GEORGE "A"

Operated by PRESIDIO PETROLEUM LLC (P-5 676084) in the CANADIAN, SE (DOUGLAS) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 183971District 10Field 15217250CondensateGasSaveExport
Value, all time
$180 k
Feb 2001 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
304
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 419 leases and 430 wells, and the rule below applies to all of them.

Discovered
1972-08-01
as the register files it
Field class
Oil and gas
the register's own label
Between wells
1,320 ft
minimum
From a lease line
660 ft
minimum

A drilling unit in this field needs at least 160 acres.

The Commission's schedule remark for this field reads: COMBINED W/HUMPHREYS (DOUGLAS) 9/81 CARRIED AS CANADIAN,SE (DOUGLA

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition1,294 bbl$59,822
GasProduction25,962 Mcf$119,950
Total$179,772

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 35.7998, -100.3783. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

35.79977, -100.37827 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
12,636 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 12,636 ft.

Completions filed
Mar 2001
1 of 1 wells

1 well

42-211324677045U12,636 ftMar 2001

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (304)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

304 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 202342085.443.09$3,588
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20190056.803.06$0
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 20180059.543.11$0
Aug 20180059.403.07$0
Jul 20180065.142.93$0
Jun 20180060.183.08$0
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 20170045.373.00$0
Jul 20170043.873.09$0
Jun 20170042.493.09$0
May 20170045.373.26$0
Apr 20170047.933.21$0
Mar 20170046.772.98$0
Feb 20170050.452.95$0
Jan 20170049.413.42$0
Dec 20160048.763.72$0
Nov 20160042.492.64$0
Oct 20160046.193.09$0
Sep 20160041.553.10$0
Aug 20160041.442.92$0
Jul 20160041.622.92$0
Jun 20160045.352.69$0
May 20160042.521.99$0
Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 20160426.472.06$8
Jan 20160327.352.36$7
Dec 20150032.362.00$0
Nov 20150038.792.17$0
Oct 20150043.552.43$0
Sep 20150042.992.76$0
Aug 20150940.162.87$26
Jul 20150248.152.95$6
Jun 20150256.152.88$6
May 201503555.212.96$103
Apr 20150049.822.71$0
Mar 20150042.892.93$0
Feb 20150044.662.98$0
Jan 20150043.433.10$0
Dec 20140054.693.59$0
Nov 20140070.464.25$0
Oct 20140078.303.90$0
Sep 20140086.164.05$0
Aug 20140089.394.04$0
Jul 20140096.564.18$0
Jun 20140098.164.74$0
May 201402594.734.73$118
Apr 20140095.944.81$0
Mar 20140095.895.06$0
Feb 20140097.406.19$0
Jan 20140090.404.86$0
Dec 20130091.824.35$0
Nov 20130088.853.74$0
Oct 20131834497.423.78$17,994
Sep 2013039104.113.72$145
Aug 2013042104.253.52$148
Jul 2013047102.523.72$175
Jun 201303794.403.93$146
May 201304294.834.15$174
Apr 201306693.964.28$283
Mar 201302793.623.91$106
Feb 201306491.233.42$219
Jan 201305791.603.42$195
Dec 201205186.773.42$174
Nov 20120086.953.62$0
Oct 201207789.383.40$262
Sep 20120094.672.92$0
Aug 20120092.662.91$0
Jul 20120085.133.02$0
Jun 20120079.822.52$0
May 20120091.612.49$0
Apr 201200101.652.00$0
Mar 201202105.052.22$4
Feb 201202101.102.57$5
Jan 20120298.092.73$5
Dec 20110296.873.24$6
Nov 20110295.723.31$7
Oct 20110284.983.65$7
Sep 20110283.623.99$8
Aug 20110283.404.15$8
Jul 20110294.144.52$9
Jun 20110092.904.64$0
May 20110298.134.40$9
Apr 201102105.964.33$9
Mar 20110296.364.06$8
Feb 20110285.644.18$8
Jan 20110286.504.59$9
Dec 20100085.734.35$0
