PIERCE, V. I. "44"

Operated by SCOUT ENERGY MANAGEMENT LLC (P-5 760218) in the OZONA (CANYON SAND) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 189796District 7CField 679952002 tax incentive programmesCondensateGasSaveExport
Value, all time
$1.2 M
Feb 2002 – May 2026
Value, last 12 filed months
$49 k
at the published price for each month
Months reported
292
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 2,312 leases and 2,323 wells, and the rule below applies to all of them.

Discovered
1962-02-23
as the register files it
Field class
Oil and gas
the register's own label
Between wells
600 ft
minimum
From a lease line
660 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2006-09-12.

The Commission's schedule remark for this field reads: ZONE TO BE SET UP IN OZONA (CANYON SAND, OIL).

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112002-09-03148866
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition163 bbl$11,245
GasProduction259,655 Mcf$1,226,610
Total$1,237,855

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.4074, -101.3473. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.40740, -101.34734 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
6,700 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 6,700 ft.

Completions filed
Feb 2002
1 of 1 wells

1 well

42-1053880066,700 ftFeb 2002

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (292)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

292 months

May 202661,028106.413.05$3,770
Apr 20261586898.932.87$3,975
Mar 20266089.753.15$539
Feb 20262985563.503.75$5,048
Jan 202691,04259.138.00$8,866
Dec 2025111,00056.664.41$5,037
Nov 2025992158.593.93$4,144
Oct 2025695459.383.30$3,509
Sep 202541,04262.743.08$3,457
Aug 2025889963.933.01$3,222
Jul 2025793566.743.32$3,567
Jun 202561,07066.483.13$3,747
May 2025121,07060.553.23$4,185
Apr 20251197962.363.54$4,155
Mar 20251288567.704.27$4,590
Feb 20251281170.884.34$4,371
Jan 20250074.324.28$0
Dec 2024098468.993.12$3,071
Nov 202401,10569.052.20$2,429
Oct 202401,26771.372.28$2,891
Sep 202401,00469.612.36$2,374
Aug 202401,06775.632.06$2,202
Jul 2024065079.932.15$1,395
Jun 2024057878.082.63$1,522
May 2024058078.812.20$1,275
Apr 2024060784.451.66$1,007
Mar 2024056780.301.55$876
Feb 2024039576.091.78$705
Jan 2024037273.023.30$1,227
Dec 2023063171.262.61$1,647
Nov 2023067577.892.81$1,895
Oct 2023065785.443.09$2,028
Sep 2023066189.042.74$1,808
Aug 2023065880.522.67$1,759
Jul 2023065174.852.64$1,720
Jun 2023063568.962.26$1,434
May 2023055870.622.23$1,243
Apr 2023065578.122.24$1,466
Mar 2023061872.852.39$1,479
Feb 2023053175.112.47$1,309
Jan 2023070576.533.39$2,388
Dec 2022074376.415.73$4,257
Nov 2022080285.005.65$4,528
Oct 2022085987.185.86$5,037
Sep 2022093084.888.16$7,592
Aug 2022093894.529.13$8,561
Jul 202201,041101.587.54$7,851
Jun 202201,011115.097.98$8,065
May 20220945109.378.43$7,969
Apr 202201,019104.226.84$6,968
Mar 202201,045108.885.08$5,305
Feb 2022078791.054.86$3,824
Jan 2022081781.844.54$3,707
Dec 2021085971.323.90$3,349
Nov 2021093677.435.24$4,902
Oct 2021097779.795.71$5,582
Sep 2021079969.865.35$4,275
Aug 2021040966.024.22$1,726
Jul 2021072070.783.98$2,867
Jun 2021066369.493.38$2,241
May 2021046563.483.02$1,403
Apr 2021070560.362.76$1,945
Mar 2021096161.302.72$2,611
Feb 2021060657.805.55$3,362
Jan 2021032850.412.81$922
Dec 2020056444.642.68$1,509
Nov 2020060738.772.71$1,643
Oct 2020064636.972.48$1,601
