SMITH, M. A. 1023

Operated by J RICO OIL, LLC (P-5 427901) in the YATES (SMITH SAND) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Oil lease lease 33667District 08Field 99295333Hydrogen sulphide fieldOilCasinghead gasSaveExport
Value, all time
$1.8 M
Jan 1993 – May 2026
Value, last 12 filed months
$36 k
at the published price for each month
Months reported
401
no gaps in the span
Streams
2
oil, casinghead gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 18 leases and 103 wells, and the rule below applies to all of them.

Discovered
1944-12-31
as the register files it
Field class
Oil
the register's own label
Between wells
300 ft
minimum
From a lease line
150 ft
minimum

A drilling unit in this field needs at least 5 acres. The field rule took effect on 2011-03-08.

The register flags this field for hydrogen sulphide. That is a poisonous gas that occurs naturally in some formations. The flag is a property of the field as the Commission records it. It is not a measurement taken at this lease, and it is not a statement that gas is escaping anywhere.

The Commission's schedule remark for this field reads: CORRELATIVE INTERVAL 712-784 ESTABLISED.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
OilDisposition43,205 bbl$1,760,719
Casinghead gasProduction347 Mcf$1,284
Total$1,762,003

48 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.8669, -101.9509. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.86693, -101.95088 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
1,060 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 1,060 ft.

Completions filed
Mar 1983
1 of 1 wells

1 well

42-3713421436S1,060 ftMar 1983

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (401)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

