KIRBY "1"

Operated by UPP OPERATING, LLC (P-5 875310) in the SAWYER (CANYON) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 192436District 7CField 812673332 tax incentive programmesCondensateGasSaveExport
Value, all time
$671 k
Jun 2002 – May 2026
Value, last 12 filed months
$57
at the published price for each month
Months reported
288
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6,629 leases and 6,629 wells, and the rule below applies to all of them.

Discovered
1967-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,000 ft
minimum
From a lease line
500 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2003-06-24.

The Commission's schedule remark for this field reads: FIELD PER ORDER 7C-0234582 6/2403

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112003-03-10149948
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition148 bbl$8,025
GasProduction121,186 Mcf$663,050
Total$671,075

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.6502, -100.7519. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.65024, -100.75191 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
8,100 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 8,100 ft.

Completions filed
Jun 2002
1 of 1 wells

1 well

42-4353584178,100 ftJun 2002

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (288)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

288 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20251056.664.41$57
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202201108.885.08$5
Feb 20220891.054.86$39
Jan 202201381.844.54$59
Dec 202121371.323.90$193
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 202102069.865.35$107
Aug 202102866.024.22$118
Jul 20210170.783.98$4
Jun 20210169.493.38$3
May 202133263.483.02$287
Apr 20210260.362.76$6
Mar 202122061.302.72$177
Feb 202102457.805.55$133
Jan 202103850.412.81$107
Dec 202023644.642.68$186
Nov 202042838.772.71$231
Oct 202005736.972.48$141
Sep 202008037.091.99$159
Aug 202011239.982.39$69
Jul 202001738.371.83$31
Jun 202001834.901.69$30
May 202002016.921.81$36
Apr 202002114.751.80$38
Mar 202013030.341.86$86
Feb 202003049.881.98$59
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20192055.302.75$111
Oct 201903053.472.42$73
Sep 201903555.052.66$93
Aug 201903453.112.30$78
Jul 201903456.272.46$84
Jun 201903352.782.49$82
May 201903458.482.74$93
Apr 201903362.632.75$91
Mar 201903356.803.06$101
Feb 201902950.852.79$81
Jan 201903146.033.23$100
Dec 201803246.594.19$134
Nov 201803552.934.24$148
Oct 201803561.443.40$119
Sep 201813459.543.11$165
Aug 201803759.403.07$113
Jul 201823865.142.93$242
Jun 201803860.183.08$117
May 201804065.382.90$116
Apr 201813963.842.90$177
Mar 201804061.222.79$111
Feb 201803761.782.77$102
Jan 201804362.874.01$172
Dec 201704557.272.92$131
Nov 201704455.423.12$137
Oct 201705249.292.98$155
Sep 201705247.523.09$161
Aug 201705745.373.00$171
Jul 201705943.873.09$182
Jun 201705842.493.09$179
May 201706245.373.26$202
Apr 201706247.933.21$199
Mar 201706746.772.98$200
Feb 201706150.452.95$180
Jan 201707249.413.42$246
Dec 201607748.763.72$287
Nov 201607742.492.64$204
Oct 201608346.193.09$256
Sep 201607941.553.10$245
Aug 201607341.442.92$213
Jul 201603241.622.92$94
Jun 201607845.352.69$209
May 201609942.521.99$197
Apr 2016010236.561.99$203
Mar 2016011333.011.79$203
Feb 2016021226.472.06$437
Jan 2016054427.352.36$1,286
Dec 2015011232.362.00$224
Nov 2015010538.792.17$228
Oct 2015020543.552.43$497
Sep 2015019542.992.76$538
Aug 2015020240.162.87$580
Jul 2015120148.152.95$640
Jun 2015119756.152.88$624
May 2015022755.212.96$671
Apr 2015122449.822.71$656
Mar 2015122042.892.93$689
Feb 2015320244.662.98$735
Jan 2015123543.433.10$772
Dec 2014123854.693.59$909
Nov 2014023670.464.25$1,003
Oct 2014016078.303.90$624
Sep 2014015986.164.05$643
Aug 2014016189.394.04$650
Jul 2014017096.564.18$711
Jun 2014013798.164.74$649
May 2014017894.734.73$841
Apr 2014220995.944.81$1,197
Mar 2014117795.895.06$991
Feb 2014122297.406.19$1,472
Jan 2014126890.404.86$1,393
Dec 2013030891.824.35$1,341
Nov 2013026588.853.74$991
Oct 2013118697.423.78$800
Sep 20130279104.113.72$1,037
Aug 20130327104.253.52$1,152
Jul 20130316102.523.72$1,175
Jun 2013129694.403.93$1,259
