HATTON, E.H. ESTATE '14C'

Operated by SCOUT ENERGY MANAGEMENT LLC (P-5 760218) in the OZONA (CANYON SAND) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 134431District 7CField 679952002 tax incentive programmesCondensateGasSaveExport
Value, all time
$468 k
Jan 1993 – May 2026
Value, last 12 filed months
$8 k
at the published price for each month
Months reported
401
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 2,312 leases and 2,323 wells, and the rule below applies to all of them.

Discovered
1962-02-23
as the register files it
Field class
Oil and gas
the register's own label
Between wells
600 ft
minimum
From a lease line
660 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2006-09-12.

The Commission's schedule remark for this field reads: ZONE TO BE SET UP IN OZONA (CANYON SAND, OIL).

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas111991-01-24123000
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition22 bbl$1,392
GasProduction166,374 Mcf$466,220
Total$467,612

64,650 Mcf of this lease's gas, across 48 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.4197, -101.5691. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.41970, -101.56910 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
7,455 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,455 ft.

Completions filed
May 1990
1 of 1 wells

1 well

42-1053574167,455 ftMay 1990

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (401)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

401 months

May 20260205106.413.05$624
Apr 2026115498.932.87$541
Mar 20260089.753.15$0
Feb 2026117363.503.75$712
Jan 2026316359.138.00$1,481
Dec 2025316856.664.41$911
Nov 2025217058.593.93$785
Oct 2025217059.383.30$681
Sep 2025121462.743.08$721
Aug 2025217863.933.01$664
Jul 2025118066.743.32$663
Jun 2025117166.483.13$601
May 2025217160.553.23$674
Apr 2025110262.363.54$424
Mar 202519867.704.27$486
Feb 202518770.884.34$449
Jan 20250074.324.28$0
Dec 2024045068.993.12$1,405
Nov 2024011469.052.20$251
Oct 2024020571.372.28$468
Sep 2024016369.612.36$385
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210379.795.71$17
Sep 20210369.865.35$16
Aug 20210266.024.22$8
Jul 20210770.783.98$28
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 201901653.472.42$39
Sep 201904055.052.66$106
Aug 201904653.112.30$106
Jul 201904656.272.46$113
Jun 20190052.782.49$0
May 20190058.482.74$0
Apr 20190062.632.75$0
Mar 20190056.803.06$0
Feb 20190050.852.79$0
Jan 20190046.033.23$0
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180061.443.40$0
Sep 201803159.543.11$96
Aug 201802559.403.07$77
Jul 201803265.142.93$94
Jun 201803160.183.08$95
May 201803265.382.90$93
Apr 201803263.842.90$93
Mar 201803361.222.79$92
Feb 201803161.782.77$86
Jan 201802962.874.01$116
Dec 201703457.272.92$99
Nov 201703455.423.12$106
Oct 201703749.292.98$110
Sep 201703247.523.09$99
Aug 201703545.373.00$105
Jul 201703843.873.09$117
Jun 201703642.493.09$111
May 201703845.373.26$124
Apr 201703747.933.21$119
Mar 201703546.772.98$104
Feb 201703550.452.95$103
Jan 201703749.413.42$127
Dec 201603748.763.72$138
Nov 201601842.492.64$48
Oct 201602046.193.09$62
Sep 201602441.553.10$74
Aug 201604441.442.92$129
Jul 20160341.622.92$9
Jun 201601445.352.69$38
May 201603342.521.99$66
Apr 201603736.561.99$74
Mar 201602733.011.79$48
Feb 201602626.472.06$54
Jan 201602827.352.36$66
Dec 201502832.362.00$56
Nov 201502838.792.17$61
Oct 201502843.552.43$68
Sep 201502042.992.76$55
Aug 201502740.162.87$78
Jul 201503248.152.95$94
Jun 201503256.152.88$92
May 201503455.212.96$100
Apr 201503449.822.71$92
Mar 201503442.892.93$100
Feb 201502844.662.98$83
Jan 201503343.433.10$102
