ROBERTSON, W. B. JR.

Operated by DJH OIL & GAS LLC (P-5 221734) in the OZONA (CANYON SAND) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 183947District 7CField 679952002 tax incentive programmesCondensateGasSaveExport
Value, all time
$2.3 M
May 2001 – Aug 2023
Value, last 12 filed months
$69
at the published price for each month
Months reported
268
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 2,312 leases and 2,323 wells, and the rule below applies to all of them.

Discovered
1962-02-23
as the register files it
Field class
Oil and gas
the register's own label
Between wells
600 ft
minimum
From a lease line
660 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2006-09-12.

The Commission's schedule remark for this field reads: ZONE TO BE SET UP IN OZONA (CANYON SAND, OIL).

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112001-11-28145642
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition2,318 bbl$61,122
GasProduction471,073 Mcf$2,203,712
Total$2,264,834

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.5499, -101.3901. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.54993, -101.39007 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
100.0%
1 of 1 wells
With a plug date
100.0%
1 of 1 wells
Median depth
10,275 ft
1 wells filed one
Completion to plug
21.5 years
median over 1 well

What the state filed about each well

On the RRC proration schedule
1100.0%
A plug date is filed
1100.0%
BothOn the schedule and plugged. Neither fact cancels the other.
1100.0%
NeitherNo plug date, and not on the schedule.
00.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 10,275 ft.

Completions filed
May 2001
1 of 1 wells
Plug dates filed
Nov 2022
1 of 1 wells

Last completion to plug: a median of 21.5 years across the 1 well that filed both dates, with the middle half between 21.5 years and 21.5 years. The gap is the distance between two filed dates. It is not a statement of how long the well produced.

1 well

42-10538598310,275 ftMay 2001Nov 2022Yes

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (268)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

