WICHITA CO. WATER IMPR. DIST.

Operated by CLARK OPERATING INC. (P-5 155236) in the WEST field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Oil lease lease 6408District 09Field 96488001OilCasinghead gasSaveExport
Value, all time
$1.7 M
Jan 1993 – May 2026
Value, last 12 filed months
$112 k
at the published price for each month
Months reported
401
no gaps in the span
Streams
2
oil, casinghead gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 20 leases and 67 wells, and the rule below applies to all of them.

Discovered
1943-08-03
as the register files it
Field class
Oil
the register's own label
Between wells
933 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
OilDisposition38,463 bbl$1,708,315
Casinghead gasProduction3,300 Mcf$14,394
Total$1,722,708

48 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (2)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 33.9151, -98.5684. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.2 miles.

33.91510, -98.56844 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
50.0%
1 of 2 wells
With a plug date
50.0%
1 of 2 wells
Median depth
4,260 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
150.0%
A plug date is filed
150.0%
BothOn the schedule and plugged. Neither fact cancels the other.
150.0%
NeitherNo plug date, and not on the schedule.
150.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 4,260 ft.

Plug dates filed
Apr 2023
1 of 2 wells; 1 filed none

2 wells

42-485872242W4,260 ftApr 2023Yes
42-485872231

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (401)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