401 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 2026170089.753.15$15,258
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 2025167056.664.41$9,462
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 2025164066.743.32$10,945
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 2024162068.993.12$11,176
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 2024162069.612.36$11,277
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 2024172078.082.63$13,430
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 2024168080.301.55$13,490
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 2023167071.262.61$11,900
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 2023160089.042.74$14,246
Aug 20230080.522.67$0
Jul 2023161074.852.64$12,051
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 2023169078.122.24$13,202
Mar 20230072.852.39$0
Feb 2023170075.112.47$12,769
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 2022165085.005.65$14,025
Oct 20220087.185.86$0
Sep 2022166084.888.16$14,090
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 20221730115.097.98$19,911
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 20221750108.885.08$19,054
Feb 2022169091.054.86$15,387
Jan 20220081.844.54$0
Dec 20210171.323.90$4
Nov 2021176177.435.24$13,633
Oct 20210179.795.71$6
Sep 2021164169.865.35$11,462
Aug 20210166.024.22$4
Jul 2021162170.783.98$11,470
Jun 20210169.493.38$3
May 20210163.483.02$3
Apr 2021163160.362.76$9,841
Mar 20210161.302.72$3
Feb 20210157.805.55$6
Jan 2021165150.412.81$8,320
Dec 20200144.642.68$3
Nov 20200138.772.71$3
Oct 2020166136.972.48$6,140
Sep 20200137.091.99$2
Aug 2020172139.982.39$6,879
Jul 20200138.371.83$2
Jun 20200134.901.69$2
May 2020163116.921.81$2,760
Apr 20200114.751.80$2
Mar 2020166130.341.86$5,038
Feb 20200149.881.98$2
Jan 2020174157.252.09$9,964
Dec 20190159.012.30$2
Nov 20190155.302.75$3
Oct 2019165153.472.42$8,825
Sep 20190155.052.66$3
Aug 20190153.112.30$2
Jul 2019166156.272.46$9,343
Jun 20190152.782.49$2
May 2019168158.482.74$9,827
Apr 20190162.632.75$3
Mar 20190056.803.06$0
Feb 2019166150.852.79$8,444
Jan 20190146.033.23$3
Dec 20180146.594.19$4
Nov 2018173152.934.24$9,161
Oct 20180161.443.40$3
Sep 2018164159.543.11$9,768
Aug 20180159.403.07$3
Jul 20180165.142.93$3
Jun 2018169160.183.08$10,174
May 20180165.382.90$3
Apr 2018163163.842.90$10,409
Mar 20180161.222.79$3
Feb 20180161.782.77$3
Jan 2018168162.874.01$10,566
Dec 2017171157.272.92$9,796
Nov 20170155.423.12$3
Oct 20170149.292.98$3
Sep 2017170147.523.09$8,081
Aug 20170145.373.00$3
Jul 2017166143.873.09$7,286
Jun 20170142.493.09$3
May 2017168145.373.26$7,625
Apr 2017156147.933.21$7,480
Mar 20170146.772.98$3
Feb 2017162150.452.95$8,176
Jan 20170149.413.42$3
Dec 2016174148.763.72$8,488
Nov 2016170142.492.64$7,226
Oct 20160146.193.09$3
Sep 2016169141.553.10$7,025
Aug 20160141.442.92$3
Jul 2016161141.622.92$6,704
Jun 20160145.352.69$3
May 2016162142.521.99$6,890
Apr 20160136.561.99$2
Mar 2016160133.011.79$5,283
Feb 20160126.472.06$2
Jan 2016167127.352.36$4,570
Dec 2015176132.362.00$5,697
Nov 20150138.792.17$2
Oct 2015161143.552.43$7,014
Sep 20150142.992.76$3
Aug 2015158140.162.87$6,348
Jul 20150148.152.95$3
Jun 2015170156.152.88$9,548
May 20150155.212.96$3
Apr 2015163149.822.71$8,123
Mar 2015170142.892.93$7,294
Feb 20150144.662.98$3
Jan 2015166143.433.10$7,212
Dec 2014162154.693.59$8,863
Nov 20140170.464.25$4
Oct 20140178.303.90$4
Sep 20140186.164.05$4
Aug 2014162189.394.04$14,485
Jul 20140196.564.18$4
Jun 20140198.164.74$5
May 20140194.734.73$5
