CLARK, JEAN

Operated by K & W VANPELT COMPANY (P-5 448748) in the JONES & LEWIS (CADDO) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 43557District 7BField 47159333CondensateGasSaveExport
Value, all time
$119 k
Jan 1993 – May 2022
Value, last 12 filed months
$0
at the published price for each month
Months reported
353
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 2 leases and 2 wells, and the rule below applies to all of them.

Discovered
1968-02-01
as the register files it
Field class
Gas
the register's own label
Between wells
no field rule filed
From a lease line
no field rule filed

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition273 bbl$14,425
GasProduction43,200 Mcf$104,875
Total$119,300

8,696 Mcf of this lease's gas, across 10 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 31.9771, -99.0058. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

31.97713, -99.00575 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
2,067 ft
1 wells filed one
Completion to plug
54.3 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 2,067 ft.

Completions filed
Feb 1968
1 of 1 wells
Plug dates filed
May 2022
1 of 1 wells

Last completion to plug: a median of 54.3 years across the 1 well that filed both dates, with the middle half between 54.3 years and 54.3 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-0490000722,067 ftFeb 1968May 2022Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (353)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

353 months

May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 20190053.112.30$0
Jul 20190056.272.46$0
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20190056.803.06$0
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 20180059.543.11$0
Aug 20180059.403.07$0
Jul 20180065.142.93$0
Jun 20180060.183.08$0
May 20180065.382.90$0
Apr 20180063.842.90$0
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 20170045.373.00$0
Jul 20170043.873.09$0
Jun 20170042.493.09$0
May 20170045.373.26$0
Apr 2017011147.933.21$356
Mar 201704946.772.98$146
Feb 201707450.452.95$218
Jan 2017010049.413.42$342
Dec 2016010048.763.72$372
Nov 2016012042.492.64$317
Oct 2016015546.193.09$479
Sep 2016015641.553.10$484
Aug 2016018541.442.92$541
Jul 2016019141.622.92$559
Jun 2016033345.352.69$894
May 2016039042.521.99$777
Apr 2016032536.561.99$647
Mar 2016042333.011.79$759
Feb 2016034526.472.06$712
Jan 2016028727.352.36$679
Dec 2015024832.362.00$496
Nov 2015029638.792.17$642
Oct 2015030843.552.43$747
Sep 2015046742.992.76$1,288
Aug 2015028140.162.87$807
Jul 2015059948.152.95$1,764
Jun 2015023856.152.88$686
May 2015032455.212.96$958
Apr 2015017249.822.71$466
Mar 2015033542.892.93$983
Feb 2015019744.662.98$586
Jan 2015022943.433.10$710
Dec 2014032054.693.59$1,149
Nov 201417237770.464.25$13,722
Oct 2014011578.303.90$449
Sep 201407986.164.05$320
Aug 2014013089.394.04$525
Jul 201406296.564.18$259
Jun 201406098.164.74$284
May 2014011094.734.73$520
Apr 2014013095.944.81$625
Mar 2014012595.895.06$632
Feb 201408597.406.19$526
Jan 201408490.404.86$408
Dec 201308691.824.35$374
Nov 201308888.853.74$329
Oct 201304697.423.78$174
Sep 20130123104.113.72$457
