FIELDS 17

Operated by UPP OPERATING, LLC (P-5 875310) in the SAWYER (CANYON) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 186228District 7CField 812673332 tax incentive programmesCondensateGasSaveExport
Value, all time
$232 k
Sep 2001 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
297
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6,629 leases and 6,629 wells, and the rule below applies to all of them.

Discovered
1967-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,000 ft
minimum
From a lease line
500 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2003-06-24.

The Commission's schedule remark for this field reads: FIELD PER ORDER 7C-0234582 6/2403

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112002-01-15145776
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition63 bbl$3,341
GasProduction41,255 Mcf$228,162
Total$231,502

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.5064, -100.6216. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.50640, -100.62158 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
6,127 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 6,127 ft.

Completions filed
Sep 2001
1 of 1 wells

1 well

42-43535599176,127 ftSep 2001

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (297)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

297 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 202001944.642.68$51
Nov 20200138.772.71$3
Oct 20200336.972.48$7
Sep 20200637.091.99$12
Aug 202002239.982.39$52
Jul 202003338.371.83$60
Jun 202002934.901.69$49
May 202002716.921.81$49
Apr 202002514.751.80$45
Mar 202002230.341.86$41
Feb 20200049.881.98$0
Jan 20200157.252.09$2
Dec 201902559.012.30$58
Nov 20190055.302.75$0
Oct 20190353.472.42$7
Sep 20190155.052.66$3
Aug 20190053.112.30$0
Jul 20190156.272.46$2
Jun 20190552.782.49$12
May 20190758.482.74$19
Apr 20190562.632.75$14
Mar 20190356.803.06$9
Feb 20190550.852.79$14
Jan 20190646.033.23$19
Dec 20180946.594.19$38
Nov 20180652.934.24$25
Oct 20180761.443.40$24
Sep 20180559.543.11$16
Aug 20180559.403.07$15
Jul 20180265.142.93$6
Jun 20180260.183.08$6
May 20180665.382.90$17
Apr 20180563.842.90$15
Mar 201801661.222.79$45
Feb 20180461.782.77$11
Jan 201801162.874.01$44
Dec 201701757.272.92$50
Nov 201701755.423.12$53
Oct 201701949.292.98$57
Sep 201701847.523.09$56
Aug 201701945.373.00$57
Jul 201702143.873.09$65
Jun 201705642.493.09$173
May 20170045.373.26$0
Apr 201703047.933.21$96
Mar 201701946.772.98$57
Feb 201701850.452.95$53
Jan 201707049.413.42$239
Dec 201604748.763.72$175
Nov 201605842.492.64$153
Oct 201605746.193.09$176
Sep 201605941.553.10$183
Aug 201605441.442.92$158
Jul 201607041.622.92$205
Jun 201605545.352.69$148
May 201606142.521.99$121
Apr 201606436.561.99$127
Mar 201606233.011.79$111
Feb 201606026.472.06$124
Jan 201607127.352.36$168
Dec 201507132.362.00$142
Nov 201502638.792.17$56
Oct 201506243.552.43$150
Sep 201504542.992.76$124
Aug 201504440.162.87$126
Jul 201504248.152.95$124
Jun 201504056.152.88$115
May 201505955.212.96$174
Apr 201502249.822.71$60
Mar 201502042.892.93$59
Feb 201502144.662.98$63
Jan 201503343.433.10$102
Dec 201402154.693.59$75
Nov 201401870.464.25$77
Oct 201401078.303.90$39
Sep 201405186.164.05$206
Aug 201401689.394.04$65
Jul 201403596.564.18$146
Jun 201404698.164.74$218
May 201405894.734.73$274
Apr 201406395.944.81$303
Mar 201405695.895.06$283
Feb 201405097.406.19$310
Jan 201406490.404.86$311
Dec 201306791.824.35$292
Nov 201306888.853.74$254
Oct 201306897.423.78$257
Sep 2013068104.113.72$253
Aug 2013068104.253.52$240
Jul 2013068102.523.72$253
Jun 201306794.403.93$264
May 201307194.834.15$295
Apr 201307393.964.28$313
Mar 201308093.623.91$313
Feb 201307191.233.42$243
Jan 201306991.603.42$236
Dec 201206986.773.42$236
Nov 201207086.953.62$254
Oct 201207489.383.40$252
Sep 201207194.672.92$207
Aug 201207692.662.91$221
Jul 201207685.133.02$230
Jun 201207979.822.52$199
