MILLSPAUGH, AUSTIN "32C"

Operated by SCOUT ENERGY MANAGEMENT LLC (P-5 760218) in the OZONA (CANYON SAND) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 155958District 7CField 679952002 tax incentive programmesCondensateGasSaveExport
Value, all time
$968 k
Aug 1995 – May 2026
Value, last 12 filed months
$12 k
at the published price for each month
Months reported
370
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 2,312 leases and 2,323 wells, and the rule below applies to all of them.

Discovered
1962-02-23
as the register files it
Field class
Oil and gas
the register's own label
Between wells
600 ft
minimum
From a lease line
660 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2006-09-12.

The Commission's schedule remark for this field reads: ZONE TO BE SET UP IN OZONA (CANYON SAND, OIL).

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas111995-12-14133549
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition31 bbl$1,984
GasProduction315,464 Mcf$965,883
Total$967,866

78,587 Mcf of this lease's gas, across 17 months, carries no value here. No free Texas wellhead gas price exists before 1997, so those months are left out of the total rather than valued at zero. The total above is therefore a floor, not an estimate.

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.4920, -101.5511. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.49200, -101.55114 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
7,500 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,500 ft.

Completions filed
Aug 1995
1 of 1 wells

1 well

42-1053689527,500 ftAug 1995

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (370)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