Sep 2020055037.091.99$1,095
Aug 2020060639.982.39$1,445
Jul 2020061538.371.83$1,122
Jun 2020061434.901.69$1,038
May 2020064816.921.81$1,176
Apr 2020071814.751.80$1,296
Mar 2020069630.341.86$1,292
Feb 2020074049.881.98$1,466
Jan 2020066257.252.09$1,387
Dec 2019069159.012.30$1,592
Nov 2019064355.302.75$1,769
Oct 2019076053.472.42$1,838
Sep 2019080455.052.66$2,136
Aug 2019099353.112.30$2,288
Jul 2019068356.272.46$1,680
Jun 2019037452.782.49$932
May 2019061258.482.74$1,677
Apr 2019064862.632.75$1,782
Mar 2019066556.803.06$2,036
Feb 2019069450.852.79$1,938
Jan 2019091546.033.23$2,954
Dec 2018097646.594.19$4,085
Nov 2018082852.934.24$3,508
Oct 2018084961.443.40$2,885
Sep 201801,03259.543.11$3,207
Aug 2018075559.403.07$2,315
Jul 2018086465.142.93$2,533
Jun 2018075660.183.08$2,326
May 2018076065.382.90$2,205
Apr 2018083563.842.90$2,422
Mar 2018089561.222.79$2,494
Feb 2018082761.782.77$2,288
Jan 2018088762.874.01$3,556
Dec 2017087557.272.92$2,556
Nov 2017063655.423.12$1,983
Oct 2017079149.292.98$2,360
Sep 2017060947.523.09$1,880
Aug 2017051845.373.00$1,556
Jul 2017055743.873.09$1,720
Jun 2017055142.493.09$1,701
May 2017043745.373.26$1,426
Apr 2017049547.933.21$1,590
Mar 2017058346.772.98$1,739
Feb 2017079550.452.95$2,347
Jan 2017066949.413.42$2,287
Dec 2016088948.763.72$3,310
Nov 2016076242.492.64$2,015
Oct 2016051646.193.09$1,595
Sep 2016051141.553.10$1,584
Aug 2016053941.442.92$1,576
Jul 2016063641.622.92$1,860
Jun 2016076645.352.69$2,057
May 2016061942.521.99$1,232
Apr 2016039336.561.99$782
Mar 2016046933.011.79$841
Feb 2016041326.472.06$852
Jan 2016064627.352.36$1,527
Dec 2015067732.362.00$1,355
Nov 2015028738.792.17$622
Oct 2015055443.552.43$1,344
Sep 2015041442.992.76$1,142
Aug 2015066140.162.87$1,899
Jul 2015079848.152.95$2,350
Jun 2015081456.152.88$2,347
May 2015093255.212.96$2,754
Apr 2015094149.822.71$2,547
Mar 2015079742.892.93$2,339
Feb 2015066944.662.98$1,991
Jan 2015076643.433.10$2,375
Dec 2014081654.693.59$2,931
Nov 2014074070.464.25$3,146
Oct 2014079778.303.90$3,109
Sep 2014083586.164.05$3,378
Aug 201401,01089.394.04$4,075
Jul 2014085396.564.18$3,565
Jun 2014079998.164.74$3,785
May 201401,04694.734.73$4,944
Apr 2014083295.944.81$4,001
Mar 2014062995.895.06$3,181
Feb 2014049897.406.19$3,084
Jan 201401,03990.404.86$5,050
Dec 2013097791.824.35$4,254
Nov 2013068988.853.74$2,576
Oct 2013063897.423.78$2,411
Sep 20130794104.113.72$2,952
Aug 20130940104.253.52$3,311
Jul 201301,162102.523.72$4,320
Jun 201301,02094.403.93$4,012
May 2013077694.834.15$3,220
Apr 201301,12393.964.28$4,809
Mar 2013087793.623.91$3,432
Feb 201301,00591.233.42$3,437
Jan 2013054791.603.42$1,871
Dec 2012053586.773.42$1,830
Nov 2012065186.953.62$2,360
Oct 2012052389.383.40$1,778
Sep 2012038194.672.92$1,112
Aug 2012052192.662.91$1,515
Jul 2012072285.133.02$2,181
Jun 2012073279.822.52$1,844
May 2012069491.612.49$1,727
Apr 20120416101.652.00$831
Mar 20120321105.052.22$713
Feb 20120629101.102.57$1,617
Jan 2012092798.092.73$2,534
Dec 2011086696.873.24$2,806
Nov 201101,02195.723.31$3,381
Oct 2011093984.983.65$3,426
Sep 201101,05283.623.99$4,193
Aug 201101,03683.404.15$4,299
Jul 201101,12194.144.52$5,064
Jun 201101,10092.904.64$5,104
May 201101,03298.134.40$4,546
Apr 20110681105.964.33$2,951
Mar 2011086396.364.06$3,501
Feb 2011092385.644.18$3,858
Jan 201101,10386.504.59$5,061
Dec 2010095585.734.35$4,152
Nov 201001,24580.843.80$4,725
Oct 2010060078.103.51$2,105
