TWEEDY "A"

Operated by LEGACY RESERVES OPERATING LP (P-5 495445) in the DOVE CREEK (CISCO) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 107972District 7CField 25930568NGPA filingCondensateGasSaveExport
Value, all time
$62 k
Jan 1993 – May 2011
Value, last 12 filed months
$0
at the published price for each month
Months reported
221
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 41 leases and 44 wells, and the rule below applies to all of them.

Discovered
1965-07-10
as the register files it
Field class
Oil and gas
the register's own label
Between wells
1,320 ft
minimum
From a lease line
660 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 1984-09-01.

The Commission's schedule remark for this field reads: OPTIONAL 40 ACRE UNITS/DIAG 2100'

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition65 bbl$1,117
GasProduction23,106 Mcf$60,997
Total$62,115

14,114 Mcf of this lease's gas, across 33 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 31.2373, -100.7110. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

31.23731, -100.71097 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
6,270 ft
1 wells filed one
Completion to plug
27.7 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 6,270 ft.

Completions filed
Sep 1983
1 of 1 wells
Plug dates filed
May 2011
1 of 1 wells

Last completion to plug: a median of 27.7 years across the 1 well that filed both dates, with the middle half between 27.7 years and 27.7 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-2353205916,270 ftSep 1983May 2011Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (221)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