370 months

May 20260319106.413.05$972
Apr 2026136298.932.87$1,138
Mar 20260089.753.15$0
Feb 2026220563.503.75$896
Jan 2026224859.138.00$2,102
Dec 2025324756.664.41$1,260
Nov 2025327258.593.93$1,244
Oct 2025229459.383.30$1,090
Sep 2025122662.743.08$758
Aug 2025219963.933.01$728
Jul 2025222966.743.32$893
Jun 2025124466.483.13$830
May 2025324460.553.23$970
Apr 2025323062.363.54$1,002
Mar 2025324867.704.27$1,262
Feb 2025322170.884.34$1,172
Jan 20250074.324.28$0
Dec 2024024468.993.12$762
Nov 2024023969.052.20$525
Oct 2024029071.372.28$662
Sep 2024024569.612.36$579
Aug 2024025575.632.06$526
Jul 2024025079.932.15$537
Jun 2024026578.082.63$698
May 2024025678.812.20$563
Apr 2024026984.451.66$446
Mar 2024027180.301.55$419
Feb 2024025476.091.78$453
Jan 2024028573.023.30$940
Dec 2023026971.262.61$702
Nov 2023030677.892.81$859
Oct 2023029485.443.09$908
Sep 2023030889.042.74$842
Aug 2023031980.522.67$853
Jul 2023031874.852.64$840
Jun 2023030968.962.26$698
May 2023031170.622.23$693
Apr 2023033078.122.24$738
Mar 2023029772.852.39$711
Feb 2023025875.112.47$636
Jan 2023030976.533.39$1,047
Dec 2022031176.415.73$1,782
Nov 2022031785.005.65$1,790
Oct 2022030387.185.86$1,777
Sep 2022031384.888.16$2,555
Aug 2022032894.529.13$2,994
Jul 20220308101.587.54$2,323
Jun 20220310115.097.98$2,473
May 20220338109.378.43$2,850
Apr 20220341104.226.84$2,332
Mar 20220340108.885.08$1,726
Feb 2022031391.054.86$1,521
Jan 2022035181.844.54$1,593
Dec 2021034471.323.90$1,341
Nov 2021036777.435.24$1,922
Oct 2021036679.795.71$2,091
Sep 2021038269.865.35$2,044
Aug 2021033066.024.22$1,393
Jul 2021031470.783.98$1,250
Jun 2021036069.493.38$1,217
May 2021029163.483.02$878
Apr 2021035860.362.76$988
Mar 2021038261.302.72$1,038
Feb 2021033557.805.55$1,859
Jan 2021035150.412.81$986
Dec 2020027044.642.68$722
Nov 2020029238.772.71$790
Oct 2020031036.972.48$768
Sep 2020026337.091.99$524
Aug 2020029139.982.39$694
Jul 2020029538.371.83$538
Jun 2020029534.901.69$499
May 2020031116.921.81$564
Apr 2020034414.751.80$621
Mar 2020036530.341.86$678
Feb 2020032349.881.98$640
Jan 2020040057.252.09$838
Dec 2019041259.012.30$949
Nov 2019039055.302.75$1,073
Oct 2019040853.472.42$987
Sep 2019042255.052.66$1,121
Aug 2019044653.112.30$1,028
Jul 2019042956.272.46$1,055
Jun 2019041452.782.49$1,031
May 2019043258.482.74$1,184
Apr 2019041462.632.75$1,139
Mar 2019043456.803.06$1,329
Feb 2019038950.852.79$1,086
Jan 2019031646.033.23$1,020
Dec 2018032746.594.19$1,369
Nov 2018030252.934.24$1,280
Oct 2018034461.443.40$1,169
Sep 2018036559.543.11$1,134
Aug 2018028359.403.07$868
Jul 2018033765.142.93$988
Jun 2018032860.183.08$1,009
May 2018033665.382.90$975
Apr 2018034863.842.90$1,009
Mar 2018036661.222.79$1,020
Feb 2018032661.782.77$902
Jan 2018036462.874.01$1,459
Dec 2017038057.272.92$1,110
Nov 2017032555.423.12$1,013
Oct 2017032749.292.98$976
Sep 2017030247.523.09$932
Aug 2017032045.373.00$961
Jul 2017031543.873.09$972
Jun 2017029842.493.09$920
May 2017032445.373.26$1,057
Apr 2017030447.933.21$976
Mar 2017032046.772.98$955
Feb 2017030150.452.95$889
Jan 2017033449.413.42$1,142
Dec 2016047248.763.72$1,757
Nov 2016046142.492.64$1,219
Oct 2016042246.193.09$1,304
Sep 2016038741.553.10$1,200
Aug 2016047641.442.92$1,392
Jul 2016045641.622.92$1,334
Jun 2016046345.352.69$1,244
May 2016029842.521.99$593
Apr 2016036036.561.99$717
Mar 2016036033.011.79$646
Feb 2016027826.472.06$574
Jan 2016033127.352.36$783
Dec 2015032432.362.00$648
Nov 2015037438.792.17$811
Oct 2015045743.552.43$1,109
Sep 2015037542.992.76$1,034
Aug 2015044840.162.87$1,287
