017.742.95$5,673
Aug 199702,49917.862.55$6,384
Jul 199702,79217.582.25$6,273
Jun 199701,25817.242.26$2,840
May 19970018.972.31$0
Apr 19970017.882.08$0
Mar 19970018.951.94$0
Feb 19970020.492.21$0
Jan 19970023.483.54$0
Dec 19960023.32$0
Nov 19960021.97$0
Oct 19960023.31$0
Sep 19960022.22$0
Aug 19960020.26$0
Jul 19960019.55$0
Jun 19960018.73$0
May 19960019.43$0
Apr 19960021.51$0
Mar 19960019.38$0
Feb 19960016.98$0
Jan 19960017.07$0
Dec 19950017.19$0
Nov 19950016.00$0
Oct 19950015.43$0
Sep 19950016.18$0
Aug 19950015.92$0
Jul 19950015.24$0
Jun 19950016.41$0
May 19950017.56$0
Apr 19950017.73$0
Mar 19950016.44$0
Feb 19950016.58$0
Jan 19950015.92$0
Dec 19940015.03$0
Nov 19940015.90$0
Oct 19940015.58$0
Sep 19940015.29$0
Aug 19940016.13$0
Jul 19940017.56$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Aug 2008 — as filed, then multipliedworked
Condensate            59 bbl  × $114.22 =     $6,739
Gas                    0 Mcf  × $  8.48 =         $0

────────────────────────────────────────────────────
Month total                                   $6,739

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 08/G/153217 is the state's own key, not one this site invented.