MECKEL

Operated by UPP OPERATING, LLC (P-5 875310) in the SONORA (CANYON UPPER) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 183128District 7CField 846465002 tax incentive programmesCondensateGasSaveExport
Value, all time
$705 k
Mar 2001 – May 2026
Value, last 12 filed months
$109
at the published price for each month
Months reported
303
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 959 leases and 959 wells, and the rule below applies to all of them.

Discovered
1954-05-01
as the register files it
Field class
Gas
the register's own label
Between wells
933 ft
minimum
From a lease line
467 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 1993-09-13.

The Commission's schedule remark for this field reads: EFFECTIVE JAN 1; ANNUAL TESTING. ALL WELLS EXEMPT FROM SIWHP.

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112001-08-22144689
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition4 bbl$93
GasProduction145,206 Mcf$704,413
Total$704,506

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.6386, -100.6643. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.63860, -100.66429 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
6,129 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 6,129 ft.

Completions filed
Mar 2001
1 of 1 wells

1 well

42-43535310516,129 ftMar 2001

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (303)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

303 months

May 202602106.413.05$6
Apr 20260298.932.87$6
Mar 20260089.753.15$0
Feb 20260163.503.75$4
Jan 20260059.138.00$0
Dec 20250156.664.41$4
Nov 20250458.593.93$16
Oct 20250459.383.30$13
Sep 20250462.743.08$12
Aug 20250563.933.01$15
Jul 20250566.743.32$17
Jun 20250566.483.13$16
May 20250860.553.23$26
Apr 20250462.363.54$14
Mar 20250467.704.27$17
Feb 20250470.884.34$17
Jan 20250474.324.28$17
Dec 20240468.993.12$12
Nov 20240469.052.20$9
Oct 20240571.372.28$11
Sep 20240569.612.36$12
Aug 20240675.632.06$12
Jul 202401279.932.15$26
Jun 20240078.082.63$0
May 20240178.812.20$2
Apr 20240184.451.66$2
Mar 20240480.301.55$6
Feb 20240576.091.78$9
Jan 20240573.023.30$16
Dec 20230671.262.61$16
Nov 20230677.892.81$17
Oct 20230685.443.09$19
Sep 20230689.042.74$16
Aug 20230580.522.67$13
Jul 20230674.852.64$16
Jun 20230668.962.26$14
May 20230670.622.23$13
Apr 20230678.122.24$13
Mar 20230672.852.39$14
Feb 20230475.112.47$10
Jan 20230576.533.39$17
Dec 20220576.415.73$29
Nov 20220585.005.65$28
Oct 20220487.185.86$23
Sep 20220584.888.16$41
Aug 20220594.529.13$46
Jul 202204101.587.54$30
Jun 202204115.097.98$32
May 202205109.378.43$42
Apr 202205104.226.84$34
Mar 202205108.885.08$25
Feb 20220491.054.86$19
Jan 20220581.844.54$23
Dec 20210471.323.90$16
Nov 20210477.435.24$21
Oct 20210079.795.71$0
Sep 20210169.865.35$5
Aug 20210466.024.22$17
Jul 20210470.783.98$16
Jun 20210569.493.38$17
May 20210463.483.02$12
Apr 20210460.362.76$11
Mar 20210561.302.72$14
Feb 20210457.805.55$22
Jan 20210450.412.81$11
Dec 20200444.642.68$11
Nov 20200438.772.71$11
Oct 20200436.972.48$10
Sep 20200437.091.99$8
Aug 20200539.982.39$12
Jul 20200438.371.83$7
Jun 20200434.901.69$7
