CLARA DUNN UNIT

Operated by J-W OPERATING CO. (P-5 427960) in the MONTEATH (ATOKA, UPPER) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 138036District 09Field 62580100NGPA filingCondensateGasSaveExport
Value, all time
$404 k
Jan 1993 – Mar 2010
Value, last 12 filed months
$6 k
at the published price for each month
Months reported
207
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 32 leases and 32 wells, and the rule below applies to all of them.

Discovered
1980-08-22
as the register files it
Field class
Gas
the register's own label
Between wells
no field rule filed
From a lease line
no field rule filed

The Commission's schedule remark for this field reads: AOF-1 AND AOF-2 EFFECTIVE 08/01/2005.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition52 bbl$1,493
GasProduction157,931 Mcf$402,329
Total$403,822

82,340 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 33.1733, -97.3625. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

33.17332, -97.36255 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
6,300 ft
1 wells filed one
Completion to plug
18.9 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 6,300 ft.

Completions filed
Apr 1991
1 of 1 wells
Plug dates filed
Mar 2010
1 of 1 wells

Last completion to plug: a median of 18.9 years across the 1 well that filed both dates, with the middle half between 18.9 years and 18.9 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-1213053026,300 ftApr 1991Mar 2010Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (207)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

207 months

Mar 20100078.394.39$0
Feb 20100073.585.44$0
Jan 20100074.365.96$0
Dec 20090071.445.48$0
Nov 20090074.593.75$0
Oct 20090072.544.11$0
Sep 20090065.543.06$0
Aug 20090067.423.22$0
Jul 20090061.133.46$0
Jun 20090066.163.90$0
May 20091316254.743.93$1,348
Apr 200901,41446.773.59$5,073
Mar 200902,45042.144.06$9,945
Feb 20090032.814.63$0
Jan 200901,10335.865.37$5,924
Dec 20080037.105.98$0
Nov 20080055.496.86$0
Oct 20080075.246.92$0
Sep 20080129101.767.88$1,016
Aug 20080804114.228.48$6,820
Jul 200802,743131.0811.39$31,241
Jun 200804,262131.3313.03$55,545
May 200802,909123.1711.57$33,670
Apr 200802,028110.3110.45$21,202
Mar 200800101.909.66$0
Feb 20080092.538.77$0
Jan 20080090.388.21$0
Dec 20070688.337.30$44
Nov 200703491.677.29$248
Oct 200703282.856.92$222
Sep 200701675.846.24$100
Aug 200706469.066.39$409
Jul 200704870.906.39$307
Jun 2007041262.007.55$3,110
May 200707658.747.85$596
Apr 200707359.617.81$570
Mar 2007019256.927.30$1,402
Feb 20070055.108.22$0
Jan 20070250.306.73$13
Dec 20060056.656.92$0
Nov 2006020154.207.62$1,531
Oct 2006039754.906.01$2,387
Sep 2006022760.085.04$1,143
Aug 2006024068.717.34$1,762
Jul 2006023069.376.34$1,459
Jun 2006027966.286.38$1,781
May 2006022966.016.42$1,471
Apr 2006021964.397.36$1,612
Mar 2006040756.707.08$2,883
Feb 2006025057.597.75$1,938
Jan 2006030460.598.93$2,716
Dec 2005040354.9413.42$5,406
Nov 2005023854.6910.59$2,520
Oct 200509458.3413.80$1,297
Sep 2005012961.4512.08$1,558
Aug 2005027061.519.80$2,645
Jul 2005028955.697.84$2,267
Jun 2005025752.337.38$1,897
May 2005043445.226.65$2,887
Apr 2005023649.207.36$1,737
Mar 2005038450.377.15$2,747
Feb 200501,03545.226.31$6,533
Jan 200501,06243.166.32$6,714
Dec 2004077339.866.75$5,219
Nov 2004081645.286.33$5,166
Oct 2004087049.706.52$5,668
Sep 2004024743.245.28$1,305
Aug 2004047942.375.55$2,659
Jul 2004023038.286.08$1,399
Jun 2004041936.106.43$2,695
May 2004043437.486.49$2,819
Apr 2004034834.475.86$2,039
Mar 2004036534.365.53$2,019
Feb 2004041832.455.51$2,303
Jan 2004038932.036.30$2,451
Dec 2003022530.266.30$1,418
Nov 2003025028.804.60$1,149
Oct 2003025628.174.76$1,218
Sep 2003024226.314.75$1,149