Dec 201403354.693.59$119
Nov 201403070.464.25$128
Oct 201403178.303.90$121
Sep 201402986.164.05$117
Aug 201403089.394.04$121
Jul 201402996.564.18$121
Jun 201402698.164.74$123
May 201402494.734.73$113
Apr 201401595.944.81$72
Mar 201403395.895.06$167
Feb 201403197.406.19$192
Jan 201403590.404.86$170
Dec 201303591.824.35$152
Nov 201303388.853.74$123
Oct 201303497.423.78$129
Sep 2013031104.113.72$115
Aug 2013028104.253.52$99
Jul 2013027102.523.72$100
Jun 201303394.403.93$130
May 20130994.834.15$37
Apr 201303493.964.28$146
Mar 201301593.623.91$59
Feb 20130091.233.42$0
Jan 20130491.603.42$14
Dec 20120086.773.42$0
Nov 201201886.953.62$65
Oct 201202289.383.40$75
Sep 20120494.672.92$12
Aug 20120092.662.91$0
Jul 201203585.133.02$106
Jun 201202579.822.52$63
May 201202391.612.49$57
Apr 2012020101.652.00$40
Mar 2012016105.052.22$36
Feb 2012014101.102.57$36
Jan 20120098.092.73$0
Dec 20110496.873.24$13
Nov 2011020395.723.31$672
Oct 2011030684.983.65$1,116
Sep 2011028183.623.99$1,120
Aug 2011027483.404.15$1,137
Jul 2011028094.144.52$1,265
Jun 2011026792.904.64$1,239
May 2011029098.134.40$1,277
Apr 20110268105.964.33$1,161
Mar 2011029796.364.06$1,205
Feb 2011027085.644.18$1,129
Jan 2011031886.504.59$1,459
Dec 2010031185.734.35$1,352
Nov 2010028780.843.80$1,089
Oct 2010030878.103.51$1,081
Sep 2010030472.633.98$1,210
Aug 2010029873.684.42$1,317
Jul 2010028872.554.74$1,364
Jun 2010030470.364.91$1,493
May 2010032871.124.24$1,389
Apr 2010024481.694.12$1,006
Mar 2010032378.394.39$1,418
Feb 2010030473.585.44$1,654
Jan 2010034374.365.96$2,046
Dec 2009032371.445.48$1,771
Nov 2009031374.593.75$1,174
Oct 2009032872.544.11$1,348
Sep 2009031965.543.06$978
Aug 2009034767.423.22$1,117
Jul 2009030161.133.46$1,043
Jun 2009030466.163.90$1,184
May 2009030554.743.93$1,197
Apr 2009031946.773.59$1,144
Mar 2009033842.144.06$1,372
Feb 2009031932.814.63$1,478
Jan 2009033635.865.37$1,805
Dec 2008033937.105.98$2,026
Nov 2008030255.496.86$2,072
Oct 2008035875.246.92$2,478
Sep 20080314101.767.88$2,473
Aug 20080410114.228.48$3,478
Jul 20080426131.0811.39$4,852
Jun 20080499131.3313.03$6,503
May 20080469123.1711.57$5,428
Apr 20080392110.3110.45$4,098
Mar 20080469101.909.66$4,532
Feb 2008055292.538.77$4,841
Jan 2008050290.388.21$4,119
Dec 2007046588.337.30$3,395
Nov 2007046991.677.29$3,420
Oct 2007053982.856.92$3,731
Sep 2007054575.846.24$3,403
Aug 2007064869.066.39$4,139
Jul 2007062670.906.39$3,999
Jun 2007024562.007.55$1,849
May 2007024958.747.85$1,954
Apr 2007020259.617.81$1,577
Mar 2007052856.927.30$3,855
Feb 2007043855.108.22$3,599
Jan 2007040550.306.73$2,724
Dec 2006055356.656.92$3,826
Nov 2006049554.207.62$3,771
Oct 2006039254.906.01$2,357
Sep 2006038260.085.04$1,924
Aug 2006055868.717.34$4,096
Jul 2006058169.376.34$3,685
Jun 2006054266.286.38$3,460
May 2006053166.016.42$3,412
Apr 2006048264.397.36$3,548
Mar 2006050456.707.08$3,570
Feb 2006037257.597.75$2,883
Jan 2006042460.598.93$3,788
Dec 2005041154.9413.42$5,514
Nov 2005037554.6910.59$3,971
Oct 2005038958.3413.80$5,367
Sep 2005040161.4512.08$4,844
Aug 2005043861.519.80$4,291
Jul 2005047255.697.84$3,702
Jun 2005051452.337.38$3,794
May 2005043345.226.65$2,880
Apr 2005041249.207.36$3,033
Mar 2005041550.377.15$2,969
Feb 2005041845.226.31$2,638
Jan 2005043143.166.32$2,725
Dec 2004042739.866.75$2,883
Nov 2004047845.286.33$3,026
Oct 2004055249.706.52$3,596
Sep 2004048443.245.28$2,557
Aug 2004053942.375.55$2,992
Jul 2004044538.286.08$2,707
Jun 2004056736.106.43$3,648
May 2004057437.486.49$3,728
Apr 2004052234.475.86$3,058
Mar 2004058434.365.53$3,230
Feb 2004050632.455.51$2,788
Jan 2004057332.036.30$3,610
Dec 2003053730.266.30$3,384
Nov 2003057828.804.60$2,656
Oct 2003059128.174.76$2,813