May 20200416.921.81$7
Apr 20200414.751.80$7
Mar 20200430.341.86$7
Feb 20200349.881.98$6
Jan 20200357.252.09$6
Dec 20190359.012.30$7
Nov 20190355.302.75$8
Oct 20190353.472.42$7
Sep 20190355.052.66$8
Aug 20190353.112.30$7
Jul 20190356.272.46$7
Jun 20190352.782.49$7
May 20190358.482.74$8
Apr 201907062.632.75$193
Mar 20190356.803.06$9
Feb 20190650.852.79$17
Jan 20190146.033.23$3
Dec 20180046.594.19$0
Nov 20180052.934.24$0
Oct 20180161.443.40$3
Sep 20180059.543.11$0
Aug 20180159.403.07$3
Jul 20180165.142.93$3
Jun 20180160.183.08$3
May 20180165.382.90$3
Apr 20180163.842.90$3
Mar 20180061.222.79$0
Feb 20180061.782.77$0
Jan 20180062.874.01$0
Dec 20170057.272.92$0
Nov 20170055.423.12$0
Oct 20170049.292.98$0
Sep 20170047.523.09$0
Aug 20170045.373.00$0
Jul 20170043.873.09$0
Jun 20170042.493.09$0
May 20170245.373.26$7
Apr 20170047.933.21$0
Mar 20170046.772.98$0
Feb 20170050.452.95$0
Jan 20170049.413.42$0
Dec 20160048.763.72$0
Nov 20160042.492.64$0
Oct 20160046.193.09$0
Sep 20160041.553.10$0
Aug 20160041.442.92$0
Jul 20160041.622.92$0
Jun 20160045.352.69$0
May 20160042.521.99$0
Apr 20160036.561.99$0
Mar 20160033.011.79$0
Feb 20160026.472.06$0
Jan 20160027.352.36$0
Dec 20150032.362.00$0
Nov 20150138.792.17$2
Oct 20150043.552.43$0
Sep 20150042.992.76$0
Aug 20150040.162.87$0
Jul 20150048.152.95$0
Jun 20150156.152.88$3
May 20150155.212.96$3
Apr 20150249.822.71$5
Mar 20150342.892.93$9
Feb 20150244.662.98$6
Jan 20150043.433.10$0
Dec 20140054.693.59$0
Nov 20140270.464.25$9
Oct 20140178.303.90$4
Sep 20140086.164.05$0
Aug 20140189.394.04$4
Jul 20140196.564.18$4
Jun 20140098.164.74$0
May 20140094.734.73$0
Apr 20140095.944.81$0
Mar 20140095.895.06$0
Feb 20140097.406.19$0
Jan 20140090.404.86$0
Dec 20130091.824.35$0
Nov 20130188.853.74$4
Oct 20130197.423.78$4
Sep 201302104.113.72$7
Aug 201302104.253.52$7
Jul 201303102.523.72$11
Jun 20130494.403.93$16
May 20130694.834.15$25
Apr 20130693.964.28$26
Mar 20130793.623.91$27
Feb 20130791.233.42$24
Jan 20130891.603.42$27
Dec 20120986.773.42$31
Nov 20120986.953.62$33
Oct 201201089.383.40$34
Sep 20120894.672.92$23
Aug 201201092.662.91$29
Jul 201201185.133.02$33
Jun 201201279.822.52$30
May 201201491.612.49$35
Apr 2012016101.652.00$32
Mar 2012017105.052.22$38
Feb 2012018101.102.57$46
Jan 201202498.092.73$66
Dec 201102896.873.24$91
Nov 20110695.723.31$20
Oct 201103284.983.65$117
Sep 20110383.623.99$12
Aug 20110983.404.15$37
Jul 201101494.144.52$63
Jun 20110392.904.64$14
May 201103098.134.40$132
Apr 2011040105.964.33$173
Mar 201104596.364.06$183
Feb 201104185.644.18$171
Jan 201104786.504.59$216
Dec 201005085.734.35$217
Nov 201005180.843.80$194
Oct 201005678.103.51$197
Sep 201005772.633.98$227
Aug 201004573.684.42$199
Jul 201006672.554.74$313
Jun 201003870.364.91$187
May 201006371.124.24$267
Apr 201006381.694.12$260
Mar 201006578.394.39$285
Feb 201005673.585.44$305
Jan 201007274.365.96$429
Dec 200903971.445.48$214
Nov 200907774.593.75$289
Oct 200905872.544.11$238
Sep 200905165.543.06$156
Aug 20090567.423.22$16
Jul 200905761.133.46$197
Jun 200906866.163.90$265
May 200908554.743.93$334
Apr 200908146.773.59$291
Mar 200908742.144.06$353
Feb 200908132.814.63$375
