BARFIELD 8 -B-

Operated by NORTHSTAR OPERATING COMPANY (P-5 614609) in the DEWEY LAKE, S. (STRAWN) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Oil lease lease 31796District 08Field 24489380OilCasinghead gasSaveExport
Value, all time
$773 k
Jan 1993 – May 2005
Value, last 12 filed months
$3 k
at the published price for each month
Months reported
149
no gaps in the span
Streams
2
oil, casinghead gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 49 leases and 56 wells, and the rule below applies to all of them.

Discovered
1983-06-10
as the register files it
Field class
Oil and gas
the register's own label
Between wells
1,320 ft
minimum
From a lease line
660 ft
minimum

A drilling unit in this field needs at least 80 acres. The field rule took effect on 1985-09-16.

The Commission's schedule remark for this field reads: ALLOCATION FORMULA EFFECTIVE 09/01/1999.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
OilDisposition9,290 bbl$170,322
Casinghead gasProduction394,581 Mcf$603,158
Total$773,481

184,332 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 31.8216, -101.6372. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

31.82164, -101.63724 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
10,820 ft
1 wells filed one
Completion to plug
17.3 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 10,820 ft.

Completions filed
Jan 2005
1 of 1 wells
Plug dates filed
Apr 2022
1 of 1 wells

Last completion to plug: a median of 17.3 years across the 1 well that filed both dates, with the middle half between 17.3 years and 17.3 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-17332014110,820 ftJan 2005Apr 2022Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (149)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