May 201205691.612.49$139
Apr 2012079101.652.00$158
Mar 2012084105.052.22$187
Feb 2012085101.102.57$218
Jan 201209898.092.73$268
Dec 201107596.873.24$243
Nov 201107995.723.31$262
Oct 201108284.983.65$299
Sep 201107483.623.99$295
Aug 201108183.404.15$336
Jul 201108594.144.52$384
Jun 201108692.904.64$399
May 201109098.134.40$396
Apr 2011089105.964.33$386
Mar 201109796.364.06$394
Feb 201107685.644.18$318
Jan 201109686.504.59$441
Dec 201009685.734.35$417
Nov 201009380.843.80$353
Oct 201009978.103.51$347
Sep 201009772.633.98$386
Aug 2010010573.684.42$464
Jul 2010010472.554.74$493
Jun 2010010570.364.91$516
May 2010011071.124.24$466
Apr 2010010581.694.12$433
Mar 2010011178.394.39$487
Feb 2010010173.585.44$550
Jan 2010011074.365.96$656
Dec 2009011571.445.48$631
Nov 2009011574.593.75$431
Oct 2009011972.544.11$489
Sep 2009011765.543.06$359
Aug 2009012567.423.22$402
Jul 2009012561.133.46$433
Jun 2009012366.163.90$479
May 2009013754.743.93$538
Apr 2009011146.773.59$398
Mar 2009013342.144.06$540
Feb 2009012032.814.63$556
Jan 2009013135.865.37$704
Dec 2008012437.105.98$741
Nov 200807155.496.86$487
Oct 200808175.246.92$561
Sep 2008078101.767.88$614
Aug 2008099114.228.48$840
Jul 2008088131.0811.39$1,002
Jun 2008190131.3313.03$1,304
May 2008098123.1711.57$1,134
Apr 2008195110.3110.45$1,104
Mar 20081107101.909.66$1,136
Feb 2008116192.538.77$1,505
Jan 2008119290.388.21$1,666
Dec 2007118988.337.30$1,468
Nov 2007120091.677.29$1,550
Oct 2007121082.856.92$1,536
Sep 2007121375.846.24$1,406
Aug 2007133969.066.39$2,235
Jul 2007021170.906.39$1,348
Jun 2007030862.007.55$2,325
May 200714658.747.85$420
Apr 2007114359.617.81$1,176
Mar 2007127556.927.30$2,065
Feb 2007116055.108.22$1,370
Jan 2007032450.306.73$2,180
Dec 2006131956.656.92$2,264
Nov 2006135554.207.62$2,758
Oct 2006139654.906.01$2,436
Sep 2006148060.085.04$2,478
Aug 2006149768.717.34$3,717
Jul 2006149169.376.34$3,184
Jun 2006341166.286.38$2,823
May 2006250566.016.42$3,377
Apr 2006348664.397.36$3,770
Mar 2006050356.707.08$3,563
Feb 2006144757.597.75$3,522
Jan 2006046860.598.93$4,181
Dec 2005147254.9413.42$6,387
Nov 2005346754.6910.59$5,109
Oct 2005048858.3413.80$6,732
Sep 2005248261.4512.08$5,945
Aug 2005048461.519.80$4,742
Jul 2005048155.697.84$3,773
Jun 2005136952.337.38$2,776
May 2005256045.226.65$3,815
Apr 2005252949.207.36$3,992
Mar 2005259250.377.15$4,336
Feb 2005056645.226.31$3,573
Jan 2005062243.166.32$3,932
Dec 2004058839.866.75$3,970
Nov 2004046845.286.33$2,963
Oct 2004148549.706.52$3,210
Sep 2004248343.245.28$2,639
Aug 2004048942.375.55$2,714
Jul 2004049738.286.08$3,024
Jun 2004031536.106.43$2,026
May 2004015637.486.49$1,013
Apr 2004025734.475.86$1,506
Mar 2004025434.365.53$1,405
Feb 2004024132.455.51$1,328
Jan 2004026832.036.30$1,688
Dec 2003026630.266.30$1,676
Nov 2003026328.804.60$1,209
Oct 2003026128.174.76$1,242
Sep 2003032326.314.75$1,534
Aug 2003036229.765.13$1,857
Jul 2003036929.415.17$1,908
Jun 2003025128.565.98$1,502
May 2003042126.595.97$2,515
Apr 2003042726.675.41$2,309
Mar 2003034231.146.10$2,085
Feb 2003140233.487.93$3,220
Jan 2003128930.315.58$1,644
Dec 200216226.914.85$328
Nov 2002141824.664.14$1,754
Oct 2002138726.464.23$1,663
Sep 2002130727.443.64$1,143
Aug 2002157625.963.16$1,849
Jul 200201,04024.583.06$3,184
Jun 2002142723.733.34$1,449
May 2002065824.663.58$2,358
Apr 2002149223.653.51$1,752
Mar 2002124722.003.10$788
Feb 2002128818.222.38$702
Jan 2002018517.172.38$440
Dec 2001274616.932.36$1,798
Nov 2001396918.072.41$2,385
Oct 200121,25019.782.53$3,201
Sep 200101,56024.262.25$3,512

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Dec 2020 — as filed, then multipliedworked
Condensate             0 bbl  × $ 44.64 =         $0
Gas                   19 Mcf  × $  2.68 =        $51

────────────────────────────────────────────────────
Month total                                      $51

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well