KARNES, J. D. UNIT 3

Operated by DEVON ENERGY PRODUCTION CO, L.P. (P-5 216378) in the BOONSVILLE (BEND CONGL., GAS) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 28707District 09Field 105745202 tax incentive programmesCondensateGasSaveExport
Value, all time
$892 k
Jan 1993 – Oct 2016
Value, last 12 filed months
$0
at the published price for each month
Months reported
286
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 3,438 leases and 3,443 wells, and the rule below applies to all of them.

Discovered
1945-05-01
as the register files it
Field class
Oil and gas
the register's own label
Between wells
1,200 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 80 acres. The field rule took effect on 1991-06-10.

The Commission's schedule remark for this field reads: AMOUNT HAD BEEN CALCULATED FOR 5/1/97.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112002-05-09147636
NGPA3none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition381 bbl$20,122
GasProduction210,227 Mcf$871,468
Total$891,590

20,723 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 33.1172, -97.6212. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

33.11716, -97.62120 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
6,150 ft
1 wells filed one
Completion to plug
55.8 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 6,150 ft.

Completions filed
Dec 1960
1 of 1 wells
Plug dates filed
Oct 2016
1 of 1 wells

Last completion to plug: a median of 55.8 years across the 1 well that filed both dates, with the middle half between 55.8 years and 55.8 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-4970118036,150 ftDec 1960Oct 2016Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (286)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