Aug 2003022029.765.13$1,129
Jul 2003019429.415.17$1,003
Jun 2003028928.565.98$1,729
May 2003027426.595.97$1,637
Apr 2003028526.675.41$1,541
Mar 2003033331.146.10$2,030
Feb 2003021333.487.93$1,688
Jan 2003036630.315.58$2,043
Dec 2002039926.914.85$1,937
Nov 2002021624.664.14$894
Oct 200208326.464.23$351
Sep 2002018127.443.64$658
Aug 2002049225.963.16$1,557
Jul 2002021824.583.06$667
Jun 2002014123.733.34$471
May 2002016424.663.58$588
Apr 2002016123.653.51$565
Mar 2002034722.003.10$1,077
Feb 2002042218.222.38$1,003
Jan 2002055717.172.38$1,323
Dec 2001035916.932.36$849
Nov 2001027518.072.41$662
Oct 2001025019.782.53$632
Sep 2001035224.262.25$792
Aug 2001021324.873.05$650
Jul 2001026123.933.20$834
Jun 2001028524.563.82$1,090
May 2001022425.524.31$965
Apr 2001026124.685.34$1,393
Mar 2001032424.545.38$1,742
Feb 2001023727.755.77$1,367
Jan 2001028927.478.40$2,427
Dec 2000022126.889.12$2,016
Nov 2000733232.215.66$2,104
Oct 2000029331.235.15$1,508
Sep 2000053931.875.19$2,796
Aug 2000054429.644.54$2,470
Jul 2000049928.534.09$2,041
Jun 2000052429.304.40$2,304
May 2000068827.263.68$2,532
Apr 2000064424.513.12$2,007
Mar 2000065928.422.86$1,885
Feb 2000061127.622.73$1,666
Jan 2000074125.272.48$1,838
Dec 1999068324.282.42$1,655
Nov 1999054023.192.43$1,314
Oct 1999066220.982.80$1,856
Sep 1999037221.752.62$974
Aug 1999054219.262.88$1,559
Jul 1999068217.892.37$1,618
Jun 1999083215.942.36$1,965
May 1999089215.792.32$2,070
Apr 1999077515.102.21$1,711
Mar 1999072412.471.84$1,331
Feb 199907209.981.82$1,309
Jan 1999092810.381.90$1,763
Dec 199808759.201.77$1,552
Nov 1998091910.892.19$2,009
Oct 1998096612.421.97$1,902
Sep 1998057012.592.08$1,187
Aug 1998057111.301.91$1,089
Jul 1998076611.742.24$1,714
Jun 1998074711.242.24$1,671
May 1998071112.622.21$1,569
Apr 1998070513.042.51$1,766
Mar 1998098712.802.31$2,279
Feb 1998066313.952.30$1,524
Jan 1998079714.702.15$1,717
Dec 1997093316.322.41$2,250
Nov 1997061218.193.09$1,890
Oct 1997062919.253.15$1,981
Sep 1997047817.742.95$1,412
Aug 1997065717.862.55$1,678
Jul 1997089117.582.25$2,002
Jun 1997080517.242.26$1,817
May 1997074018.972.31$1,708
Apr 1997099217.882.08$2,066
Mar 1997087818.951.94$1,703
Feb 1997071720.492.21$1,582
Jan 1997091623.483.54$3,242
Dec 1996073623.32$0
Nov 1996093421.97$0
Oct 199601,25523.31$0
Sep 1996774422.22$156
Aug 1996054220.26$0
Jul 1996082319.55$0
Jun 199601,30118.73$0
May 199601,86019.43$0
Apr 199601,84421.51$0
Mar 199601,66319.38$0
Feb 199601,51116.98$0
Jan 199602,01017.07$0
Dec 199501,62317.19$0
Nov 1995251,57616.00$400
Oct 199501,81615.43$0
Sep 199501,71416.18$0
Aug 199501,92215.92$0
Jul 199501,92215.24$0
Jun 199501,91416.41$0
May 199502,10717.56$0
Apr 199501,74117.73$0
Mar 199501,57216.44$0
Feb 199501,64216.58$0
Jan 199501,62015.92$0
Dec 199401,42815.03$0
Nov 199401,44515.90$0
Oct 199401,51215.58$0
Sep 199401,37415.29$0
Aug 199401,47516.13$0
Jul 199401,54217.56$0
Jun 199401,64917.09$0
May 199401,98215.88$0
Apr 199404,02114.14$0
Mar 199402,73212.46$0
Feb 199402,54012.50$0
Jan 199401,75212.66$0
Dec 199303,05312.33$0
Nov 199301,41714.49$0
Oct 199301,35315.85$0
Sep 199302,82715.03$0
Aug 199301,85915.66$0
Jul 199301,82715.46$0
Jun 199301,70416.79$0
May 199301,96017.68$0
Apr 199301,67218.05$0
Mar 199301,59018.14$0
Feb 199301,39617.90$0
Jan 199301,83816.93$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2009 — as filed, then multipliedworked
Condensate            13 bbl  × $ 54.74 =       $712
Gas                  162 Mcf  × $  3.93 =       $636

────────────────────────────────────────────────────
Month total                                   $1,348

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 09/G/138036 is the state's own key, not one this site invented.