401 months

May 20261691106.413.05$17,986
Apr 20260198.932.87$3
Mar 2026344189.753.15$30,877
Feb 2026173163.503.75$10,989
Jan 20260159.138.00$8
Dec 2025174156.664.41$9,863
Nov 2025166158.593.93$9,730
Oct 20250159.383.30$3
Sep 2025168162.743.08$10,543
Aug 2025170163.933.01$10,871
Jul 20250166.743.32$3
Jun 2025168166.483.13$11,172
May 2025165160.553.23$9,994
Apr 20250162.363.54$4
Mar 2025171167.704.27$11,581
Feb 20250170.884.34$4
Jan 2025172174.324.28$12,787
Dec 2024172168.993.12$11,869
Nov 20240169.052.20$2
Oct 2024342171.372.28$24,411
Sep 20240169.612.36$2
Aug 20240175.632.06$2
Jul 2024171179.932.15$13,670
Jun 2024177178.082.63$13,823
May 20240178.812.20$2
Apr 2024170184.451.66$14,358
Mar 20240180.301.55$2
Feb 2024165176.091.78$12,557
Jan 2024172173.023.30$12,563
Dec 2023165171.262.61$11,761
Nov 20230177.892.81$3
Oct 2023157185.443.09$13,417
Sep 2023166189.042.74$14,783
Aug 2023171180.522.67$13,772
Jul 20230174.852.64$3
Jun 2023176168.962.26$12,139
May 2023178170.622.23$12,573
Apr 2023180178.122.24$14,064
Mar 20230172.852.39$2
Feb 2023177175.112.47$13,297
Jan 2023182176.533.39$13,932
Dec 2022172176.415.73$13,148
Nov 20220185.005.65$6
Oct 20220187.185.86$6
Sep 2022151184.888.16$12,825
Aug 20220194.529.13$9
Jul 20221751101.587.54$17,784
Jun 20221661115.097.98$19,113
May 202201109.378.43$8
Apr 20221671104.226.84$17,412
Mar 20221771108.885.08$19,277
Feb 20220191.054.86$5
Jan 20220181.844.54$5
Dec 2021170171.323.90$12,128
Nov 20210177.435.24$5
Oct 2021179179.795.71$14,288
Sep 20210169.865.35$5
Aug 2021175166.024.22$11,558
Jul 2021168170.783.98$11,895
Jun 20210169.493.38$3
May 20210163.483.02$3
Apr 20210160.362.76$3
Mar 20210161.302.72$3
Feb 2021168157.805.55$9,716
Jan 20210150.412.81$3
Dec 2020172144.642.68$7,681
Nov 20200138.772.71$3
Oct 20200136.972.48$2
Sep 2020168137.091.99$6,233
Aug 202001239.982.39$29
Jul 20201701238.371.83$6,545
Jun 20201671234.901.69$5,849
May 202001216.921.81$22
Apr 202001214.751.80$22
Mar 20203421230.341.86$10,399
Feb 20201701249.881.98$8,503
Jan 202001257.252.09$25
Dec 201901259.012.30$28
Nov 20191721255.302.75$9,545
Oct 201901253.472.42$29
Sep 20191661255.052.66$9,170
Aug 201901253.112.30$28
Jul 20193401256.272.46$19,161
Jun 201901252.782.49$30
May 20191691258.482.74$9,916
Apr 201901262.632.75$33
Mar 201901256.803.06$37
Feb 20191111250.852.79$5,678
Jan 20191291246.033.23$5,977
Dec 20181271246.594.19$5,967
Nov 20181261252.934.24$6,720
Oct 2018126061.443.40$7,741
Sep 201801259.543.11$37
Aug 20181211259.403.07$7,224
Jul 2018781265.142.93$5,116
Jun 20181151260.183.08$6,958
May 20181121265.382.90$7,357
Apr 20182161263.842.90$13,824
Mar 20181281261.222.79$7,870
Feb 20181231261.782.77$7,632
Jan 20181151262.874.01$7,278
Dec 201701257.272.92$35
Nov 20171131255.423.12$6,300
Oct 20172501249.292.98$12,358
Sep 201701247.523.09$37
Aug 20172101245.373.00$9,564
Jul 20171151243.873.09$5,082
Jun 20171261242.493.09$5,391
May 20171331245.373.26$6,073
Apr 20172251247.933.21$10,823
Mar 201701246.772.98$36
Feb 20171071250.452.95$5,434
Jan 2017109049.413.42$5,386
Dec 2016671248.763.72$3,312
Nov 20161061242.492.64$4,536
Oct 20161101246.193.09$5,118
Sep 2016781241.553.10$3,278
Aug 20161161241.442.92$4,842
Jul 20161151241.622.92$4,821
Jun 20162011245.352.69$9,148
May 20161231242.521.99$5,254
Apr 201601236.561.99$24
Mar 20161241233.011.79$4,115
Feb 20161241226.472.06$3,307
Jan 201601227.352.36$28
Dec 201501232.362.00$24
Nov 201501238.792.17$26
Oct 20151141243.552.43$4,994
Sep 20151001242.992.76$4,332
Aug 20151311240.162.87$5,295
Jul 201501248.152.95$35
Jun 201501256.152.88$35
May 20150055.212.96$0
Apr 201578049.822.71$3,886
Mar 20151611242.892.93$6,941
Feb 20151311244.662.98$5,886