Jul 2015045148.152.95$1,328
Jun 2015043356.152.88$1,248
May 2015045055.212.96$1,330
Apr 2015044649.822.71$1,207
Mar 2015046742.892.93$1,371
Feb 2015039844.662.98$1,185
Jan 2015044343.433.10$1,374
Dec 2014046954.693.59$1,684
Nov 2014045370.464.25$1,926
Oct 2014046678.303.90$1,818
Sep 2014047986.164.05$1,938
Aug 2014044189.394.04$1,779
Jul 2014043796.564.18$1,826
Jun 2014045698.164.74$2,160
May 2014048194.734.73$2,273
Apr 2014049195.944.81$2,361
Mar 2014046795.895.06$2,362
Feb 2014045297.406.19$2,799
Jan 2014049990.404.86$2,426
Dec 2013054091.824.35$2,351
Nov 2013048288.853.74$1,802
Oct 2013050797.423.78$1,916
Sep 20130549104.113.72$2,041
Aug 20130623104.253.52$2,195
Jul 20130373102.523.72$1,387
Jun 2013043794.403.93$1,719
May 2013040094.834.15$1,660
Apr 2013050393.964.28$2,154
Mar 2013044893.623.91$1,753
Feb 2013033691.233.42$1,149
Jan 2013054891.603.42$1,874
Dec 2012035486.773.42$1,211
Nov 2012038086.953.62$1,377
Oct 2012049789.383.40$1,690
Sep 2012036994.672.92$1,077
Aug 2012040892.662.91$1,187
Jul 2012047785.133.02$1,441
Jun 2012049379.822.52$1,242
May 2012049091.612.49$1,219
Apr 20120458101.652.00$915
Mar 20120479105.052.22$1,064
Feb 20120460101.102.57$1,182
Jan 2012051898.092.73$1,416
Dec 2011053796.873.24$1,740
Nov 2011046395.723.31$1,533
Oct 2011048584.983.65$1,770
Sep 2011046283.623.99$1,841
Aug 2011048383.404.15$2,004
Jul 2011049294.144.52$2,222
Jun 2011049492.904.64$2,292
May 2011052098.134.40$2,291
Apr 20110545105.964.33$2,362
Mar 2011056996.364.06$2,309
Feb 2011047285.644.18$1,973
Jan 2011059286.504.59$2,717
Dec 2010054985.734.35$2,387
Nov 2010056780.843.80$2,152
Oct 2010059778.103.51$2,095
Sep 2010053872.633.98$2,141
Aug 2010055673.684.42$2,457
Jul 2010057172.554.74$2,705
Jun 2010057570.364.91$2,823
May 2010056271.124.24$2,380
Apr 2010053381.694.12$2,197
Mar 2010062978.394.39$2,760
Feb 2010052873.585.44$2,874
Jan 2010050874.365.96$3,030
Dec 2009056871.445.48$3,115
Nov 2009053974.593.75$2,022
Oct 2009052572.544.11$2,158
Sep 2009051665.543.06$1,581
Aug 2009056667.423.22$1,822
Jul 2009053361.133.46$1,847
Jun 2009047066.163.90$1,831
May 2009057754.743.93$2,265
Apr 2009055246.773.59$1,980
Mar 2009053542.144.06$2,172
Feb 2009045932.814.63$2,127
Jan 2009060535.865.37$3,249
Dec 2008062137.105.98$3,712
Nov 2008059655.496.86$4,089
Oct 2008062975.246.92$4,354
Sep 20080558101.767.88$4,395
Aug 20080529114.228.48$4,488
Jul 20080562131.0811.39$6,401
Jun 20080632131.3313.03$8,237
May 20080663123.1711.57$7,674
Apr 20080702110.3110.45$7,339
Mar 20080710101.909.66$6,861
Feb 2008059292.538.77$5,192
Jan 2008058690.388.21$4,809
Dec 2007064588.337.30$4,710
Nov 2007051691.677.29$3,763
Oct 2007056982.856.92$3,939
Sep 2007052875.846.24$3,297
Aug 2007051669.066.39$3,296
Jul 2007058170.906.39$3,711
Jun 2007055462.007.55$4,182
May 2007053958.747.85$4,229
Apr 2007049159.617.81$3,832
Mar 2007055856.927.30$4,075
Feb 2007056055.108.22$4,601
Jan 2007060050.306.73$4,036
Dec 2006063256.656.92$4,372
Nov 2006063454.207.62$4,829
Oct 2006065254.906.01$3,921
Sep 2006065260.085.04$3,284
Aug 2006067968.717.34$4,984
Jul 2006072069.376.34$4,567
Jun 2006071566.286.38$4,564
May 2006066866.016.42$4,292
Apr 2006059564.397.36$4,379
Mar 2006066556.707.08$4,710
Feb 2006064057.597.75$4,961
Jan 2006076760.598.93$6,852
Dec 2005077354.9413.42$10,370
Nov 2005060854.6910.59$6,438
Oct 2005079358.3413.80$10,940
Sep 2005065361.4512.08$7,888
Aug 2005074161.519.80$7,259
Jul 2005070655.697.84$5,538
Jun 2005091352.337.38$6,739
May 2005076945.226.65$5,115
Apr 2005072849.207.36$5,358
Mar 2005061750.377.15$4,415
Feb 2005069045.226.31$4,355
