BLASDEL

Operated by PRESIDIO PETROLEUM LLC (P-5 676084) in the KIRSTEN (GRANITE WASH) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 236232District 10Field 496892802 tax incentive programmesCondensateGasSaveExport
Value, all time
$4.3 M
Feb 2008 – May 2026
Value, last 12 filed months
$162 k
at the published price for each month
Months reported
220
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 7 leases and 7 wells, and the rule below applies to all of them.

Discovered
1994-08-20
as the register files it
Field class
Gas
the register's own label
Between wells
1,320 ft
minimum
From a lease line
660 ft
minimum

A drilling unit in this field needs at least 640 acres. The field rule took effect on 2005-09-01.

The Commission's schedule remark for this field reads: AOF-1 AND AOF-2 EFFECTIVE 04/01/2006.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112008-07-15183614
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition14,621 bbl$1,174,245
GasProduction537,016 Mcf$3,097,000
Total$4,271,245

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 35.5300, -100.2392. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

35.53003, -100.23921 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
14,130 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 14,130 ft.

Completions filed
Feb 2008
1 of 1 wells

1 well

42-4833232610414,130 ftFeb 2008

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (220)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

220 months

May 202606,369106.413.05$19,399
Apr 202606,19698.932.87$17,781
Mar 202605,31589.753.15$16,739
Feb 202606,28363.503.75$23,563
Jan 202605,98559.138.00$47,868
Dec 202504,69356.664.41$20,712
Nov 2025076158.593.93$2,988
Oct 2025079359.383.30$2,621
Sep 2025074462.743.08$2,289
Aug 2025078563.933.01$2,367
Jul 2025080366.743.32$2,662
Jun 2025084066.483.13$2,628
May 2025091160.553.23$2,945
Apr 2025090662.363.54$3,210
Mar 2025092667.704.27$3,952
Feb 2025086470.884.34$3,750
Jan 2025090074.324.28$3,851
Dec 2024094268.993.12$2,940
Nov 2024090769.052.20$1,994
Oct 2024088071.372.28$2,008
Sep 2024085569.612.36$2,022
Aug 2024083775.632.06$1,727
Jul 2024081179.932.15$1,741
Jun 2024082878.082.63$2,181
May 2024091678.812.20$2,014
Apr 2024075484.451.66$1,251
Mar 2024087780.301.55$1,355
Feb 2024087976.091.78$1,568
Jan 2024089373.023.30$2,945
Dec 2023091271.262.61$2,381
Nov 2023084377.892.81$2,367
Oct 2023092885.443.09$2,865
Sep 2023093389.042.74$2,552
Aug 2023088980.522.67$2,376
Jul 2023085374.852.64$2,253
Jun 2023085068.962.26$1,920
May 2023088070.622.23$1,960
Apr 2023089378.122.24$1,998
Mar 202301,01372.852.39$2,424
Feb 2023087575.112.47$2,157
Jan 2023092976.533.39$3,147
Dec 2022084176.415.73$4,818
Nov 2022079885.005.65$4,506
Oct 2022080687.185.86$4,726
Sep 2022069484.888.16$5,666
Aug 2022078694.529.13$7,174
Jul 20220662101.587.54$4,993
Jun 20220697115.097.98$5,560
May 20220765109.378.43$6,451
Apr 20220766104.226.84$5,238
Mar 20220738108.885.08$3,746
Feb 2022089591.054.86$4,349
Jan 2022088681.844.54$4,020
Dec 2021093171.323.90$3,630
Nov 2021077277.435.24$4,043
Oct 2021080379.795.71$4,588
Sep 2021089369.865.35$4,778
Aug 2021089066.024.22$3,756
Jul 2021083670.783.98$3,329
Jun 2021081369.493.38$2,748
May 20219280863.483.02$8,278
Apr 2021074260.362.76$2,047
Mar 2021085761.302.72$2,328
Feb 2021061057.805.55$3,384
Jan 2021096750.412.81$2,718
Dec 202001,13544.642.68$3,037
Nov 202001,12838.772.71$3,053
Oct 202001,14936.972.48$2,848
Sep 202001,16037.091.99$2,310
Aug 202001,17139.982.39$2,793
Jul 202001,24038.371.83$2,263
Jun 202001,17734.901.69$1,989
May 202001,30716.921.81$2,372
Apr 202001,38414.751.80$2,497
Mar 202001,33330.341.86$2,474
Feb 2020067949.881.98$1,345
Jan 20201821,32657.252.09$13,197
Dec 201901,27359.012.30$2,933
Nov 201901,46855.302.75$4,038
Oct 201901,41753.472.42$3,427
Sep 201901,33955.052.66$3,558
Aug 201901,39253.112.30$3,208
Jul 201901,39056.272.46$3,419
Jun 20191921,47052.782.49$13,796
May 201901,37158.482.74$3,757
Apr 201901,00962.632.75$2,775
Mar 201921,05656.803.06$3,347
Feb 2019196450.852.79$2,743
Jan 201911,55446.033.23$5,063
Dec 20182031,56446.594.19$16,004
Nov 201811,44552.934.24$6,176
Oct 201811,30861.443.40$4,506
Sep 201801,19159.543.11$3,702
Aug 201811,38259.403.07$4,297