Jan 20151311243.433.10$5,727
Dec 20141281254.693.59$7,043
Nov 20141381270.464.25$9,775
Oct 20141341278.303.90$10,539
Sep 20141351286.164.05$11,680
Aug 2014611289.394.04$5,501
Jul 20141291296.564.18$12,506
Jun 20141331298.164.74$13,112
May 20141301294.734.73$12,372
Apr 20141241295.944.81$11,954
Mar 201401295.895.06$61
Feb 20141331297.406.19$13,029
Jan 201401290.404.86$58
Dec 20131081291.824.35$9,969
Nov 201301288.853.74$45
Oct 201301297.423.78$45
Sep 20139512104.113.72$9,935
Aug 201313112104.253.52$13,699
Jul 2013012102.523.72$45
Jun 20131301294.403.93$12,319
May 201301294.834.15$50
Apr 2013911293.964.28$8,602
Mar 2013731293.623.91$6,881
Feb 201301291.233.42$41
Jan 20131141291.603.42$10,483
Dec 201201286.773.42$41
Nov 2012981286.953.62$8,565
Oct 201201289.383.40$41
Sep 20121021294.672.92$9,691
Aug 201201292.662.91$35
Jul 20121191285.133.02$10,167
Jun 201201279.822.52$30
May 201201291.612.49$30
Apr 201211512101.652.00$11,714
Mar 2012012105.052.22$27
Feb 201211012101.102.57$11,152
Jan 201201298.092.73$33
Dec 20111331296.873.24$12,923
Nov 201101295.723.31$40
Oct 201101284.983.65$44
Sep 20111411283.623.99$11,838
Aug 201101283.404.15$50
Jul 201101294.144.52$54
Jun 201101292.904.64$56
May 20111211298.134.40$11,927
Apr 20112312105.964.33$2,489
Mar 201101296.364.06$49
Feb 201101285.644.18$50
Jan 20111361286.504.59$11,819
Dec 201001285.734.35$52
Nov 201001280.843.80$46
Oct 201001278.103.51$42
Sep 201001272.633.98$48
Aug 20101121273.684.42$8,305
Jul 2010701272.554.74$5,135
Jun 2010701270.364.91$4,984
May 20101311271.124.24$9,368
Apr 201001281.694.12$49
Mar 201001278.394.39$53
Feb 201001273.585.44$65
Jan 20101281274.365.96$9,590
Dec 200901271.445.48$66
Nov 200901274.593.75$45
Oct 200901272.544.11$49
Sep 200901265.543.06$37
Aug 20091701267.423.22$11,500
Jul 200901261.133.46$42
Jun 200901266.163.90$47
May 200901254.743.93$47
Apr 200901246.773.59$43
Mar 200901242.144.06$49
Feb 20091761232.814.63$5,830
Jan 200901235.865.37$64
Dec 200801237.105.98$72
Nov 200801255.496.86$82
Oct 200801275.246.92$83
Sep 2008012101.767.88$95
Aug 2008012114.228.48$102
Jul 2008012131.0811.39$137
Jun 2008012131.3313.03$156
May 200818112123.1711.57$22,433
Apr 2008012110.3110.45$125
Mar 2008012101.909.66$116
Feb 200801292.538.77$105
Jan 200801290.388.21$98
Dec 200701288.337.30$88
Nov 20071821291.677.29$16,771
Oct 200701282.856.92$83
Sep 200701275.846.24$75
Aug 200701269.066.39$77
Jul 20071741270.906.39$12,413
Jun 200701262.007.55$91
May 200701258.747.85$94
Apr 200701259.617.81$94
Mar 20071841256.927.30$10,561
Feb 200701255.108.22$99
Jan 200701250.306.73$81
Dec 200601256.656.92$83
Nov 20061751254.207.62$9,576
Oct 200601254.906.01$72
Sep 200601260.085.04$60
Aug 200601268.717.34$88
Jul 200601269.376.34$76
Jun 200601266.286.38$77
May 200601266.016.42$77
Apr 200601264.397.36$88
Mar 20061711256.707.08$9,781
Feb 200601257.597.75$93
Jan 20061801260.598.93$11,013
Dec 200501254.9413.42$161
Nov 20051791254.6910.59$9,917
Oct 20051791258.3413.80$10,608
Sep 200501261.4512.08$145
Aug 200501261.519.80$118
Jul 200501255.697.84$94
Jun 200501252.337.38$89
May 20051771245.226.65$8,084
Apr 200501249.207.36$88
Mar 200501250.377.15$86
Feb 200501245.226.31$76
Jan 20051791243.166.32$7,802
Dec 200401239.866.75$81
Nov 20041751245.286.33$8,000
Oct 200401249.706.52$78
Sep 20041771243.245.28$7,717
Aug 200401242.375.55$67
Jul 20041761238.286.08$6,810
Jun 200401236.106.43$77
May 20041781237.486.49$6,749
Apr 20041721234.475.86$5,999
Mar 200401234.365.53$66
Feb 20041731232.455.51$5,680
Jan 200401232.036.30$76
Dec 200301230.266.30$76
Nov 20031771228.804.60$5,153
Oct 20031301228.174.76$3,719
Sep 200301226.314.75$57
Aug 200301229.765.13$62
Jul 20031771229.415.17$5,268