Nov 20100080.843.80$0
Oct 20100078.103.51$0
Sep 20100072.633.98$0
Aug 20100073.684.42$0
Jul 20100072.554.74$0
Jun 20100070.364.91$0
May 20100671.124.24$25
Apr 20100881.694.12$33
Mar 201001578.394.39$66
Feb 20100873.585.44$44
Jan 201001074.365.96$60
Dec 200901071.445.48$55
Nov 200902574.593.75$94
Oct 200901472.544.11$58
Sep 200902265.543.06$67
Aug 200901367.423.22$42
Jul 200901761.133.46$59
Jun 200902666.163.90$101
May 200902454.743.93$94
Apr 200902046.773.59$72
Mar 200902742.144.06$110
Feb 200903532.814.63$162
Jan 200903935.865.37$209
Dec 200804737.105.98$281
Nov 200803855.496.86$261
Oct 200805075.246.92$346
Sep 2008024101.767.88$189
Aug 2008019114.228.48$161
Jul 200800131.0811.39$0
Jun 2008056131.3313.03$730
May 2008016123.1711.57$185
Apr 2008063110.3110.45$659
Mar 2008024101.909.66$232
Feb 200804092.538.77$351
Jan 200808390.388.21$681
Dec 200707288.337.30$526
Nov 200708391.677.29$605
Oct 200706982.856.92$478
Sep 200707575.846.24$468
Aug 20071703269.066.39$11,945
Jul 200708170.906.39$517
Jun 200708262.007.55$619
May 2007010858.747.85$847
Apr 200709459.617.81$734
Mar 200707956.927.30$577
Feb 200706255.108.22$509
Jan 2007010250.306.73$686
Dec 200607756.656.92$533
Nov 200607854.207.62$594
Oct 200607154.906.01$427
Sep 2006010160.085.04$509
Aug 200609768.717.34$712
Jul 2006010169.376.34$641
Jun 200608866.286.38$562
May 2006010866.016.42$694
Apr 200609364.397.36$685
Mar 2006011856.707.08$836
Feb 2006011157.597.75$860
Jan 2006012160.598.93$1,081
Dec 2005011554.9413.42$1,543
Nov 2005011454.6910.59$1,207
Oct 2005012758.3413.80$1,752
Sep 2005011161.4512.08$1,341
Aug 2005014861.519.80$1,450
Jul 2005013855.697.84$1,082
Jun 200511511552.337.38$6,867
May 2005014445.226.65$958
Apr 2005013649.207.36$1,001
Mar 2005014350.377.15$1,023
Feb 2005013345.226.31$839
Jan 2005014243.166.32$898
Dec 2004013939.866.75$938
Nov 2004012445.286.33$785
Oct 2004015049.706.52$977
Sep 2004012643.245.28$666
Aug 2004015042.375.55$833
Jul 2004015438.286.08$937
Jun 200412914936.106.43$5,615
May 2004016737.486.49$1,085
Apr 2004015734.475.86$920
Mar 2004015534.365.53$857
Feb 2004015732.455.51$865
Jan 2004017032.036.30$1,071
Dec 2003016730.266.30$1,052
Nov 2003014328.804.60$657
Oct 2003015728.174.76$747
Sep 2003015826.314.75$750
Aug 2003014829.765.13$759
Jul 20035416029.415.17$2,415
Jun 2003026028.565.98$1,556
May 2003017526.595.97$1,045
Apr 2003014126.675.41$762
Mar 2003013731.146.10$835
Feb 2003013233.487.93$1,046
Jan 20036415230.315.58$2,788
Dec 2002014626.914.85$709
Nov 2002010024.664.14$414
Oct 2002010026.464.23$423
Sep 2002483427.443.64$1,441
Aug 2002014325.963.16$452
Jul 2002019824.583.06$606
Jun 2002019423.733.34$648
May 20027624024.663.58$2,734
Apr 2002025023.653.51$878
Mar 2002028922.003.10$897
Feb 2002076218.222.38$1,810
Jan 20027690017.172.38$3,443
Dec 2001098616.932.36$2,331
Nov 200101,05718.072.41$2,543
Oct 2001741,06419.782.53$4,154
Sep 200101,05524.262.25$2,375
Aug 200101,19624.873.05$3,652
Jul 2001671,23423.933.20$5,549
Jun 200101,55824.563.82$5,958
May 2001911,99125.524.31$10,898
Apr 200101,97624.685.34$10,543
Mar 20011051,38124.545.38$10,002
Feb 2001023127.755.77$1,332

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Oct 2023 — as filed, then multipliedworked
Condensate            42 bbl  × $ 85.44 =     $3,588
Gas                    0 Mcf  × $  3.09 =         $0

────────────────────────────────────────────────────
Month total                                   $3,588

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 10/G/183971 is the state's own key, not one this site invented.