BORN 863

Operated by LATIGO PETROLEUM, LLC (P-5 488260) in the LIPSCOMB (CLEVELAND) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 196751District 10Field 538692702 tax incentive programmesCondensateGasSaveExport
Value, all time
$5.0 M
Dec 2002 – May 2026
Value, last 12 filed months
$27 k
at the published price for each month
Months reported
282
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 1,389 leases and 1,486 wells, and the rule below applies to all of them.

Discovered
1958-05-24
as the register files it
Field class
Oil and gas
the register's own label
Between wells
0 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2013-08-06.

The Commission's schedule remark for this field reads: FIELD

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112004-06-25157737
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition3,141 bbl$166,159
GasProduction831,101 Mcf$4,797,764
Total$4,963,922

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 36.3270, -100.3218. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

36.32702, -100.32184 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
no depth filed
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

Completions filed
Dec 2002
1 of 1 wells

1 well

42-295326605Dec 2002

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (282)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

282 months

May 20260633106.413.05$1,928
Apr 2026067598.932.87$1,937
Mar 2026066789.753.15$2,101
Feb 2026060563.503.75$2,269
Jan 2026065959.138.00$5,271
Dec 2025042556.664.41$1,876
Nov 2025042058.593.93$1,649
Oct 2025068459.383.30$2,261
Sep 2025054862.743.08$1,686
Aug 2025065663.933.01$1,978
Jul 2025067666.743.32$2,241
Jun 2025070566.483.13$2,206
May 2025065960.553.23$2,130
Apr 2025062662.363.54$2,218
Mar 2025065567.704.27$2,796
Feb 2025062170.884.34$2,696
Jan 2025064374.324.28$2,751
Dec 2024065868.993.12$2,054
Nov 2024064969.052.20$1,427
Oct 2024061871.372.28$1,410
Sep 2024029669.612.36$700
Aug 2024064875.632.06$1,337
Jul 2024068779.932.15$1,475
Jun 2024072678.082.63$1,912
May 20240078.812.20$0
Apr 2024081684.451.66$1,354
Mar 2024079280.301.55$1,224
Feb 2024082776.091.78$1,475
Jan 2024082773.023.30$2,727
Dec 2023090371.262.61$2,357
Nov 202314981877.892.81$13,902
Oct 2023091985.443.09$2,837
Sep 2023092589.042.74$2,530
Aug 2023080480.522.67$2,149
Jul 2023077774.852.64$2,053
Jun 2023090768.962.26$2,048
May 2023091470.622.23$2,036
Apr 202301,01178.122.24$2,262
Mar 202301,04772.852.39$2,506
Feb 2023095575.112.47$2,355
Jan 202301,06576.533.39$3,608
Dec 2022095776.415.73$5,483
Nov 202201,05285.005.65$5,940
Oct 202201,11387.185.86$6,526
Sep 202201,09784.888.16$8,956
Aug 202201,15594.529.13$10,542
Jul 202201,181101.587.54$8,907
Jun 202201,179115.097.98$9,405
May 202201,181109.378.43$9,959
Apr 20220867104.226.84$5,928
Mar 20220516108.885.08$2,619
Feb 2022072691.054.86$3,528
Jan 2022080881.844.54$3,666
Dec 2021081771.323.90$3,186
Nov 2021084277.435.24$4,409
Oct 2021077079.795.71$4,400
Sep 2021082369.865.35$4,404
Aug 2021087066.024.22$3,672
Jul 2021188470.783.98$3,591
Jun 2021086569.493.38$2,924
May 2021086063.483.02$2,595
Apr 2021087960.362.76$2,425
Mar 2021090861.302.72$2,467
Feb 2021072457.805.55$4,017
Jan 2021092350.412.81$2,594
Dec 2020090944.642.68$2,432
Nov 2020487438.772.71$2,521
Oct 2020094936.972.48$2,352
Sep 2020089737.091.99$1,786
Aug 2020092339.982.39$2,201
Jul 20200038.371.83$0