286 months

Oct 20160046.193.09$0
Sep 20160041.553.10$0
Aug 20160041.442.92$0
Jul 20160041.622.92$0
Jun 20160045.352.69$0
May 20160042.521.99$0
Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 20160026.472.06$0
Jan 20160027.352.36$0
Dec 20150032.362.00$0
Nov 20150038.792.17$0
Oct 20150043.552.43$0
Sep 20150042.992.76$0
Aug 20150040.162.87$0
Jul 20150048.152.95$0
Jun 20150056.152.88$0
May 20150055.212.96$0
Apr 20150049.822.71$0
Mar 20150042.892.93$0
Feb 20150044.662.98$0
Jan 20150043.433.10$0
Dec 20140054.693.59$0
Nov 20140070.464.25$0
Oct 20140078.303.90$0
Sep 20140086.164.05$0
Aug 201403489.394.04$137
Jul 2014021696.564.18$903
Jun 201406298.164.74$294
May 2014033994.734.73$1,602
Apr 2014035895.944.81$1,722
Mar 2014036195.895.06$1,826
Feb 2014031597.406.19$1,950
Jan 2014032890.404.86$1,594
Dec 2013030991.824.35$1,346
Nov 2013027988.853.74$1,043
Oct 2013025197.423.78$949
Sep 20130433104.113.72$1,610
Aug 20130199104.253.52$701
Jul 20130383102.523.72$1,424
Jun 2013035194.403.93$1,381
May 2013024194.834.15$1,000
Apr 2013043693.964.28$1,867
Mar 2013042393.623.91$1,655
Feb 2013022791.233.42$776
Jan 2013012791.603.42$434
Dec 2012058386.773.42$1,994
Nov 2012024886.953.62$899
Oct 2012026189.383.40$887
Sep 2012038894.672.92$1,132
Aug 2012027192.662.91$788
Jul 2012034585.133.02$1,042
Jun 2012038779.822.52$975
May 2012033891.612.49$841
Apr 20120263101.652.00$525
Mar 20120438105.052.22$973
Feb 20120482101.102.57$1,239
Jan 2012035898.092.73$979
Dec 2011040396.873.24$1,306
Nov 2011034695.723.31$1,146
Oct 2011040184.983.65$1,463
Sep 2011027383.623.99$1,088
Aug 2011044583.404.15$1,846
Jul 2011029994.144.52$1,351
Jun 2011040792.904.64$1,888
May 2011040798.134.40$1,793
Apr 20110326105.964.33$1,413
Mar 2011039196.364.06$1,586
Feb 2011032085.644.18$1,338
Jan 2011031186.504.59$1,427
Dec 2010038885.734.35$1,687
Nov 2010037980.843.80$1,438
Oct 2010041378.103.51$1,449
Sep 2010031972.633.98$1,269
Aug 2010042673.684.42$1,883
Jul 2010036372.554.74$1,719
Jun 2010040170.364.91$1,969
May 2010056771.124.24$2,401
Apr 2010061181.694.12$2,519
Mar 2010050278.394.39$2,203
Feb 2010038273.585.44$2,079
Jan 2010032374.365.96$1,926
Dec 2009034371.445.48$1,881
Nov 2009040074.593.75$1,501
Oct 2009047072.544.11$1,932
Sep 2009041665.543.06$1,275
Aug 2009052967.423.22$1,703
Jul 2009052461.133.46$1,815
Jun 2009040666.163.90$1,581
May 2009046154.743.93$1,810
Apr 2009029146.773.59$1,044
Mar 2009043842.144.06$1,778
Feb 2009036832.814.63$1,705
Jan 2009039035.865.37$2,095
Dec 2008043137.105.98$2,576
Nov 2008042255.496.86$2,895
Oct 2008042775.246.92$2,956
Sep 20081543101.767.88$4,379
Aug 20081306114.228.48$2,710
Jul 20081443131.0811.39$5,177
Jun 20084439131.3313.03$6,247
May 20089520123.1711.57$7,127
Apr 20080380110.3110.45$3,973
Mar 20080600101.909.66$5,798
Feb 2008051892.538.77$4,543
Jan 2008048590.388.21$3,980
Dec 2007026488.337.30$1,928
Nov 200712638491.677.29$14,350
Oct 2007032782.856.92$2,263
Sep 2007058375.846.24$3,640
Aug 2007032069.066.39$2,044
Jul 2007053170.906.39$3,392
Jun 2007027162.007.55$2,046
May 2007046858.747.85$3,672
Apr 2007061059.617.81$4,761
Mar 2007013256.927.30$964
Feb 200705355.108.22$435
Jan 2007033950.306.73$2,280
Dec 2006062956.656.92$4,352
Nov 2006011954.207.62$906
Oct 2006037454.906.01$2,249
Sep 2006049760.085.04$2,503
Aug 2006053968.717.34$3,956
Jul 2006042769.376.34$2,708
Jun 2006041566.286.38$2,649
May 2006043366.016.42$2,782
Apr 2006033764.397.36$2,480
Mar 2006052656.707.08$3,726
Feb 2006025357.597.75$1,961
Jan 2006058360.598.93$5,208
Dec 2005048454.9413.42$6,493
Nov 200501,29054.6910.59$13,659
Oct 2005016858.3413.80$2,318
Sep 2005030061.4512.08$3,624
Aug 2005031261.519.80$3,057
Jul 2005035455.697.84$2,777
Jun 2005013952.337.38$1,026
May 2005030245.226.65$2,009
Apr 2005027949.207.36$2,054
Mar 2005048050.377.15$3,434
Feb 2005021145.226.31$1,332
Jan 200507043.166.32$443
Dec 2004026739.866.75$1,803
Nov 2004038345.286.33$2,425
Oct 2004081649.706.52$5,316
Sep 2004049643.245.28$2,621
Aug 2004020142.375.55$1,116
Jul 2004040838.286.08$2,482