Jan 2005075043.166.32$4,742
Dec 2004074639.866.75$5,036
Nov 2004075945.286.33$4,805
Oct 2004072049.706.52$4,691
Sep 2004056243.245.28$2,970
Aug 2004082842.375.55$4,596
Jul 2004085438.286.08$5,196
Jun 2004094136.106.43$6,053
May 2004090237.486.49$5,858
Apr 2004091234.475.86$5,343
Mar 2004087234.365.53$4,822
Feb 2004082532.455.51$4,545
Jan 2004084932.036.30$5,348
Dec 2003082930.266.30$5,224
Nov 2003083328.804.60$3,828
Oct 2003082928.174.76$3,946
Sep 2003089226.314.75$4,236
Aug 2003095129.765.13$4,878
Jul 2003092529.415.17$4,783
Jun 2003083028.565.98$4,966
May 2003090826.595.97$5,423
Apr 2003086226.675.41$4,661
Mar 2003088731.146.10$5,407
Feb 2003080833.487.93$6,404
Jan 200301,13530.315.58$6,336
Dec 2002036626.914.85$1,776
Nov 2002091824.664.14$3,798
Oct 2002093826.464.23$3,967
Sep 2002089827.443.64$3,264
Aug 2002092825.963.16$2,936
Jul 200201,03424.583.06$3,166
Jun 2002094723.733.34$3,161
May 2002095024.663.58$3,405
Apr 2002092123.653.51$3,235
Mar 2002097922.003.10$3,038
Feb 2002085018.222.38$2,019
Jan 200201,02617.172.38$2,437
Dec 2001097416.932.36$2,303
Nov 2001095718.072.41$2,302
Oct 200101,12919.782.53$2,855
Sep 2001096024.262.25$2,161
Aug 2001099224.873.05$3,029
Jul 2001097123.933.20$3,104
Jun 2001099924.563.82$3,820
May 2001096725.524.31$4,165
Apr 200101,08924.685.34$5,810
Mar 2001094624.545.38$5,086
Feb 200101,08227.755.77$6,240
Jan 2001084727.478.40$7,114
Dec 200001,09826.889.12$10,017
Nov 200001,01032.215.66$5,715
Oct 200001,10131.235.15$5,665
Sep 200001,11131.875.19$5,762
Aug 200001,17729.644.54$5,344
Jul 200001,25828.534.09$5,145
Jun 200001,19429.304.40$5,250
May 200001,22727.263.68$4,515
Apr 200001,20024.513.12$3,739
Mar 200001,22228.422.86$3,495
Feb 200001,30827.622.73$3,566
Jan 200001,19725.272.48$2,969
Dec 199901,24324.282.42$3,013
Nov 199901,43923.192.43$3,503
Oct 199901,52620.982.80$4,278
Sep 199901,57221.752.62$4,117
Aug 199901,66919.262.88$4,799
Jul 199901,56317.892.37$3,708
Jun 199901,41915.942.36$3,352
May 199901,49215.792.32$3,463
Apr 199901,29915.102.21$2,868
Mar 199901,61112.471.84$2,962
Feb 199901,5219.981.82$2,765
Jan 199901,46910.381.90$2,791
Dec 199801,6049.201.77$2,844
Nov 199801,71210.892.19$3,742
Oct 199801,78912.421.97$3,523
Sep 199801,79412.592.08$3,736
Aug 199801,84311.301.91$3,515
Jul 199801,92711.742.24$4,311
Jun 199802,22911.242.24$4,987
May 199801,72612.622.21$3,808
Apr 199801,52513.042.51$3,821
Mar 199801,91112.802.31$4,413
Feb 199801,70313.952.30$3,915
Jan 199801,81214.702.15$3,904
Dec 199701,81716.322.41$4,381
Nov 199701,97518.193.09$6,099
Oct 199702,15919.253.15$6,800
Sep 199702,32417.742.95$6,867
Aug 199702,31617.862.55$5,917
Jul 199702,39717.582.25$5,386
Jun 199702,45817.242.26$5,548
May 199702,56518.972.31$5,921
Apr 199702,43717.882.08$5,076
Mar 199702,57318.951.94$4,989
Feb 199702,54520.492.21$5,614
Jan 199702,93123.483.54$10,375
Dec 199602,97623.32$0
Nov 199603,02421.97$0
Oct 199603,32323.31$0
Sep 199603,23922.22$0
Aug 199603,58120.26$0
Jul 199603,71919.55$0
Jun 199603,84818.73$0
May 199604,02719.43$0
Apr 199604,52221.51$0
Mar 199604,79819.38$0
Feb 199604,70216.98$0
Jan 199605,44017.07$0
Dec 199505,64017.19$0
Nov 199506,08716.00$0
Oct 199508,52815.43$0
Sep 1995010,33916.18$0
Aug 1995079415.92$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                  319 Mcf  × $  3.05 =       $972

────────────────────────────────────────────────────
Month total                                     $972

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/155958 is the state's own key, not one this site invented.