Jun 2020080734.901.69$1,364
May 20201601,04216.921.81$4,598
Apr 202001,12014.751.80$2,021
Mar 202001,16130.341.86$2,155
Feb 202001,17749.881.98$2,331
Jan 2020064357.252.09$1,347
Dec 201901,31159.012.30$3,021
Nov 201901,49655.302.75$4,115
Oct 201901,19853.472.42$2,897
Sep 2019093055.052.66$2,471
Aug 2019091053.112.30$2,097
Jul 201901,02856.272.46$2,529
Jun 201901,01952.782.49$2,539
May 2019096158.482.74$2,633
Apr 2019086762.632.75$2,385
Mar 2019094856.803.06$2,903
Feb 2019089550.852.79$2,499
Jan 201901,10846.033.23$3,577
Dec 201801,23346.594.19$5,161
Nov 2018072152.934.24$3,055
Oct 2018066061.443.40$2,243
Sep 2018083059.543.11$2,580
Aug 201801,02359.403.07$3,137
Jul 201801,05965.142.93$3,105
Jun 201802,38460.183.08$7,335
May 201801,07465.382.90$3,115
Apr 201801,08163.842.90$3,136
Mar 201801,13261.222.79$3,155
Feb 2018099461.782.77$2,750
Jan 201801,12662.874.01$4,514
Dec 201701,15057.272.92$3,360
Nov 201701,15555.423.12$3,602
Oct 201701,09149.292.98$3,255
Sep 201701,16247.523.09$3,587
Aug 201701,10645.373.00$3,323
Jul 201701,03343.873.09$3,189
Jun 201701,06942.493.09$3,300
May 201701,14845.373.26$3,746
Apr 201701,17847.933.21$3,783
Mar 201701,05046.772.98$3,133
Feb 201701,04550.452.95$3,085
Jan 201701,01149.413.42$3,456
Dec 201601,18548.763.72$4,412
Nov 201601,21242.492.64$3,205
Oct 201601,21446.193.09$3,752
Sep 201601,17441.553.10$3,640
Aug 2016251,30441.442.92$4,849
Jul 201601,19641.622.92$3,498
Jun 201601,17045.352.69$3,142
May 201601,08342.521.99$2,156
Apr 201601,28836.561.99$2,564
Mar 201601,22433.011.79$2,196
Feb 2016681,29526.472.06$4,472
Jan 201601,52427.352.36$3,603
Dec 201501,30532.362.00$2,612
Nov 201501,22338.792.17$2,651
Oct 201501,35943.552.43$3,298
Sep 201501,36742.992.76$3,771
Aug 201501,32540.162.87$3,806
Jul 201501,39248.152.95$4,100
Jun 201501,20456.152.88$3,471
May 201501,20255.212.96$3,552
Apr 201501,23949.822.71$3,353
Mar 201501,23342.892.93$3,619
Feb 2015561,20944.662.98$6,099
Jan 201501,35243.433.10$4,192
Dec 201401,19954.693.59$4,306
Nov 201401,28270.464.25$5,451
Oct 201401,43778.303.90$5,606
Sep 201401,36386.164.05$5,514
Aug 201401,28189.394.04$5,169
Jul 201401,33496.564.18$5,576
Jun 201401,30798.164.74$6,191
May 201401,38994.734.73$6,565
Apr 2014501,22195.944.81$10,669
Mar 201401,41395.895.06$7,145
Feb 201401,25297.406.19$7,752
Jan 201401,48690.404.86$7,223
Dec 201301,46391.824.35$6,371
Nov 201301,50888.853.74$5,637
Oct 201301,59897.423.78$6,039
Sep 2013471,567104.113.72$10,719
Aug 201301,627104.253.52$5,731
Jul 201301,440102.523.72$5,354
Jun 201301,21994.403.93$4,795
May 2013521,52194.834.15$11,242
Apr 201301,55093.964.28$6,638
Mar 201301,51393.623.91$5,920
Feb 201301,38891.233.42$4,747
Jan 201301,36291.603.42$4,658
Dec 201201,60286.773.42$5,479
Nov 201201,43786.953.62$5,209
Oct 201201,55889.383.40$5,297
Sep 201201,46894.672.92$4,284
Aug 201201,47792.662.91$4,295
Jul 2012671,58085.133.02$10,477
Jun 201201,52979.822.52$3,852
May 201201,66991.612.49$4,153
Apr 201201,680101.652.00$3,355
Mar 201201,597105.052.22$3,549
Feb 201201,741101.102.57$4,475
Jan 201201,94798.092.73$5,323
Dec 201101,74396.873.24$5,647
Nov 201102,21595.723.31$7,334
Oct 201102,23184.983.65$8,140
Sep 201125750583.623.99$23,503
Aug 201102,09183.404.15$8,676
Jul 201102,44494.144.52$11,040
Jun 201101,93492.904.64$8,974
May 201101,63698.134.40$7,206
Apr 201101,623105.964.33$7,033
Mar 201102,33496.364.06$9,470
Feb 201101,76485.644.18$7,373