Aug 20130100104.253.52$352
Jul 2013082102.523.72$305
Jun 2013010394.403.93$405
May 2013011394.834.15$469
Apr 2013010093.964.28$428
Mar 2013028693.623.91$1,119
Feb 2013032791.233.42$1,118
Jan 2013035391.603.42$1,207
Dec 2012032486.773.42$1,108
Nov 2012023286.953.62$841
Oct 2012025889.383.40$877
Sep 201202194.672.92$61
Aug 201202092.662.91$58
Jul 201201885.133.02$54
Jun 201201879.822.52$45
May 201201891.612.49$45
Apr 2012017101.652.00$34
Mar 2012019105.052.22$42
Feb 2012017101.102.57$44
Jan 201201698.092.73$44
Dec 201101796.873.24$55
Nov 201101495.723.31$46
Oct 201101384.983.65$47
Sep 201101283.623.99$48
Aug 201101683.404.15$66
Jul 201101894.144.52$81
Jun 201101892.904.64$84
May 201101898.134.40$79
Apr 2011018105.964.33$78
Mar 201101896.364.06$73
Feb 201101685.644.18$67
Jan 201102286.504.59$101
Dec 201002285.734.35$96
Nov 201002080.843.80$76
Oct 201002278.103.51$77
Sep 201002272.633.98$88
Aug 201002373.684.42$102
Jul 201002372.554.74$109
Jun 201002270.364.91$108
May 201001871.124.24$76
Apr 201002281.694.12$91
Mar 201002278.394.39$97
Feb 201002073.585.44$109
Jan 201001974.365.96$113
Dec 200901071.445.48$55
Nov 200901574.593.75$56
Oct 200902072.544.11$82
Sep 200901965.543.06$58
Aug 200902067.423.22$64
Jul 200902061.133.46$69
Jun 200902266.163.90$86
May 200902454.743.93$94
Apr 200902546.773.59$90
Mar 200901642.144.06$65
Feb 20090832.814.63$37
Jan 200901835.865.37$97
Dec 200801037.105.98$60
Nov 200802255.496.86$151
Oct 200802675.246.92$180
Sep 200806101.767.88$47
Aug 2008022114.228.48$187
Jul 200808131.0811.39$91
Jun 2008018131.3313.03$235
May 2008018123.1711.57$208
Apr 200807110.3110.45$73
Mar 2008010101.909.66$97
Feb 20080692.538.77$53
Jan 20080690.388.21$49
Dec 200701088.337.30$73
Nov 20070891.677.29$58
Oct 200701082.856.92$69
Sep 200701075.846.24$62
Aug 200701269.066.39$77
Jul 20070870.906.39$51
Jun 200701062.007.55$75
May 200701058.747.85$78
Apr 20070859.617.81$62
Mar 200701456.927.30$102
Feb 20070855.108.22$66
Jan 200701050.306.73$67
Dec 200601956.656.92$131
Nov 20060354.207.62$23
Oct 20060654.906.01$36
Sep 200601060.085.04$50
Aug 20060968.717.34$66
Jul 200601469.376.34$89
Jun 200601766.286.38$109
May 200602066.016.42$129
Apr 200602064.397.36$147
Mar 200601856.707.08$127
Feb 20060657.597.75$47
Jan 20060960.598.93$80
Dec 200501054.9413.42$134
Nov 200502054.6910.59$212
Oct 200501058.3413.80$138
Sep 20050661.4512.08$72
Aug 200501061.519.80$98
Jul 20050655.697.84$47
Jun 200501052.337.38$74
May 200501545.226.65$100
Apr 200501649.207.36$118
Mar 200501050.377.15$72
Feb 20050945.226.31$57
Jan 20050943.166.32$57
Dec 20040439.866.75$27
Nov 20040245.286.33$13
Oct 20040349.706.52$20
Sep 20040243.245.28$11
Aug 20040342.375.55$17
Jul 20040338.286.08$18
Jun 20040436.106.43$26
May 20040937.486.49$58
Apr 20040834.475.86$47
Mar 20040334.365.53$17
Feb 20040732.455.51$39
Jan 200401032.036.30$63
Dec 20030830.266.30$50
Nov 20030028.804.60$0
Oct 20030028.174.76$0
Sep 200302026.314.75$95
Aug 200303029.765.13$154
Jul 20030029.415.17$0
Jun 20030028.565.98$0
May 20030026.595.97$0
Apr 200301226.675.41$65
Mar 200301031.146.10$61
Feb 200303433.487.93$269
Jan 200301830.315.58$100
Dec 200202726.914.85$131