Jun 2004065236.106.43$4,194
May 2004085737.486.49$5,566
Apr 2004095334.475.86$5,583
Mar 2004057034.365.53$3,152
Feb 200401,27232.455.51$7,008
Jan 200401,33132.036.30$8,385
Dec 2003098230.266.30$6,188
Nov 200302,01328.804.60$9,250
Oct 200302,33828.174.76$11,128
Sep 200301,73726.314.75$8,250
Aug 200301,48129.765.13$7,597
Jul 200302,52429.415.17$13,051
Jun 200302,28428.565.98$13,665
May 200302,56126.595.97$15,296
Apr 200302,52526.675.41$13,653
Mar 20031242,81331.146.10$21,010
Feb 200302,48833.487.93$19,720
Jan 200302,60830.315.58$14,558
Dec 200202,99126.914.85$14,518
Nov 200202,83024.664.14$11,708
Oct 200203,07126.464.23$12,988
Sep 200202,63627.443.64$9,582
Aug 200202,96625.963.16$9,385
Jul 200203,14324.583.06$9,623
Jun 20021152,83623.733.34$12,196
May 200203,46624.663.58$12,422
Apr 200203,05423.653.51$10,727
Mar 200203,46922.003.10$10,763
Feb 200203,43318.222.38$8,156
Jan 200203,63417.172.38$8,633
Dec 200103,75616.932.36$8,881
Nov 200101,51318.072.41$3,640
Oct 200102,18519.782.53$5,526
Sep 200102,11424.262.25$4,759
Aug 200102,30224.873.05$7,028
Jul 200102,69323.933.20$8,610
Jun 200102,51224.563.82$9,606
May 200102,63925.524.31$11,367
Apr 200102,50024.685.34$13,338
Mar 200102,66124.545.38$14,307
Feb 200102,26327.755.77$13,051
Jan 200102,26127.478.40$18,990
Dec 200002,50226.889.12$22,825
Nov 200002,66732.215.66$15,090
Oct 200003,11631.235.15$16,033
Sep 200003,65631.875.19$18,962
Aug 200003,54829.644.54$16,111
Jul 200002,81528.534.09$11,513
Jun 200002,39229.304.40$10,518
May 200001,25727.263.68$4,625
Apr 200001,43724.513.12$4,478
Mar 200001,29528.422.86$3,703
Feb 2000097727.622.73$2,664
Jan 2000039725.272.48$985
Dec 1999061824.282.42$1,498
Nov 1999051323.192.43$1,249
Oct 1999053320.982.80$1,494
Sep 1999051321.752.62$1,343
Aug 1999035419.262.88$1,018
Jul 1999054217.892.37$1,286
Jun 1999053115.942.36$1,254
May 1999090615.792.32$2,103
Apr 1999090415.102.21$1,996
Mar 1999097312.471.84$1,789
Feb 199905079.981.82$922
Jan 1999034510.381.90$655
Dec 199803489.201.77$617
Nov 1998044510.892.19$973
Oct 1998033112.421.97$652
Sep 1998029912.592.08$623
Aug 1998030111.301.91$574
Jul 1998047611.742.24$1,065
Jun 1998050311.242.24$1,125
May 1998046612.622.21$1,028
Apr 1998043313.042.51$1,085
Mar 1998055112.802.31$1,273
Feb 1998054713.952.30$1,258
Jan 1998060614.702.15$1,306
Dec 1997047216.322.41$1,138
Nov 1997033718.193.09$1,041
Oct 1997031419.253.15$989
Sep 1997040817.742.95$1,206
Aug 1997037417.862.55$955
Jul 1997059717.582.25$1,341
Jun 1997032217.242.26$727
May 1997060418.972.31$1,394
Apr 1997037317.882.08$777
Mar 1997051618.951.94$1,001
Feb 1997056020.492.21$1,235
Jan 1997074523.483.54$2,637
Dec 1996012023.32$0
Nov 1996026321.97$0
Oct 1996031523.31$0
Sep 1996037122.22$0
Aug 1996044720.26$0
Jul 1996046319.55$0
Jun 1996040818.73$0
May 1996049719.43$0
Apr 1996055021.51$0
Mar 1996053919.38$0
Feb 1996042116.98$0
Jan 1996054517.07$0
Dec 1995053217.19$0
Nov 1995045816.00$0
Oct 1995010015.43$0
Sep 1995053716.18$0
Aug 1995050015.92$0
Jul 1995051715.24$0
Jun 1995053216.41$0
May 1995037317.56$0
Apr 1995046917.73$0
Mar 1995046916.44$0
Feb 1995032316.58$0
Jan 1995039415.92$0
Dec 1994022015.03$0
Nov 1994038115.90$0
Oct 1994032015.58$0
Sep 1994048915.29$0
Aug 1994042516.13$0
Jul 1994040917.56$0
Jun 1994045717.09$0
May 1994069115.88$0
Apr 1994040514.14$0
Mar 1994045212.46$0
Feb 1994032412.50$0
Jan 1994039912.66$0
Dec 1993057812.33$0
Nov 1993055314.49$0
Oct 1993026315.85$0
Sep 1993048815.03$0
Aug 1993057115.66$0
Jul 1993045515.46$0
Jun 1993036416.79$0
May 1993041017.68$0
Apr 1993043618.05$0
Mar 1993047118.14$0
Feb 1993046617.90$0
Jan 1993055316.93$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Aug 2014 — as filed, then multipliedworked
Condensate             0 bbl  × $ 89.39 =         $0
Gas                   34 Mcf  × $  4.04 =       $137

────────────────────────────────────────────────────
Month total                                     $137

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 09/G/28707 is the state's own key, not one this site invented.