Jan 201102,05286.504.59$9,416
Dec 201001,80085.734.35$7,826
Nov 201001,91280.843.80$7,257
Oct 201002,15378.103.51$7,555
Sep 201002,20172.633.98$8,759
Aug 201002,11473.684.42$9,343
Jul 201001,95172.554.74$9,241
Jun 201001,84970.364.91$9,079
May 201002,06071.124.24$8,725
Apr 201002,15381.694.12$8,876
Mar 201002,02078.394.39$8,865
Feb 201002,05373.585.44$11,173
Jan 201002,48674.365.96$14,827
Dec 200902,54971.445.48$13,978
Nov 200902,39674.593.75$8,989
Oct 200902,48872.544.11$10,226
Sep 200902,43965.543.06$7,475
Aug 200902,22567.423.22$7,161
Jul 200902,21361.133.46$7,667
Jun 200902,08366.163.90$8,113
May 200902,08054.743.93$8,166
Apr 200902,83346.773.59$10,163
Mar 200901,99842.144.06$8,110
Feb 20091802,27532.814.63$16,446
Jan 200902,38035.865.37$12,783
Dec 200802,49337.105.98$14,901
Nov 200802,64755.496.86$18,159
Oct 200802,84975.246.92$19,721
Sep 200803,677101.767.88$28,964
Aug 200802,349114.228.48$19,927
Jul 20080405131.0811.39$4,613
Jun 200802,072131.3313.03$27,004
May 200802,559123.1711.57$29,619
Apr 200803,259110.3110.45$34,072
Mar 200803,460101.909.66$33,438
Feb 20081893,47192.538.77$47,931
Jan 200804,08190.388.21$33,488
Dec 200704,21588.337.30$30,778
Nov 200704,53391.677.29$33,053
Oct 200704,96782.856.92$34,381
Sep 200706,12975.846.24$38,270
Aug 20071941,09369.066.39$20,380
Jul 20070370.906.39$19
Jun 200701,66262.007.55$12,546
May 200703,83058.747.85$30,051
Apr 200704,05759.617.81$31,666
Mar 200704,41656.927.30$32,246
Feb 200704,24455.108.22$34,869
Jan 200703,97350.306.73$26,726
Dec 200604,81756.656.92$33,326
Nov 200604,47254.207.62$34,065
Oct 200605,20354.906.01$31,290
Sep 200605,25460.085.04$26,465
Aug 20061175,70768.717.34$49,928
Jul 200606,12569.376.34$38,849
Jun 200606,23266.286.38$39,784
May 200607,18966.016.42$46,189
Apr 200603,18064.397.36$23,406
Mar 20061883,52256.707.08$35,606
Feb 200605,65457.597.75$43,825
Jan 200606,43060.598.93$57,441
Dec 200505,58654.9413.42$74,938
Nov 200505,65354.6910.59$59,856
Oct 200506,96258.3413.80$96,046
Sep 200506,71061.4512.08$81,050
Aug 200507,10361.519.80$69,587
Jul 20052106,64955.697.84$63,847
Jun 200508,70552.337.38$64,252
May 200503,57945.226.65$23,805
Apr 200507,10849.207.36$52,318
Mar 200506,70550.377.15$47,973
Feb 200506,51345.226.31$41,110
Jan 200507,25343.166.32$45,855
Dec 20041987,59339.866.75$59,153
Nov 200407,70945.286.33$48,801
Oct 200408,66649.706.52$56,460
Sep 200408,47943.245.28$44,802
Aug 20041397,83942.375.55$49,401
Jul 200409,17838.286.08$55,841
Jun 200409,14036.106.43$58,798
May 200409,48037.486.49$61,569
Apr 200409,64734.475.86$56,517
Mar 2004010,35034.365.53$57,237
Feb 200408,05432.455.51$44,374
Jan 200419111,48132.036.30$78,444
Dec 2003012,80830.266.30$80,711
Nov 2003013,14728.804.60$60,413
Oct 2003013,68828.174.76$65,150
Sep 200315714,85526.314.75$74,682
Aug 2003017,07929.765.13$87,610
Jul 2003018,78629.415.17$97,139
Jun 20038317,50528.565.98$107,102
May 2003022,53026.595.97$134,564
Apr 200316726,38726.675.41$147,136
Mar 2003035,02831.146.10$213,532
Feb 200319239,90633.487.93$322,718
Jan 2003013,61330.315.58$75,988
Dec 20020026.914.85$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                  633 Mcf  × $  3.05 =     $1,928

────────────────────────────────────────────────────
Month total                                   $1,928

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 10/G/196751 is the state's own key, not one this site invented.