268 months

Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20231068.962.26$69
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 2022138981.844.54$1,847
Dec 2021047571.323.90$1,852
Nov 2021048677.435.24$2,545
Oct 2021057079.795.71$3,257
Sep 2021061169.865.35$3,269
Aug 2021059766.024.22$2,520
Jul 2021068470.783.98$2,724
Jun 2021044469.493.38$1,501
May 2021078763.483.02$2,375
Apr 2021070660.362.76$1,947
Mar 2021066961.302.72$1,818
Feb 2021045257.805.55$2,508
Jan 2021150550.412.81$1,470
Dec 2020057644.642.68$1,541
Nov 2020052538.772.71$1,421
Oct 2020051836.972.48$1,284
Sep 2020052437.091.99$1,043
Aug 2020055539.982.39$1,324
Jul 2020050438.371.83$920
Jun 2020044234.901.69$747
May 2020053716.921.81$975
Apr 2020055514.751.80$1,001
Mar 2020063230.341.86$1,173
Feb 2020058949.881.98$1,167
Jan 2020159757.252.09$1,308
Dec 2019054559.012.30$1,256
Nov 2019041855.302.75$1,150
Oct 2019044053.472.42$1,064
Sep 2019042355.052.66$1,124
Aug 2019054353.112.30$1,251
Jul 2019042156.272.46$1,036
Jun 2019047352.782.49$1,178
May 2019049658.482.74$1,359
Apr 2019050562.632.75$1,389
Mar 2019057356.803.06$1,755
Feb 2019045150.852.79$1,259
Jan 2019052646.033.23$1,698
Dec 2018045646.594.19$1,909
Nov 2018143152.934.24$1,879
Oct 2018040661.443.40$1,380
Sep 2018042259.543.11$1,312
Aug 2018049359.403.07$1,512
Jul 2018058565.142.93$1,715
Jun 2018050460.183.08$1,551
May 2018049765.382.90$1,442
Apr 2018045963.842.90$1,331
Mar 2018052861.222.79$1,471
Feb 2018061661.782.77$1,704
Jan 2018064562.874.01$2,586
Dec 2017062657.272.92$1,829
Nov 2017055455.423.12$1,728
Oct 2017148449.292.98$1,493
Sep 2017069447.523.09$2,143
Aug 2017083545.373.00$2,509
Jul 2017084343.873.09$2,603
Jun 2017080042.493.09$2,470
May 2017077545.373.26$2,529
Apr 2017081347.933.21$2,611
Mar 2017084746.772.98$2,527
Feb 2017053650.452.95$1,583
Jan 2017074949.413.42$2,561
Dec 2016167048.763.72$2,543
Nov 2016056542.492.64$1,494
Oct 2016062846.193.09$1,941
Sep 2016064441.553.10$1,997
Aug 2016064041.442.92$1,872
Jul 2016063241.622.92$1,848
Jun 2016085045.352.69$2,283
May 2016060642.521.99$1,207
Apr 2016291736.561.99$1,899
Mar 2016098833.011.79$1,772
Feb 2016080726.472.06$1,665
Jan 201601,07627.352.36$2,544
Dec 2015192832.362.00$1,890
Nov 201501,00838.792.17$2,185
Oct 201501,15043.552.43$2,791
Sep 201501,07042.992.76$2,952
Aug 201501,03040.162.87$2,959
Jul 2015094748.152.95$2,789
Jun 2015096556.152.88$2,782
May 2015044855.212.96$1,324
Apr 2015185649.822.71$2,367
Mar 2015089442.892.93$2,624
Feb 2015073044.662.98$2,173
Jan 2015055643.433.10$1,724
Dec 2014069554.693.59$2,496
Nov 2014163270.464.25$2,758
Oct 2014080778.303.90$3,148
Sep 2014077286.164.05$3,123
Aug 2014075989.394.04$3,063
Jul 2014075896.564.18$3,168
Jun 2014087398.164.74$4,135
May 2014077694.734.73$3,668
Apr 2014094995.944.81$4,564
Mar 201401,05595.895.06$5,335
Feb 2014197297.406.19$6,116
Jan 201401,00390.404.86$4,875
Dec 2013091491.824.35$3,980
Nov 201311,00588.853.74$3,846
Oct 2013090797.423.78$3,428
Sep 201301,017104.113.72$3,781
Aug 201301,345104.253.52$4,738
Jul 201301,133102.523.72$4,212
Jun 2013095794.403.93$3,764
May 201301,02694.834.15$4,257
Apr 201311,14393.964.28$4,989
Mar 2013090393.623.91$3,533
Feb 2013092591.233.42$3,163
Jan 201311,07791.603.42$3,775
Dec 201201,04486.773.42$3,571
Nov 2012073086.953.62$2,646
Oct 2012078489.383.40$2,665
Sep 2012178094.672.92$2,371
Aug 201201,08392.662.91$3,150
Jul 201201,09585.133.02$3,308
Jun 2012092879.822.52$2,338
May 2012092691.612.49$2,304
Apr 20120897101.652.00$1,791
Mar 20120963105.052.22$2,140
Feb 20120864101.102.57$2,221
Jan 201201,12898.092.73$3,084
Dec 2011184496.873.24$2,831
Nov 201101,04395.723.31$3,454
Oct 201101,02884.983.65$3,751
Sep 2011095383.623.99$3,798
Aug 201101,18583.404.15$4,917
Jul 201101,12194.144.52$5,064
Jun 2011095292.904.64$4,417
May 201111,25898.134.40$5,639
Apr 20110957105.964.33$4,147
Mar 201101,38796.364.06$5,628
Feb 201101,04585.644.18$4,368
Jan 201111,08686.504.59$5,070
Dec 201001,37485.734.35$5,974
Nov 201011,21180.843.80$4,677