221 months

May 20110098.134.40$0
Apr 201100105.964.33$0
Mar 20110096.364.06$0
Feb 20110085.644.18$0
Jan 20110086.504.59$0
Dec 20100085.734.35$0
Nov 20100080.843.80$0
Oct 20100078.103.51$0
Sep 20100072.633.98$0
Aug 20100073.684.42$0
Jul 20100072.554.74$0
Jun 20100070.364.91$0
May 20100071.124.24$0
Apr 20100081.694.12$0
Mar 20100078.394.39$0
Feb 20100073.585.44$0
Jan 20100074.365.96$0
Dec 20090071.445.48$0
Nov 20090074.593.75$0
Oct 20090072.544.11$0
Sep 20090065.543.06$0
Aug 20090067.423.22$0
Jul 20090061.133.46$0
Jun 20090066.163.90$0
May 20090054.743.93$0
Apr 20090046.773.59$0
Mar 20090042.144.06$0
Feb 20090032.814.63$0
Jan 20090035.865.37$0
Dec 20080037.105.98$0
Nov 200806955.496.86$473
Oct 2008016475.246.92$1,135
Sep 20080227101.767.88$1,788
Aug 20080175114.228.48$1,485
Jul 20080183131.0811.39$2,084
Jun 20080214131.3313.03$2,789
May 20080236123.1711.57$2,732
Apr 20080183110.3110.45$1,913
Mar 20080130101.909.66$1,256
Feb 2008013092.538.77$1,140
Jan 2008017390.388.21$1,420
Dec 2007016088.337.30$1,168
Nov 2007016491.677.29$1,196
Oct 2007016282.856.92$1,121
Sep 2007015075.846.24$937
Aug 2007017869.066.39$1,137
Jul 2007016670.906.39$1,060
Jun 2007016362.007.55$1,230
May 2007019658.747.85$1,538
Apr 2007017059.617.81$1,327
Mar 2007016756.927.30$1,219
Feb 2007013855.108.22$1,134
Jan 2007010450.306.73$700
Dec 200607556.656.92$519
Nov 200605354.207.62$404
Oct 200605854.906.01$349
Sep 200605960.085.04$297
Aug 200606368.717.34$462
Jul 200605169.376.34$323
Jun 200607366.286.38$466
May 200605766.016.42$366
Apr 200607064.397.36$515
Mar 200606556.707.08$460
Feb 200606957.597.75$535
Jan 200608160.598.93$724
Dec 200507754.9413.42$1,033
Nov 200506754.6910.59$709
Oct 200506758.3413.80$924
Sep 200505561.4512.08$664
Aug 200507161.519.80$696
Jul 200506955.697.84$541
Jun 200506852.337.38$502
May 200508145.226.65$539
Apr 200507149.207.36$523
Mar 200507950.377.15$565
Feb 200506245.226.31$391
Jan 200507643.166.32$480
Dec 200406239.866.75$419
Nov 200405445.286.33$342
Oct 200405749.706.52$371
Sep 200405743.245.28$301
Aug 200404942.375.55$272
Jul 200405438.286.08$329
Jun 200405536.106.43$354
May 2004011137.486.49$721
Apr 2004019334.475.86$1,131
Mar 200403934.365.53$216
Feb 200403932.455.51$215
Jan 200405032.036.30$315
Dec 200303430.266.30$214
Nov 200306328.804.60$290
Oct 200304728.174.76$224
Sep 200303926.314.75$185
Aug 200303529.765.13$180
Jul 200304229.415.17$217
Jun 200304228.565.98$251
May 200304026.595.97$239
Apr 200305326.675.41$287
Mar 200304131.146.10$250
Feb 200304633.487.93$365
Jan 200305530.315.58$307
Dec 200205826.914.85$282
Nov 200205324.664.14$219
Oct 200206726.464.23$283
Sep 200205127.443.64$185
Aug 200208725.963.16$275
Jul 200207824.583.06$239
Jun 200203323.733.34$110
May 200206024.663.58$215
Apr 200208123.653.51$285
Mar 200207322.003.10$227
Feb 200207218.222.38$171
Jan 200205817.172.38$138
Dec 200126916.932.36$197
Nov 200106818.072.41$164
Oct 200117019.782.53$197
Sep 200106524.262.25$146
Aug 200108424.873.05$256
Jul 200105223.933.20$166
Jun 200103324.563.82$126
May 200104825.524.31$207
Apr 200105324.685.34$283
Mar 200105224.545.38$280
Feb 200104727.755.77$271
Jan 200104427.478.40$370
Dec 200001126.889.12$100
Nov 200012632.215.66$179
Oct 200006631.235.15$340
Sep 200005831.875.19$301
Aug 200005729.644.54$259
Jul 200005128.534.09$209
Jun 200005329.304.40$233
May 200005127.263.68$188
Apr 200005824.513.12$181
Mar 200007128.422.86$203
Feb 200005027.622.73$136
Jan 200005125.272.48$127
Dec 199914224.282.42$126
Nov 199905123.192.43$124
Oct 19990020.982.80$0
Sep 19990021.752.62$0
Aug 19990019.262.88$0
Jul 19990017.892.37$0
Jun 199902515.942.36$59
May 199901915.792.32$44
Apr 199902015.102.21$44
Mar 19990012.471.84$0
Feb 1999009.981.82$0
Jan 19990010.381.90$0
Dec 1998009.201.77$0
Nov 19980010.892.19$0
Oct 19980012.421.97$0
Sep 19980012.592.08$0
Aug 19980011.301.91$0
Jul 19980011.742.24$0
Jun 19980011.242.24$0
May 19980012.622.21$0
Apr 19980013.042.51$0
Mar 19980012.802.31$0
Feb 19980013.952.30$0
Jan 19980014.702.15$0
Dec 19970016.322.41$0
Nov 19970018.193.09$0
Oct 19970019.253.15$0
Sep 19970017.742.95$0
Aug 19970017.862.55$0
Jul 19970017.582.25$0
Jun 19970017.242.26$0
May 19970018.972.31$0
Apr 19970017.882.08$0
Mar 19970018.951.94$0
Feb 19970020.492.21$0
Jan 19970023.483.54$0
Dec 19960023.32$0
Nov 19960021.97$0
Oct 19960023.31$0
Sep 19960022.22$0
Aug 19960020.26$0
Jul 19960019.55$0
Jun 19960018.73$0
May 19960019.43$0
Apr 19960021.51$0
Mar 19960019.38$0
Feb 19960016.98$0
Jan 19960017.07$0
Dec 19950017.19$0
Nov 19950016.00$0
Oct 199502115.43$0
Sep 199505616.18$0
Aug 199501015.92$0
Jul 199501215.24$0
Jun 199502716.41$0
May 199509717.56$0
Apr 199506217.73$0
Mar 199506516.44$0
Feb 199507916.58$0
Jan 199506115.92$0
Dec 19940015.03$0
Nov 199401615.90$0
Oct 199402815.58$0
Sep 1994014215.29$0
Aug 199441,71316.13$65
Jul 1994022317.56$0
Jun 19941720917.09$291
May 1994023215.88$0
Apr 1994022614.14$0
Mar 1994118212.46$12
Feb 1994018912.50$0
Jan 1994627712.66$76
Dec 1993028912.33$0
Nov 1993016914.49$0
Oct 1993018015.85$0
Sep 1993034415.03$0
Aug 199302,72415.66$0
Jul 1993081415.46$0
Jun 1993111,09016.79$185
May 199301,39117.68$0
Apr 1993211,58218.05$379
Mar 1993067318.14$0
Feb 1993051817.90$0
Jan 1993041316.93$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Nov 2008 — as filed, then multipliedworked
Condensate             0 bbl  × $ 55.49 =         $0
Gas                   69 Mcf  × $  6.86 =       $473

────────────────────────────────────────────────────
Month total                                     $473

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/107972 is the state's own key, not one this site invented.