Nov 200202024.664.14$83
Oct 200202826.464.23$118
Sep 200203927.443.64$142
Aug 20020025.963.16$0
Jul 20020024.583.06$0
Jun 200207723.733.34$257
May 200201824.663.58$65
Apr 200202723.653.51$95
Mar 2002011822.003.10$366
Feb 20020018.222.38$0
Jan 20020017.172.38$0
Dec 200107116.932.36$168
Nov 200107518.072.41$180
Oct 2001010619.782.53$268
Sep 2001010124.262.25$227
Aug 2001011024.873.05$336
Jul 200106023.933.20$192
Jun 2001011424.563.82$436
May 200104125.524.31$177
Apr 2001010624.685.34$566
Mar 200107224.545.38$387
Feb 200109327.755.77$536
Jan 2001016827.478.40$1,411
Dec 2000022626.889.12$2,062
Nov 2000021532.215.66$1,216
Oct 2000026631.235.15$1,369
Sep 2000025631.875.19$1,328
Aug 2000030529.644.54$1,385
Jul 2000026628.534.09$1,088
Jun 20003628129.304.40$2,290
May 2000031927.263.68$1,174
Apr 2000018824.513.12$586
Mar 2000019628.422.86$561
Feb 2000023527.622.73$641
Jan 2000026525.272.48$657
Dec 1999045624.282.42$1,105
Nov 19990023.192.43$0
Oct 199902020.982.80$56
Sep 1999062221.752.62$1,629
Aug 199901019.262.88$29
Jul 1999021017.892.37$498
Jun 199909215.942.36$217
May 1999012215.792.32$283
Apr 199902315.102.21$51
Mar 19990012.471.84$0
Feb 1999009.981.82$0
Jan 199902010.381.90$38
Dec 199801789.201.77$316
Nov 1998018810.892.19$411
Oct 1998032612.421.97$642
Sep 1998048012.592.08$1,000
Aug 1998047011.301.91$896
Jul 1998090011.742.24$2,014
Jun 1998023111.242.24$517
May 1998046212.622.21$1,019
Apr 1998072213.042.51$1,809
Mar 1998073012.802.31$1,686
Feb 1998049013.952.30$1,127
Jan 1998082114.702.15$1,769
Dec 199701,03816.322.41$2,503
Nov 199701,58918.193.09$4,907
Oct 1997651,34419.253.15$5,485
Sep 19970017.742.95$0
Aug 19970017.862.55$0
Jul 19970017.582.25$0
Jun 199702,64917.242.26$5,979
May 199702,29118.972.31$5,289
Apr 1997025017.882.08$521
Mar 1997025018.951.94$485
Feb 1997011020.492.21$243
Jan 19970023.483.54$0
Dec 19960023.32$0
Nov 19960021.97$0
Oct 19960023.31$0
Sep 19960022.22$0
Aug 19960020.26$0
Jul 19960019.55$0
Jun 19960018.73$0
May 19960019.43$0
Apr 19960021.51$0
Mar 19960019.38$0
Feb 19960016.98$0
Jan 19960017.07$0
Dec 19950017.19$0
Nov 19950016.00$0
Oct 19950015.43$0
Sep 19950016.18$0
Aug 19950015.92$0
Jul 19950015.24$0
Jun 19950016.41$0
May 19950017.56$0
Apr 19950017.73$0
Mar 19950016.44$0
Feb 19950016.58$0
Jan 19950015.92$0
Dec 19940015.03$0
Nov 19940015.90$0
Oct 19940015.58$0
Sep 19940015.29$0
Aug 19940016.13$0
Jul 1994086517.56$0
Jun 19940017.09$0
May 19940015.88$0
Apr 1994073714.14$0
Mar 19940012.46$0
Feb 1994055012.50$0
Jan 19940012.66$0
Dec 19930012.33$0
Nov 19930014.49$0
Oct 19930015.85$0
Sep 19930015.03$0
Aug 199301,09415.66$0
Jul 1993056615.46$0
Jun 1993058916.79$0
May 199301,11217.68$0
Apr 199301,06518.05$0
Mar 199301,10418.14$0
Feb 199301,01417.90$0
Jan 19930016.93$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Apr 2017 — as filed, then multipliedworked
Condensate             0 bbl  × $ 47.93 =         $0
Gas                  111 Mcf  × $  3.21 =       $356

────────────────────────────────────────────────────
Month total                                     $356

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7B/G/43557 is the state's own key, not one this site invented.