Jun 20031831228.565.98$5,298
May 200301226.595.97$72
Apr 200301226.675.41$65
Mar 20031821231.146.10$5,741
Feb 20031811233.487.93$6,155
Jan 200301230.315.58$67
Dec 200201226.914.85$58
Nov 20021781224.664.14$4,439
Oct 20020026.464.23$0
Sep 20021701227.443.64$4,708
Aug 20021741225.963.16$4,555
Jul 200201224.583.06$37
Jun 200201223.733.34$40
May 20021741224.663.58$4,334
Apr 200201223.653.51$42
Mar 20021741222.003.10$3,865
Feb 200201218.222.38$29
Jan 20021821217.172.38$3,153
Dec 20011741216.932.36$2,974
Nov 200101218.072.41$29
Oct 20011781219.782.53$3,551
Sep 200101224.262.25$27
Aug 200101224.873.05$37
Jul 20011741223.933.20$4,202
Jun 200101224.563.82$46
May 20011731225.524.31$4,467
Apr 200101224.685.34$64
Mar 200101224.545.38$65
Feb 200101227.755.77$69
Jan 20011751227.478.40$4,908
Dec 200001226.889.12$109
Nov 20001741232.215.66$5,672
Oct 20001291231.235.15$4,090
Sep 20001701231.875.19$5,480
Aug 20001331229.644.54$3,997
Jul 20003111228.534.09$8,922
Jun 200001229.304.40$53
May 20001741227.263.68$4,787
Apr 20001801224.513.12$4,449
Mar 20001791228.422.86$5,122
Feb 20001811227.622.73$5,032
Jan 20001331225.272.48$3,391
Dec 19991331224.282.42$3,258
Nov 19991331223.192.43$3,113
Oct 19991331220.982.80$2,824
Sep 19991301221.752.62$2,859
Aug 19991321219.262.88$2,577
Jul 199901217.892.37$28
Jun 19991611215.942.36$2,595
May 19991321215.792.32$2,112
Apr 19991311215.102.21$2,005
Mar 19991361212.471.84$1,718
Feb 1999133129.981.82$1,349
Jan 19991351210.381.90$1,424
Dec 1998173129.201.77$1,613
Nov 19981341210.892.19$1,485
Oct 19982851212.421.97$3,563
Sep 19981251212.592.08$1,599
Aug 19981251211.301.91$1,435
Jul 19981701211.742.24$2,023
Jun 19981301211.242.24$1,488
May 19981601212.622.21$2,046
Apr 19981451213.042.51$1,921
Mar 1998260112.802.31$3,330
Feb 1998148113.952.30$2,067
Jan 1998177114.702.15$2,604
Dec 1997133116.322.41$2,173
Nov 1997159118.193.09$2,895
Oct 1997148119.253.15$2,852
Sep 1997132117.742.95$2,345
Aug 1997134117.862.55$2,396
Jul 1997161117.582.25$2,833
Jun 1997158117.242.26$2,726
May 1997126118.972.31$2,393
Apr 1997131117.882.08$2,344
Mar 1997154118.951.94$2,920
Feb 1997174120.492.21$3,567
Jan 1997149123.483.54$3,502
Dec 1996262123.32$6,110
Nov 19960121.97$0
Oct 1996328123.31$7,646
Sep 1996172122.22$3,822
Aug 19960120.26$0
Jul 1996265119.55$5,181
Jun 1996167118.73$3,128
May 1996130119.43$2,526
Apr 1996130121.51$2,796
Mar 1996130119.38$2,519
Feb 1996135116.98$2,292
Jan 1996134117.07$2,287
Dec 1995135117.19$2,321
Nov 1995133116.00$2,128
Oct 1995133115.43$2,052
Sep 1995175116.18$2,832
Aug 1995132115.92$2,101
Jul 1995130115.24$1,981
Jun 19950116.41$0
May 1995133117.56$2,335
Apr 1995132117.73$2,340
Mar 1995165116.44$2,713
Feb 1995134116.58$2,222
Jan 1995168115.92$2,675
Dec 1994267115.03$4,013
Nov 1994134115.90$2,131
Oct 1994132115.58$2,057
Sep 1994133115.29$2,034
Aug 1994152116.13$2,452
Jul 1994139117.56$2,441
Jun 1994264117.09$4,512
May 1994131115.88$2,080
Apr 1994133114.14$1,881
Mar 1994305112.46$3,800
Feb 1994135112.50$1,688
Jan 1994135112.66$1,709
Dec 1993134112.33$1,652
Nov 1993310114.49$4,492
Oct 1993133115.85$2,108
Sep 1993129115.03$1,939
Aug 1993132115.66$2,067
Jul 1993265115.46$4,097
Jun 1993174116.79$2,921
May 1993173117.68$3,059
Apr 1993178118.05$3,213
Mar 1993341118.14$6,186
Feb 19930117.90$0
Jan 1993167116.93$2,827

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Oil                  169 bbl  × $106.41 =    $17,983
Casinghead gas         1 Mcf  × $  3.05 =         $3

────────────────────────────────────────────────────
Month total                                  $17,986

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 09/O/6408 is the state's own key, not one this site invented.