Oct 201001,16178.103.51$4,074
Sep 201001,12372.633.98$4,469
Aug 201001,11973.684.42$4,945
Jul 201001,03972.554.74$4,921
Jun 2010098670.364.91$4,842
May 201011,11871.124.24$4,806
Apr 201001,07481.694.12$4,428
Mar 2010098678.394.39$4,327
Feb 2010092973.585.44$5,056
Jan 201011,12074.365.96$6,754
Dec 200901,17171.445.48$6,421
Nov 2009141,22874.593.75$5,651
Oct 200901,13372.544.11$4,657
Sep 200901,22765.543.06$3,760
Aug 200901,38367.423.22$4,451
Jul 200901,55261.133.46$5,377
Jun 200901,38266.163.90$5,383
May 200901,49354.743.93$5,861
Apr 2009201,31746.773.59$5,660
Mar 200901,33842.144.06$5,431
Feb 2009201,20632.814.63$6,244
Jan 200901,35735.865.37$7,288
Dec 2008201,53637.105.98$9,923
Nov 200801,58155.496.86$10,846
Oct 2008171,55275.246.92$12,022
Sep 200801,080101.767.88$8,507
Aug 200801,393114.228.48$11,817
Jul 200801,280131.0811.39$14,578
Jun 200801,568131.3313.03$20,435
May 200801,414123.1711.57$16,366
Apr 200841,459110.3110.45$15,695
Mar 200801,565101.909.66$15,124
Feb 200831,28792.538.77$11,565
Jan 200801,37590.388.21$11,283
Dec 200741,43188.337.30$10,802
Nov 200701,49791.677.29$10,916
Oct 200701,63282.856.92$11,297
Sep 200701,45675.846.24$9,092
Aug 200701,53069.066.39$9,774
Jul 200731,49370.906.39$9,750
Jun 200701,53662.007.55$11,594
May 200701,58558.747.85$12,436
Apr 200701,65559.617.81$12,918
Mar 200731,78356.927.30$13,190
Feb 200731,42255.108.22$11,848
Jan 200731,51850.306.73$10,362
Dec 200601,65856.656.92$11,471
Nov 200631,71854.207.62$13,249
Oct 200601,83454.906.01$11,029
Sep 200601,81660.085.04$9,148
Aug 200601,79568.717.34$13,175
Jul 200632,03469.376.34$13,109
Jun 200601,93666.286.38$12,359
May 200602,09366.016.42$13,448
Apr 200631,88764.397.36$14,082
Mar 200602,13156.707.08$15,094
Feb 200631,83857.597.75$14,419
Jan 200632,05660.598.93$18,549
Dec 200532,06254.9413.42$27,827
Nov 200541,96454.6910.59$21,014
Oct 200502,03258.3413.80$28,033
Sep 200541,66961.4512.08$20,406
Aug 200502,01761.519.80$19,760
Jul 200502,19855.697.84$17,240
Jun 200572,12452.337.38$16,044
May 200502,18945.226.65$14,559
Apr 200502,25549.207.36$16,598
Mar 200582,44550.377.15$17,897
Feb 200582,31445.226.31$14,968
Jan 200582,32343.166.32$15,032
Dec 200482,75739.866.75$18,932
Nov 2004172,61345.286.33$17,311
Oct 200422,82649.706.52$18,511
Sep 200482,95043.245.28$15,933
Aug 2004103,13042.375.55$17,797
Jul 200403,04138.286.08$18,502
Jun 2004103,29436.106.43$21,551
May 200483,50337.486.49$23,050
Apr 2004102,94934.475.86$17,621
Mar 2004282,93434.365.53$17,188
Feb 2004283,21532.455.51$18,622
Jan 2004293,70232.036.30$24,250
Dec 2003274,00630.266.30$26,061
Nov 200303,91028.804.60$17,967
Oct 2003274,03728.174.76$19,975
Sep 200324,09326.314.75$19,492
Aug 2003274,30029.765.13$22,861
Jul 200304,32029.415.17$22,338
Jun 2003294,15328.565.98$25,675
May 200304,53526.595.97$27,086
Apr 2003534,39626.675.41$25,184
Mar 2003274,83431.146.10$30,309
Feb 2003274,11333.487.93$33,503
Jan 2003304,65930.315.58$26,916
Dec 2002564,69526.914.85$24,295
Nov 2002274,84524.664.14$20,709
Oct 2002527,80226.464.23$34,372
Sep 2002275,04827.443.64$19,091
Aug 2002275,68025.963.16$18,673
Jul 2002275,48024.583.06$17,442
Jun 2002275,64323.733.34$19,478
May 2002286,69024.663.58$24,667
Apr 2002856,87823.653.51$26,168
Mar 2002917,33422.003.10$24,757
Feb 20021107,31318.222.38$19,378
Jan 20021649,56517.172.38$25,539
Dec 200118111,35816.932.36$29,919
Nov 20011475,93018.072.41$16,921
Oct 20011967,97819.782.53$24,052
Sep 20011687,52424.262.25$21,015
Aug 200121510,90824.873.05$38,651
Jul 2001899,83423.933.20$33,570
Jun 2001019,76924.563.82$75,600
May 2001019,05625.524.31$82,080

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Jun 2023 — as filed, then multipliedworked
Condensate             1 bbl  × $ 68.96 =        $69
Gas                    0 Mcf  × $  2.26 =         $0

────────────────────────────────────────────────────
Month total                                      $69

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/183947 is the state's own key, not one this site invented.