Sep 2003069726.314.75$3,310
Aug 2003067029.765.13$3,437
Jul 2003062729.415.17$3,242
Jun 2003051028.565.98$3,051
May 2003047726.595.97$2,849
Apr 2003054526.675.41$2,947
Mar 2003057131.146.10$3,481
Feb 2003050333.487.93$3,987
Jan 2003048330.315.58$2,696
Dec 2002049626.914.85$2,407
Nov 2002060224.664.14$2,490
Oct 2002057726.464.23$2,440
Sep 2002056727.443.64$2,061
Aug 2002057725.963.16$1,826
Jul 2002052524.583.06$1,607
Jun 2002047323.733.34$1,579
May 2002048624.663.58$1,742
Apr 2002058323.653.51$2,048
Mar 2002052622.003.10$1,632
Feb 2002045618.222.38$1,083
Jan 2002053017.172.38$1,259
Dec 2001046216.932.36$1,092
Nov 2001054818.072.41$1,318
Oct 2001052019.782.53$1,315
Sep 2001050524.262.25$1,137
Aug 2001057424.873.05$1,753
Jul 2001071323.933.20$2,280
Jun 2001067424.563.82$2,577
May 2001055025.524.31$2,369
Apr 2001063924.685.34$3,409
Mar 2001070424.545.38$3,785
Feb 2001067127.755.77$3,870
Jan 2001093227.478.40$7,828
Dec 2000048526.889.12$4,424
Nov 2000054732.215.66$3,095
Oct 2000044631.235.15$2,295
Sep 2000052331.875.19$2,713
Aug 2000052029.644.54$2,361
Jul 2000069728.534.09$2,851
Jun 2000041929.304.40$1,842
May 2000062527.263.68$2,300
Apr 2000044124.513.12$1,374
Mar 2000056028.422.86$1,601
Feb 2000047527.622.73$1,295
Jan 2000067325.272.48$1,669
Dec 1999064924.282.42$1,573
Nov 1999063723.192.43$1,550
Oct 1999058820.982.80$1,649
Sep 1999062221.752.62$1,629
Aug 1999085619.262.88$2,462
Jul 1999087317.892.37$2,071
Jun 1999083115.942.36$1,963
May 1999095715.792.32$2,221
Apr 1999058515.102.21$1,292
Mar 1999067612.471.84$1,243
Feb 199906239.981.82$1,132
Jan 1999071110.381.90$1,351
Dec 199807879.201.77$1,396
Nov 1998083510.892.19$1,825
Oct 199801,01012.421.97$1,989
Sep 1998066212.592.08$1,379
Aug 1998091811.301.91$1,751
Jul 1998095411.742.24$2,134
Jun 1998094311.242.24$2,110
May 1998083612.622.21$1,845
Apr 1998085613.042.51$2,145
Mar 1998095412.802.31$2,203
Feb 1998095913.952.30$2,205
Jan 1998093014.702.15$2,004
Dec 199701,01716.322.41$2,452
Nov 199701,04418.193.09$3,224
Oct 1997090519.253.15$2,851
Sep 1997095317.742.95$2,816
Aug 1997099717.862.55$2,547
Jul 199701,03217.582.25$2,319
Jun 199701,02117.242.26$2,305
May 199701,01018.972.31$2,332
Apr 1997079417.882.08$1,654
Mar 1997071618.951.94$1,388
Feb 1997083020.492.21$1,831
Jan 199701,26623.483.54$4,481
Dec 199601,21223.32$0
Nov 199601,14921.97$0
Oct 199601,14823.31$0
Sep 199601,25222.22$0
Aug 199601,16520.26$0
Jul 199601,11619.55$0
Jun 199601,19418.73$0
May 1996095119.43$0
Apr 199601,07721.51$0
Mar 199601,26119.38$0
Feb 199601,02916.98$0
Jan 199601,34417.07$0
Dec 199501,06217.19$0
Nov 1995097616.00$0
Oct 199501,10915.43$0
Sep 199501,09216.18$0
Aug 199501,07815.92$0
Jul 199501,32015.24$0
Jun 199501,15516.41$0
May 199501,23717.56$0
Apr 199501,10717.73$0
Mar 199501,26616.44$0
Feb 199501,06716.58$0
Jan 199501,31715.92$0
Dec 199401,49015.03$0
Nov 199401,40515.90$0
Oct 199401,37215.58$0
Sep 199401,31215.29$0
Aug 199401,29416.13$0
Jul 199401,43017.56$0
Jun 199401,52217.09$0
May 199401,47915.88$0
Apr 199401,58514.14$0
Mar 199401,39812.46$0
Feb 199401,27812.50$0
Jan 199401,30312.66$0
Dec 199301,49112.33$0
Nov 199301,66414.49$0
Oct 199301,48415.85$0
Sep 199301,31915.03$0
Aug 199301,87015.66$0
Jul 199301,76215.46$0
Jun 199301,60116.79$0
May 199301,87817.68$0
Apr 199301,76518.05$0
Mar 199301,91618.14$0
Feb 199301,55617.90$0
Jan 199301,79216.93$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                  205 Mcf  × $  3.05 =       $624

────────────────────────────────────────────────────
Month total                                     $624

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/134431 is the state's own key, not one this site invented.