Apr 2014165195.944.81$15,835
Mar 20140195.895.06$5
Feb 2014168197.406.19$16,369
Jan 20140190.404.86$5
Dec 2013176191.824.35$16,165
Nov 20130188.853.74$4
Oct 2013170197.423.78$16,565
Sep 20131731104.113.72$18,015
Aug 201301104.253.52$4
Jul 20131611102.523.72$16,509
Jun 2013166194.403.93$15,674
May 20130194.834.15$4
Apr 2013172193.964.28$16,165
Mar 20130193.623.91$4
Feb 2013158191.233.42$14,418
Jan 2013165191.603.42$15,117
Dec 20120186.773.42$3
Nov 20120186.953.62$4
Oct 20120189.383.40$3
Sep 2012164194.672.92$15,529
Aug 20120192.662.91$3
Jul 2012160185.133.02$13,624
Jun 20120179.822.52$3
May 20120191.612.49$2
Apr 20121641101.652.00$16,673
Mar 201201105.052.22$2
Feb 201201101.102.57$3
Jan 2012163198.092.73$15,991
Dec 20110196.873.24$3
Nov 2011166195.723.31$15,893
Oct 20110184.983.65$4
Sep 2011163183.623.99$13,634
Aug 2011161183.404.15$13,432
Jul 20110194.144.52$5
Jun 20110192.904.64$5
May 2011201198.134.40$19,729
Apr 201101105.964.33$4
Mar 2011160196.364.06$15,422
Feb 20110185.644.18$4
Jan 20110186.504.59$5
Dec 20100185.734.35$4
Nov 2010164180.843.80$13,262
Oct 20100178.103.51$4
Sep 2010171172.633.98$12,424
Aug 20100173.684.42$4
Jul 20100172.554.74$5
Jun 20100170.364.91$5
May 2010164171.124.24$11,668
Apr 20100181.694.12$4
Mar 2010143178.394.39$11,214
Feb 20100173.585.44$5
Jan 20100174.365.96$6
Dec 2009168171.445.48$12,007
Nov 20090174.593.75$4
Oct 2009160172.544.11$11,611
Sep 20090165.543.06$3
Aug 2009159167.423.22$10,723
Jul 20090161.133.46$3
Jun 20090166.163.90$4
May 2009161154.743.93$8,817
Apr 20090146.773.59$4
Mar 2009175142.144.06$7,379
Feb 20090132.814.63$5
Jan 20090135.865.37$5
Dec 2008172137.105.98$6,387
Nov 20080155.496.86$7
Oct 2008176175.246.92$13,249
Sep 200801101.767.88$8
Aug 200801114.228.48$8
Jul 20081641131.0811.39$21,509
Jun 200801131.3313.03$13
May 20081721123.1711.57$21,197
Apr 200801110.3110.45$10
Mar 200801101.909.66$10
Feb 2008169192.538.77$15,646
Jan 20080190.388.21$8
Dec 2007174188.337.30$15,377
Nov 20070191.677.29$7
Oct 2007164182.856.92$13,594
Sep 20070175.846.24$6
Aug 2007171169.066.39$11,816
Jul 20070170.906.39$6
Jun 20070162.007.55$8
May 2007162158.747.85$9,524
Apr 20070159.617.81$8
Mar 20070156.927.30$7
Feb 2007165155.108.22$9,100
Jan 20070150.306.73$7
Dec 20060156.656.92$7
Nov 20060154.207.62$8
Oct 2006174154.906.01$9,559
Sep 20060160.085.04$5
Aug 2006169168.717.34$11,619
Jul 20060169.376.34$6
Jun 2006163166.286.38$10,810
May 20060166.016.42$6
Apr 2006170164.397.36$10,954
Mar 20060156.707.08$7
Feb 2006173157.597.75$9,971
Jan 20060160.598.93$9
Dec 2005169154.9413.42$9,298
Nov 20050154.6910.59$11
Oct 2005146158.3413.80$8,531
Sep 20050161.4512.08$12
Aug 2005167161.519.80$10,282
Jul 2005160155.697.84$8,918
Jun 2005157152.337.38$8,223
May 2005171145.226.65$7,739
Apr 20050149.207.36$7
Mar 2005166150.377.15$8,369
Feb 20050145.226.31$6
Jan 2005168143.166.32$7,257
Dec 2004163139.866.75$6,504
Nov 2004179145.286.33$8,111
Oct 20040149.706.52$7
Sep 2004176143.245.28$7,616
Aug 2004166142.375.55$7,039
Jul 20040138.286.08$6
Jun 2004166136.106.43$5,999
May 2004181137.486.49$6,790
Apr 20040134.475.86$6
Mar 2004182134.365.53$6,259
Feb 20040132.455.51$6
Jan 2004158132.036.30$5,067
Dec 2003159130.266.30$4,818
Nov 2003143128.804.60$4,123
Oct 2003150128.174.76$4,230
Sep 2003169126.314.75$4,451
Aug 2003165129.765.13$4,916
Jul 20030129.415.17$5
Jun 2003140128.565.98$4,004
May 2003115126.595.97$3,064
Apr 2003144126.675.41$3,846
Mar 2003129131.146.10$4,023
Feb 2003122133.487.93$4,092
Jan 2003151130.315.58$4,582
Dec 2002154126.914.85$4,149
Nov 2002162124.664.14$3,999