149 months

May 20050045.226.65$0
Apr 20050049.207.36$0
Mar 2005511050.377.15$2,640
Feb 200511045.226.31$108
Jan 200501043.166.32$63
Dec 200401039.866.75$68
Nov 200401045.286.33$63
Oct 200401049.706.52$65
Sep 200401043.245.28$53
Aug 200401042.375.55$56
Jul 200401038.286.08$61
Jun 200401036.106.43$64
May 200401037.486.49$65
Apr 200401034.475.86$59
Mar 200401034.365.53$55
Feb 200401032.455.51$55
Jan 200401032.036.30$63
Dec 200301030.266.30$63
Nov 200331028.804.60$132
Oct 200301028.174.76$48
Sep 200303726.314.75$176
Aug 200304729.765.13$241
Jul 200301029.415.17$52
Jun 200304628.565.98$275
May 200303026.595.97$179
Apr 200301626.675.41$87
Mar 200301131.146.10$67
Feb 200301033.487.93$79
Jan 200301030.315.58$56
Dec 2002010526.914.85$510
Nov 200205124.664.14$211
Oct 20021641026.464.23$4,382
Sep 200201127.443.64$40
Aug 200201425.963.16$44
Jul 200202324.583.06$70
Jun 200222423.733.34$128
May 200201024.663.58$36
Apr 200201023.653.51$35
Mar 200201,31522.003.10$4,080
Feb 200201,97218.222.38$4,685
Jan 200202,28017.172.38$5,417
Dec 200102,35416.932.36$5,566
Nov 200101,62518.072.41$3,909
Oct 20011842,68019.782.53$10,417
Sep 200102,01924.262.25$4,545
Aug 2001086724.873.05$2,647
Jul 2001061623.933.20$1,969
Jun 2001087324.563.82$3,338
May 200101,35125.524.31$5,819
Apr 200101,64924.685.34$8,798
Mar 200102,12124.545.38$11,403
Feb 20011781,78727.755.77$15,245
Jan 200102,01027.478.40$16,882
Dec 200002,17826.889.12$19,869
Nov 200002,67132.215.66$15,113
Oct 20001853,02731.235.15$21,353
Sep 200002,07631.875.19$10,767
Aug 200002,28729.644.54$10,385
Jul 200003,32828.534.09$13,611
Jun 20001783,50629.304.40$20,632
May 200003,98627.263.68$14,667
Apr 200003,74124.513.12$11,657
Mar 20001813,07728.422.86$13,943
Feb 200003,59327.622.73$9,796
Jan 20001923,54825.272.48$13,653
Dec 199903,66124.282.42$8,873
Nov 19991884,60723.192.43$15,573
Oct 199903,58520.982.80$10,051
Sep 199903,66921.752.62$9,609
Aug 19991873,41119.262.88$13,410
Jul 199903,46117.892.37$8,211
Jun 199903,17715.942.36$7,504
May 199903,42715.792.32$7,954
Apr 19991943,27815.102.21$10,167
Mar 199902,93712.471.84$5,399
Feb 199902,8289.981.82$5,141
Jan 199902,67110.381.90$5,075
Dec 19981882,8409.201.77$6,766
Nov 199803,96810.892.19$8,673
Oct 199803,99112.421.97$7,859
Sep 199804,27412.592.08$8,901
Aug 199802,22911.301.91$4,251
Jul 199803,68211.742.24$8,238
Jun 19981934,26811.242.24$11,718
May 199804,04112.622.21$8,916
Apr 199804,25313.042.51$10,655
Mar 19981864,20612.802.31$12,094
Feb 199803,95113.952.30$9,084
Jan 199805,56814.702.15$11,998
Dec 19971914,84616.322.41$14,801
Nov 199704,39818.193.09$13,582
Oct 19971714,74519.253.15$18,238
Sep 199703,76017.742.95$11,110
Aug 19971705,03917.862.55$15,910
Jul 19971745,41617.582.25$15,228
Jun 199705,18317.242.26$11,699
May 19971726,07818.972.31$17,294
Apr 199704,53417.882.08$9,443
Mar 19971915,12118.951.94$13,550
Feb 199704,84020.492.21$10,677
Jan 19971775,11423.483.54$22,258
Dec 199605,07523.32$0
Nov 19961905,42721.97$4,174
Oct 199606,08223.31$0
Sep 19961764,91222.22$3,911
Aug 199606,18920.26$0
Jul 19961896,44519.55$3,695
Jun 199606,33218.73$0
May 19961827,07219.43$3,536
Apr 19961832,64521.51$3,936
Mar 199603,08019.38$0
Feb 199602,64316.98$0
Jan 19961962,60317.07$3,346
Dec 199502,39517.19$0
Nov 199502,30216.00$0
Oct 19951812,64715.43$2,793
Sep 199502,38616.18$0
Aug 199502,51415.92$0
Jul 19951742,82815.24$2,652
Jun 199502,83716.41$0
May 19951892,82817.56$3,319
Apr 199502,80217.73$0
Mar 19951912,85216.44$3,140
Feb 199502,80716.58$0
Jan 19951972,81915.92$3,136
Dec 199402,64915.03$0
Nov 19941852,38615.90$2,942
Oct 199402,54415.58$0
Sep 199402,34915.29$0
Aug 19941882,91716.13$3,032
Jul 199403,64317.56$0
Jun 19941874,61617.09$3,196
May 19941903,60215.88$3,017
Apr 199403,88114.14$0
Mar 19941904,46912.46$2,367
Feb 19941873,90512.50$2,338
Jan 19941854,16312.66$2,342
Dec 19931894,44412.33$2,330
Nov 19931954,14314.49$2,826
Oct 19931844,51715.85$2,916
Sep 19931754,64615.03$2,630
Aug 19931874,45115.66$2,928
Jul 19931834,88315.46$2,829
Jun 19931844,33216.79$3,089
May 19931863,93217.68$3,288
Apr 19931865,00418.05$3,357
Mar 19931855,10118.14$3,356
Feb 19931883,24517.90$3,365
Jan 19931873,98816.93$3,166

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Mar 2005 — as filed, then multipliedworked
Oil                   51 bbl  × $ 50.37 =     $2,569
Casinghead gas        10 Mcf  × $  7.15 =        $72

────────────────────────────────────────────────────
Month total                                   $2,640

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 08/O/31796 is the state's own key, not one this site invented.