BYRUM 27

Operated by BCE-MACH III LLC (P-5 40209) in the RED DEER CREEK (GRANITE WASH) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 227995District 10Field 752003002 tax incentive programmesCondensateGasSaveExport
Value, all time
$2.8 M
Mar 2007 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
231
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 157 leases and 157 wells, and the rule below applies to all of them.

Discovered
1978-03-16
as the register files it
Field class
Oil and gas
the register's own label
Between wells
467 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2008-09-09.

The Commission's schedule remark for this field reads: AND PLAT AS LONG AS THE ALLOCATION IS SUSPENDED.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112007-12-12179511
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition5,303 bbl$408,251
GasProduction368,767 Mcf$2,423,655
Total$2,831,906

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 35.7742, -100.5920. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

35.77417, -100.59198 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
11,050 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 11,050 ft.

1 well

42-393319271311,050 ft

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (231)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

231 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20190056.803.06$0
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 20180059.543.11$0
Aug 20180059.403.07$0
Jul 20180065.142.93$0
Jun 20180060.183.08$0
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 20170045.373.00$0
Jul 20170043.873.09$0
Jun 20170042.493.09$0
May 20170045.373.26$0
Apr 20170047.933.21$0
Mar 20170046.772.98$0
Feb 20170050.452.95$0
Jan 20170049.413.42$0
Dec 20160048.763.72$0
Nov 20160042.492.64$0
Oct 201682046.193.09$3,788
Sep 20160041.553.10$0
Aug 20160041.442.92$0
Jul 20160041.622.92$0
Jun 20161145.352.69$48
May 20160042.521.99$0
Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 20160026.472.06$0
Jan 20160027.352.36$0
Dec 20150032.362.00$0
Nov 20150038.792.17$0
Oct 20150043.552.43$0
Sep 20150042.992.76$0
Aug 20151140.162.87$43
Jul 2015932248.152.95$1,382
Jun 201574,97856.152.88$14,744
May 20154569455.212.96$4,536
Apr 2015551349.822.71$1,638
Mar 2015029342.892.93$860
Feb 2015331344.662.98$1,066
Jan 201508043.433.10$248
Dec 2014118054.693.59$701
Nov 2014335570.464.25$1,721
Oct 201403078.303.90$117
Sep 2014232,13686.164.05$10,623
Aug 20142042,03489.394.04$26,443
Jul 2014342,17796.564.18$12,382
Jun 2014102,26798.164.74$11,720
May 2014232,07094.734.73$11,963
Apr 201481,37295.944.81$7,366
Mar 2014171,68695.895.06$10,156
Feb 201471,40897.406.19$9,400
Jan 201401,49290.404.86$7,252
Dec 20131911,60891.824.35$24,540
Nov 2013252,24988.853.74$10,629
Oct 201302,94397.423.78$11,123
Sep 20131882,809104.113.72$30,016
Aug 201302,347104.253.52$8,268
Jul 201302,900102.523.72$10,781
Jun 20131812,03194.403.93$25,075
May 201302,92594.834.15$12,136
Apr 201302,76393.964.28$11,833
Mar 201302,65393.623.91$10,381
Feb 2013272,25691.233.42$10,179
Jan 201302,63191.603.42$8,998
Dec 20121862,31786.773.42$24,064
Nov 201202,71186.953.62$9,827
Oct 201202,65089.383.40$9,009
Sep 201201,91994.672.92$5,600
Aug 201202,25092.662.91$6,543
Jul 20121862,11385.133.02$22,217
Jun 201202,29179.822.52$5,771
May 201202,04391.612.49$5,084
Apr 20121842,350101.652.00$23,396
Mar 201201,366105.052.22$3,035
Feb 20120985101.102.57$2,532
Jan 201201,16098.092.73$3,172
Dec 201101,02796.873.24$3,327
Nov 2011088795.723.31$2,937
Oct 201101,38684.983.65$5,057
Sep 201101,04783.623.99$4,173
Aug 2011076583.404.15$3,174
Jul 2011014994.144.52$673
Jun 20110092.904.64$0
May 20110098.134.40$0
Apr 201100105.964.33$0
Mar 20110096.364.06$0
Feb 20110085.644.18$0
Jan 20110086.504.59$0
Dec 20100085.734.35$0
Nov 20100080.843.80$0
Oct 20100078.103.51$0
Sep 20100072.633.98$0
Aug 20100073.684.42$0
Jul 20100072.554.74$0
Jun 20100070.364.91$0
May 201003171.124.24$131
Apr 201002781.694.12$111
Mar 201006278.394.39$272
Feb 201008873.585.44$479
Jan 2010022974.365.96$1,366
Dec 2009038571.445.48$2,111
Nov 2009048874.593.75$1,831
Oct 2009076172.544.11$3,128
Sep 200901,02565.543.06$3,141
Aug 200901,27767.423.22$4,110
Jul 200901,65461.133.46$5,730
Jun 200901,55866.163.90$6,068
May 200901,59754.743.93$6,269
Apr 200902,12746.773.59$7,631
Mar 200904,15742.144.06$16,873
Feb 20091824,06032.814.63$24,781
Jan 200904,15735.865.37$22,327
Dec 20081965,34837.105.98$39,237
Nov 200806,05455.496.86$41,533
Oct 200804,93875.246.92$34,181
Sep 200803,163101.767.88$24,915
Aug 200805,280114.228.48$44,790
Jul 20081806,173131.0811.39$93,901
Jun 200804,348131.3313.03$56,666
May 200807,150123.1711.57$82,756
Apr 20081838,876110.3110.45$112,984
Mar 200809,269101.909.66$89,576
Feb 2008138,23792.538.77$73,446
Jan 200806,65890.388.21$54,634
Dec 200719410,43588.337.30$93,332
Nov 200720115,36491.677.29$130,455
Oct 200719219,85282.856.92$153,322
Sep 200719517,60175.846.24$124,692
Aug 200737518,47469.066.39$143,908
Jul 200757825,48270.906.39$203,758
Jun 200738924,34762.007.55$207,900
May 200757331,47058.747.85$280,580
Apr 200720119,85859.617.81$166,977
Mar 200702,77456.927.30$20,256

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Oct 2016 — as filed, then multipliedworked
Condensate            82 bbl  × $ 46.19 =     $3,788
Gas                    0 Mcf  × $  3.09 =         $0

────────────────────────────────────────────────────
Month total                                   $3,788

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 10/G/227995 is the state's own key, not one this site invented.