Oct 2002136126.464.23$3,603
Sep 2002151127.443.64$4,147
Aug 2002137125.963.16$3,560
Jul 2002175124.583.06$4,305
Jun 2002150123.733.34$3,563
May 2002139124.663.58$3,431
Apr 2002163123.653.51$3,858
Mar 2002148122.003.10$3,259
Feb 2002149118.222.38$2,717
Jan 2002126117.172.38$2,166
Dec 2001155116.932.36$2,627
Nov 2001161118.072.41$2,912
Oct 2001160119.782.53$3,167
Sep 2001155124.262.25$3,763
Aug 2001152124.873.05$3,783
Jul 2001164123.933.20$3,928
Jun 2001161124.563.82$3,958
May 2001176125.524.31$4,496
Apr 2001175124.685.34$4,324
Mar 2001300124.545.38$7,367
Feb 2001161127.755.77$4,474
Jan 2001323127.478.40$8,881
Dec 2000129126.889.12$3,477
Nov 2000332132.215.66$10,699
Oct 2000149131.235.15$4,658
Sep 2000149131.875.19$4,754
Aug 2000314129.644.54$9,312
Jul 2000164128.534.09$4,683
Jun 2000163129.304.40$4,780
May 2000308127.263.68$8,400
Apr 2000163124.513.12$3,998
Mar 2000335128.422.86$9,524
Feb 2000162127.622.73$4,477
Jan 2000181125.272.48$4,576
Dec 1999161124.282.42$3,912
Nov 1999176123.192.43$4,084
Oct 1999157120.982.80$3,297
Sep 1999164121.752.62$3,570
Aug 1999174119.262.88$3,354
Jul 1999155117.892.37$2,775
Jun 1999180115.942.36$2,872
May 1999140115.792.32$2,213
Apr 1999150115.102.21$2,267
Mar 1999172112.471.84$2,147
Feb 199917719.981.82$1,768
Jan 1999159110.381.90$1,652
Dec 199818019.201.77$1,658
Nov 1998153110.892.19$1,668
Oct 1998170112.421.97$2,113
Sep 1998184112.592.08$2,319
Aug 1998160111.301.91$1,810
Jul 1998167111.742.24$1,963
Jun 1998116111.242.24$1,306
May 1998127112.622.21$1,605
Apr 1998144113.042.51$1,880
Mar 1998161112.802.31$2,063
Feb 1998160113.952.30$2,234
Jan 1998179114.702.15$2,633
Dec 1997143116.322.41$2,336
Nov 1997360118.193.09$6,551
Oct 1997329119.253.15$6,336
Sep 19970117.742.95$3
Aug 1997135117.862.55$2,414
Jul 1997176117.582.25$3,096
Jun 1997178117.242.26$3,071
May 1997179118.972.31$3,398
Apr 1997174117.882.08$3,113
Mar 1997182118.951.94$3,451
Feb 1997179120.492.21$3,670
Jan 1997180123.483.54$4,230
Dec 1996308123.32$7,183
Nov 1996188121.97$4,130
Oct 1996178123.31$4,149
Sep 1996179122.22$3,977
Aug 1996162120.26$3,282
Jul 1996176119.55$3,441
Jun 1996181118.73$3,390
May 1996185119.43$3,595
Apr 1996169121.51$3,635
Mar 1996170119.38$3,295
Feb 1996198116.98$3,362
Jan 1996361117.07$6,162
Dec 1995195117.19$3,352
Nov 1995186116.00$2,976
Oct 19950115.43$0
Sep 1995185116.18$2,993
Aug 1995176115.92$2,802
Jul 1995188115.24$2,865
Jun 1995183116.41$3,003
May 1995184117.56$3,231
Apr 1995186117.73$3,298
Mar 1995184116.44$3,025
Feb 1995144116.58$2,388
Jan 1995161115.92$2,563
Dec 1994369115.03$5,546
Nov 1994184115.90$2,926
Oct 1994182115.58$2,836
Sep 1994182115.29$2,783
Aug 1994178116.13$2,871
Jul 1994171117.56$3,003
Jun 1994346117.09$5,913
May 1994172115.88$2,731
Apr 1994172114.14$2,432
Mar 1994172112.46$2,143
Feb 1994168112.50$2,100
Jan 1994172112.66$2,178
Dec 1993172112.33$2,121
Nov 1993172114.49$2,492
Oct 1993172115.85$2,726
Sep 1993172115.03$2,585
Aug 1993344115.66$5,387
Jul 19930115.46$0
Jun 1993162116.79$2,720
May 1993171117.68$3,023
Apr 1993345118.05$6,227
Mar 1993345118.14$6,258
Feb 1993172117.90$3,079
Jan 1993322116.93$5,451

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Mar 2026 — as filed, then multipliedworked
Oil                  170 bbl  × $ 89.75 =    $15,258
Casinghead gas         0 Mcf  × $  3.15 =         $0

────────────────────────────────────────────────────
Month total                                  $15,258

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 08/O/33667 is the state's own key, not one this site invented.