May 2013131194.834.15$1,385
Apr 2013038093.964.28$1,627
Mar 2013031493.623.91$1,229
Feb 201303291.233.42$109
Jan 201308491.603.42$287
Dec 2012011386.773.42$386
Nov 201203486.953.62$123
Oct 201204889.383.40$163
Sep 201201094.672.92$29
Aug 201203492.662.91$99
Jul 2012013985.133.02$420
Jun 2012013079.822.52$327
May 2012015191.612.49$376
Apr 20120127101.652.00$254
Mar 20120166105.052.22$369
Feb 20120225101.102.57$578
Jan 2012021698.092.73$591
Dec 2011031096.873.24$1,004
Nov 2011121995.723.31$821
Oct 2011037484.983.65$1,365
Sep 2011021383.623.99$849
Aug 2011030783.404.15$1,274
Jul 2011034994.144.52$1,577
Jun 2011027292.904.64$1,262
May 2011025698.134.40$1,128
Apr 20110337105.964.33$1,460
Mar 2011234196.364.06$1,576
Feb 2011013085.644.18$543
Jan 2011014186.504.59$647
Dec 2010119185.734.35$916
Nov 2010016780.843.80$634
Oct 201004478.103.51$154
Sep 201001972.633.98$76
Aug 2010021373.684.42$941
Jul 2010024872.554.74$1,175
Jun 2010231470.364.91$1,683
May 2010132671.124.24$1,452
Apr 2010130181.694.12$1,323
Mar 2010131478.394.39$1,456
Feb 2010131673.585.44$1,793
Jan 2010034774.365.96$2,070
Dec 2009134771.445.48$1,974
Nov 2009137374.593.75$1,474
Oct 2009038172.544.11$1,566
Sep 2009038365.543.06$1,174
Aug 2009037967.423.22$1,220
Jul 2009038861.133.46$1,344
Jun 2009038666.163.90$1,503
May 2009135054.743.93$1,429
Apr 2009137946.773.59$1,406
Mar 2009143142.144.06$1,792
Feb 2009143732.814.63$2,057
Jan 2009027535.865.37$1,477
Dec 2008138737.105.98$2,350
Nov 2008144155.496.86$3,081
Oct 2008149975.246.92$3,529
Sep 20080240101.767.88$1,891
Aug 20081459114.228.48$4,008
Jul 20080314131.0811.39$3,576
Jun 20081447131.3313.03$5,957
May 20080317123.1711.57$3,669
Apr 20081440110.3110.45$4,710
Mar 20081427101.909.66$4,228
Feb 2008138292.538.77$3,443
Jan 2008138090.388.21$3,209
Dec 2007137588.337.30$2,827
Nov 2007242491.677.29$3,275
Oct 2007252982.856.92$3,827
Sep 2007142675.846.24$2,736
Aug 2007149169.066.39$3,206
Jul 2007143570.906.39$2,850
Jun 2007148862.007.55$3,746
May 2007259058.747.85$4,747
Apr 2007256859.617.81$4,553
Mar 2007362556.927.30$4,734
Feb 2007387255.108.22$7,330
Jan 2007384650.306.73$5,842
Dec 2006253256.656.92$3,794
Nov 2006153654.207.62$4,137
Oct 2006159754.906.01$3,645
Sep 2006157860.085.04$2,972
Aug 200601,01168.717.34$7,421
Jul 2006189269.376.34$5,727
Jun 2006123266.286.38$1,547
May 2006062466.016.42$4,009
Apr 2006059564.397.36$4,379
Mar 2006251356.707.08$3,747
Feb 2006156857.597.75$4,460
Jan 2006162560.598.93$5,644
Dec 2005150654.9413.42$6,843
Nov 2005063554.6910.59$6,724
Oct 2005252558.3413.80$7,359
Sep 2005068961.4512.08$8,322
Aug 2005075061.519.80$7,348
Jul 2005061455.697.84$4,816
Jun 2005051852.337.38$3,823
May 2005060945.226.65$4,051
Apr 2005094749.207.36$6,970
Mar 200501,08550.377.15$7,763
Feb 2005099245.226.31$6,261
Jan 200501,09843.166.32$6,942
Dec 2004475539.866.75$5,257
Nov 2004067745.286.33$4,286
Oct 2004074949.706.52$4,880
Sep 200401,04843.245.28$5,538
Aug 200401,19942.375.55$6,655
Jul 200401,39638.286.08$8,494
Jun 200401,57836.106.43$10,151
May 200401,37537.486.49$8,930
Apr 200441,32534.475.86$7,900
Mar 200402,18834.365.53$12,100
Feb 200402,28232.455.51$12,573
Jan 200441,62432.036.30$10,359
Dec 200302,07430.266.30$13,070
Nov 200341,98828.804.60$9,250
Oct 200301,50728.174.76$7,173
Sep 200301,64526.314.75$7,813
Aug 200302,14829.765.13$11,019
Jul 200302,23129.415.17$11,536
Jun 200302,08228.565.98$12,457
May 200343,72426.595.97$22,349
Apr 200303,15626.675.41$17,065
Mar 200307,53131.146.10$45,909
Feb 200351,55933.487.93$12,524
Jan 200371,41730.315.58$8,122
Dec 200201,61126.914.85$7,819
Nov 200281,91124.664.14$8,103
Oct 200203,19926.464.23$13,529
Sep 200203,05127.443.64$11,091
Aug 200283,45025.963.16$11,124
Jul 200204,68024.583.06$14,329
Jun 200205,08023.733.34$16,958

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Dec 2025 — as filed, then multipliedworked
Condensate             1 bbl  × $ 56.66 =        $57
Gas                    0 Mcf  × $  4.41 =         $0

────────────────────────────────────────────────────
Month total                                      $57

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/192436 is the state's own key, not one this site invented.