Sep 2010050972.633.98$2,026
Aug 201001,00773.684.42$4,450
Jul 201001,04772.554.74$4,959
Jun 2010038570.364.91$1,891
May 2010062671.124.24$2,651
Apr 2010046281.694.12$1,905
Mar 2010091478.394.39$4,011
Feb 2010082673.585.44$4,495
Jan 2010088474.365.96$5,272
Dec 2009080571.445.48$4,414
Nov 200901,01474.593.75$3,804
Oct 200901,15472.544.11$4,743
Sep 2009090865.543.06$2,783
Aug 2009091767.423.22$2,951
Jul 2009087861.133.46$3,042
Jun 2009076066.163.90$2,960
May 2009098554.743.93$3,867
Apr 2009093546.773.59$3,354
Mar 2009033442.144.06$1,356
Feb 2009074132.814.63$3,433
Jan 2009011135.865.37$596
Dec 2008040437.105.98$2,415
Nov 2008064155.496.86$4,397
Oct 200808475.246.92$581
Sep 20080184101.767.88$1,449
Aug 20080751114.228.48$6,371
Jul 20080487131.0811.39$5,547
Jun 20080537131.3313.03$6,999
May 20080823123.1711.57$9,526
Apr 20080971110.3110.45$10,152
Mar 200801,097101.909.66$10,601
Feb 200801,09592.538.77$9,604
Jan 200801,16490.388.21$9,551
Dec 2007097588.337.30$7,119
Nov 200701,01691.677.29$7,408
Oct 200701,08182.856.92$7,483
Sep 2007049775.846.24$3,103
Aug 2007053169.066.39$3,392
Jul 2007053270.906.39$3,398
Jun 2007089862.007.55$6,779
May 200701,23958.747.85$9,722
Apr 2007024259.617.81$1,889
Mar 2007037456.927.30$2,731
Feb 2007035655.108.22$2,925
Jan 200702750.306.73$182
Dec 200607256.656.92$498
Nov 200607254.207.62$548
Oct 2006031254.906.01$1,876
Sep 2006064460.085.04$3,244
Aug 2006061668.717.34$4,521
Jul 2006084169.376.34$5,334
Jun 2006090666.286.38$5,784
May 2006085466.016.42$5,487
Apr 2006074964.397.36$5,513
Mar 200601,00556.707.08$7,118
Feb 200601,08557.597.75$8,410
Jan 200601,38360.598.93$12,355
Dec 200501,26554.9413.42$16,970
Nov 2005055454.6910.59$5,866
Oct 200501,36158.3413.80$18,776
Sep 200501,12161.4512.08$13,541
Aug 200501,33961.519.80$13,118
Jul 200501,42955.697.84$11,209
Jun 200501,14552.337.38$8,451
May 200501,31345.226.65$8,733
Apr 200501,18849.207.36$8,744
Mar 200501,32750.377.15$9,495
Feb 200501,07145.226.31$6,760
Jan 200501,17343.166.32$7,416
Dec 200401,34739.866.75$9,094
Nov 200401,58645.286.33$10,040
Oct 200401,40849.706.52$9,173
Sep 200401,30343.245.28$6,885
Aug 200401,54642.375.55$8,581
Jul 200401,57538.286.08$9,583
Jun 200401,53736.106.43$9,888
May 200401,44537.486.49$9,385
Apr 200401,63034.475.86$9,549
Mar 200401,63834.365.53$9,058
Feb 200401,55532.455.51$8,567
Jan 200401,72132.036.30$10,842
Dec 200301,82530.266.30$11,500
Nov 200301,81528.804.60$8,340
Oct 200302,02428.174.76$9,634
Sep 200301,89726.314.75$9,010
Aug 200302,06129.765.13$10,572
Jul 200302,11329.415.17$10,926
Jun 200302,16128.565.98$12,929
May 200302,30126.595.97$13,743
Apr 200302,28326.675.41$12,345
Mar 200302,38131.146.10$14,515
Feb 200302,23433.487.93$17,706
Jan 200302,49630.315.58$13,933
Dec 200202,65126.914.85$12,867
Nov 200202,74624.664.14$11,360
Oct 200202,71926.464.23$11,499
Sep 2002092527.443.64$3,363
Aug 2002040825.963.16$1,291
Jul 200201,19924.583.06$3,671
Jun 200201,42523.733.34$4,757
May 200202,10624.663.58$7,548
Apr 200202,85123.653.51$10,014
Mar 200201,74722.003.10$5,420
Feb 20020018.222.38$0

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             6 bbl  × $106.41 =       $638
Gas                1,028 Mcf  × $  3.05 =     $3,131

────────────────────────────────────────────────────
Month total                                   $3,770

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/189796 is the state's own key, not one this site invented.