Jan 200907135.865.37$381
Dec 200806037.105.98$359
Nov 200806055.496.86$412
Oct 200806875.246.92$471
Sep 2008071101.767.88$559
Aug 2008078114.228.48$662
Jul 2008081131.0811.39$923
Jun 20080102131.3313.03$1,329
May 20080112123.1711.57$1,296
Apr 20080110110.3110.45$1,150
Mar 20080116101.909.66$1,121
Feb 2008011892.538.77$1,035
Jan 2008013790.388.21$1,124
Dec 2007015088.337.30$1,095
Nov 2007013691.677.29$992
Oct 2007014182.856.92$976
Sep 2007012775.846.24$793
Aug 2007014269.066.39$907
Jul 2007015770.906.39$1,003
Jun 2007018862.007.55$1,419
May 2007022858.747.85$1,789
Apr 2007018759.617.81$1,460
Mar 2007021456.927.30$1,563
Feb 2007021955.108.22$1,799
Jan 2007025350.306.73$1,702
Dec 2006021656.656.92$1,494
Nov 2006017254.207.62$1,310
Oct 2006024854.906.01$1,491
Sep 2006028560.085.04$1,436
Aug 2006031868.717.34$2,334
Jul 2006034369.376.34$2,176
Jun 2006031066.286.38$1,979
May 2006041466.016.42$2,660
Apr 2006042864.397.36$3,150
Mar 2006045156.707.08$3,194
Feb 2006043057.597.75$3,333
Jan 2006049160.598.93$4,386
Dec 2005044454.9413.42$5,956
Nov 2005062254.6910.59$6,586
Oct 2005066458.3413.80$9,160
Sep 2005063061.4512.08$7,610
Aug 200501,31661.519.80$12,893
Jul 2005085055.697.84$6,667
Jun 200501,36952.337.38$10,105
May 200501,20545.226.65$8,015
Apr 2005071549.207.36$5,263
Mar 2005046350.377.15$3,313
Feb 2005083545.226.31$5,270
Jan 200501,35243.166.32$8,548
Dec 200401,44739.866.75$9,769
Nov 200401,06445.286.33$6,736
Oct 200402,02249.706.52$13,174
Sep 200401,31743.245.28$6,959
Aug 200401,64842.375.55$9,147
Jul 200401,79038.286.08$10,891
Jun 200401,69436.106.43$10,898
May 200401,86937.486.49$12,138
Apr 200401,60434.475.86$9,397
Mar 200401,49234.365.53$8,251
Feb 200401,96432.455.51$10,821
Jan 200401,72632.036.30$10,873
Dec 200302,13230.266.30$13,435
Nov 200302,08228.804.60$9,567
Oct 200301,19628.174.76$5,693
Sep 200301,72226.314.75$8,178
Aug 200301,64229.765.13$8,423
Jul 200302,43629.415.17$12,596
Jun 200301,94928.565.98$11,661
May 200301,97326.595.97$11,784
Apr 200302,81926.675.41$15,243
Mar 200302,07431.146.10$12,643
Feb 200301,57833.487.93$12,507
Jan 200301,91730.315.58$10,701
Dec 200202,18926.914.85$10,625
Nov 200202,36624.664.14$9,788
Oct 200203,13226.464.23$13,246
Sep 200202,16827.443.64$7,881
Aug 200202,79025.963.16$8,828
Jul 200202,21324.583.06$6,776
Jun 200203,04823.733.34$10,175
May 200203,46724.663.58$12,426
Apr 200234,57623.653.51$16,143
Mar 200214,54822.003.10$14,133
Feb 200204,17718.222.38$9,923
Jan 200204,26617.172.38$10,135
Dec 200102,17116.932.36$5,133
Nov 200102,80618.072.41$6,750
Oct 200103,06219.782.53$7,743
Sep 200102,73324.262.25$6,153
Aug 200103,36024.873.05$10,259
Jul 200103,74323.933.20$11,967
Jun 200104,22824.563.82$16,169
May 200106,02025.524.31$25,930
Apr 200107,81424.685.34$41,690
Mar 200106,95124.545.38$37,372

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                    2 Mcf  × $  3.05 =         $6

────────────────────────────────────────────────────
Month total                                       $6

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/183128 is the state's own key, not one this site invented.