Jul 20181961,41865.142.93$16,925
Jun 201811,88460.183.08$5,857
May 201811,71165.382.90$5,029
Apr 201801,64863.842.90$4,781
Mar 201811,67361.222.79$4,724
Feb 20181981,49561.782.77$16,368
Jan 201821,88262.874.01$7,671
Dec 201711,68857.272.92$4,989
Nov 20171961,39155.423.12$15,200
Oct 201711,76749.292.98$5,321
Sep 201751,39547.523.09$4,544
Aug 201701,87445.373.00$5,630
Jul 20172011,55643.873.09$13,622
Jun 201741,85442.493.09$5,894
May 201771,87545.373.26$6,436
Apr 201741,72847.933.21$5,741
Mar 20171961,80846.772.98$14,561
Feb 201751,38350.452.95$4,336
Jan 201731,42149.413.42$5,006
Dec 20162051,41848.763.72$15,275
Nov 201641,50742.492.64$4,155
Oct 201631,43346.193.09$4,567
Sep 201631,54441.553.10$4,912
Aug 20161941,63341.442.92$12,815
Jul 201631,73341.622.92$5,193
Jun 201601,60845.352.69$4,319
May 201631,81042.521.99$3,731
Apr 201631,82636.561.99$3,745
Mar 20161882,12533.011.79$10,018
Feb 201632,44826.472.06$5,131
Jan 201672,31527.352.36$5,665
Dec 201582,58232.362.00$5,427
Nov 20151872,42938.792.17$12,518
Oct 2015101,80743.552.43$4,820
Sep 201521,61542.992.76$4,541
Aug 201502,06640.162.87$5,935
Jul 20151862,36248.152.95$15,912
Jun 201562,24356.152.88$6,803
May 201518710955.212.96$10,646
Apr 2015101,78949.822.71$5,340
Mar 2015149042.892.93$865
Feb 2015111,65144.662.98$5,405
Jan 2015201,22743.433.10$4,673
Dec 20142208854.693.59$12,348
Nov 201422970.464.25$264
Oct 201401978.303.90$74
Sep 2014157686.164.05$2,416
Aug 2014076089.394.04$3,067
Jul 2014059096.564.18$2,466
Jun 201418447298.164.74$20,297
May 2014028094.734.73$1,323
Apr 2014159495.944.81$2,953
Mar 2014083895.895.06$4,238
Feb 2014066497.406.19$4,111
Jan 2014098790.404.86$4,798
Dec 201318298191.824.35$20,983
Nov 2013094088.853.74$3,514
Oct 2013089597.423.78$3,383
Sep 20130754104.113.72$2,803
Aug 20130572104.253.52$2,015
Jul 20130392102.523.72$1,457
Jun 201318775594.403.93$20,623
May 2013254494.834.15$2,447
Apr 2013066893.964.28$2,861
Mar 2013156593.623.91$2,304
Feb 2013382791.233.42$3,102
Jan 20131821,26691.603.42$21,001
Dec 201201,35186.773.42$4,621
Nov 201211,45786.953.62$5,369
Oct 201201,40889.383.40$4,787
Sep 201201994.672.92$55
Aug 20121861,41092.662.91$21,335
Jul 201271,48085.133.02$5,067
Jun 2012131,52079.822.52$4,867
May 201281,70491.612.49$4,973
Apr 20121902,114101.652.00$23,535
Mar 20121932,195105.052.22$25,152
Feb 2012111,897101.102.57$5,988
Jan 201271,90598.092.73$5,895
Dec 2011151,47096.873.24$6,215
Nov 20111831,45995.723.31$22,348
Oct 201181,60684.983.65$6,539
Sep 20112061,69183.623.99$23,966
Aug 201171,84783.404.15$8,248
Jul 20111911,66794.144.52$25,511
Jun 201121,89892.904.64$8,992
May 20111952,16398.134.40$28,663
Apr 20111982,198105.964.33$30,505
Mar 2011112,16996.364.06$9,860
Feb 201171,36185.644.18$6,288
Jan 20112092,05386.504.59$27,499
Dec 2010182,21885.734.35$11,186
Nov 20101962,30180.843.80$24,578
Oct 201002,55378.103.51$8,958
Sep 2010202,62472.633.98$11,895
Aug 20102013,02873.684.42$28,192
Jul 20102033,02872.554.74$29,070
Jun 2010172,98170.364.91$15,834
May 20101933,53571.124.24$28,698
Apr 20102184,48981.694.12$36,315
Mar 2010283,30578.394.39$16,699
Feb 20102073,85673.585.44$36,217
Jan 20102094,12574.365.96$40,143
Dec 20092144,64071.445.48$40,733
Nov 20091964,87374.593.75$32,901
Oct 20094039,37872.544.11$67,780
Sep 2009153,24065.543.06$10,913
Aug 20091804,41867.423.22$26,355
Jul 20092064,70861.133.46$28,904
Jun 20091994,49966.163.90$30,689
May 20092034,92954.743.93$30,462
Apr 20091755,34746.773.59$27,367
Mar 20092055,68842.144.06$31,726
Feb 20092155,21832.814.63$31,229
Jan 20092176,61535.865.37$43,311
Dec 20082505,53337.105.98$42,347
Nov 20082227,45755.496.86$63,476
Oct 20082388,60475.246.92$77,464
Sep 20084259,614101.767.88$118,978
Aug 200822811,480114.228.48$123,427
Jul 200837712,690131.0811.39$193,949
Jun 200861016,463131.3313.03$294,667
May 200837919,586123.1711.57$273,375
Apr 200892925,290110.3110.45$366,881
Mar 20081,04555,363101.909.66$641,517
Feb 200821214,13292.538.77$143,562

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                6,369 Mcf  × $  3.05 =    $19,399

────────────────────────────────────────────────────
Month total                                  $19,399

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 10/G/236232 is the state's own key, not one this site invented.