Value, all time
$1.2 M
Jun 2006 – May 2026
Value, last 12 filed months
$523
at the published price for each month
Months reported
240
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6,629 leases and 6,629 wells, and the rule below applies to all of them.

Discovered
1967-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,000 ft
minimum
From a lease line
500 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2003-06-24.

The Commission's schedule remark for this field reads: FIELD PER ORDER 7C-0234582 6/2403

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112006-12-07171341
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition19 bbl$1,763
GasProduction255,733 Mcf$1,213,388
Total$1,215,152

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.3569, -100.6992. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.35689, -100.69917 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
7,554 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,554 ft.

Completions filed
Jun 2006
1 of 1 wells

1 well

42-43537893147,554 ftJun 2006

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (240)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

240 months

May 2026013106.413.05$40
Apr 202601098.932.87$29
Mar 202601189.753.15$35
Feb 202601163.503.75$41
Jan 202601259.138.00$96
Dec 202501256.664.41$53
Nov 202501158.593.93$43
Oct 202501259.383.30$40
Sep 202501262.743.08$37
Aug 202501263.933.01$36
Jul 202501266.743.32$40
Jun 202501166.483.13$34
May 202501160.553.23$36
Apr 202501162.363.54$39
Mar 202501267.704.27$51
Feb 20250970.884.34$39
Jan 202501074.324.28$43
Dec 202401168.993.12$34
Nov 202401069.052.20$22
Oct 202401171.372.28$25
Sep 202401169.612.36$26
Aug 202401775.632.06$35
Jul 202401679.932.15$34
Jun 202401378.082.63$34
May 202401278.812.20$26
Apr 202401884.451.66$30
Mar 2024082480.301.55$1,273
Feb 202401,36176.091.78$2,428
Jan 2024017973.023.30$590
Dec 202301371.262.61$34
Nov 2023041677.892.81$1,168
Oct 2023087085.443.09$2,686
Sep 2023070789.042.74$1,934
Aug 202301,24480.522.67$3,325
Jul 20230974.852.64$24
Jun 202301768.962.26$38
May 2023021770.622.23$483
Apr 2023060578.122.24$1,354
Mar 2023054072.852.39$1,292
Feb 2023057575.112.47$1,418
Jan 2023062376.533.39$2,111
Dec 2022058876.415.73$3,369
Nov 2022046485.005.65$2,620
Oct 2022056687.185.86$3,319
Sep 2022052884.888.16$4,310
Aug 2022097094.529.13$8,853
Jul 20220828101.587.54$6,245
Jun 20220800115.097.98$6,382
May 20220824109.378.43$6,949
Apr 20220815104.226.84$5,573
Mar 20220865108.885.08$4,391
Feb 2022080791.054.86$3,921
Jan 202201,02181.844.54$4,633
Dec 2021061971.323.90$2,414
Nov 2021039077.435.24$2,042
Oct 2021063179.795.71$3,605
Sep 2021066469.865.35$3,553
Aug 2021063866.024.22$2,693
Jul 2021093270.783.98$3,711
Jun 202103369.493.38$112
May 2021046763.483.02$1,409
Apr 2021089760.362.76$2,474
Mar 2021094061.302.72$2,554
Feb 2021081057.805.55$4,494
Jan 2021089250.412.81$2,507
Dec 2020091444.642.68$2,445
Nov 2020088138.772.71$2,384
Oct 2020091736.972.48$2,273
Sep 2020092637.091.99$1,844
Aug 2020096939.982.39$2,311
Jul 2020096038.371.83$1,752
Jun 2020094534.901.69$1,597
May 202001,00416.921.81$1,822
Apr 202001,04814.751.80$1,891
Mar 2020063130.341.86$1,171
Feb 2020061449.881.98$1,216
Jan 2020076557.252.09$1,602
Dec 2019073059.012.30$1,682
Nov 2019081555.302.75$2,242
Oct 2019068353.472.42$1,652
Sep 2019067755.052.66$1,799
Aug 2019078053.112.30$1,797
Jul 2019067456.272.46$1,658
Jun 2019054052.782.49$1,345
May 2019079858.482.74$2,187
Apr 2019068762.632.75$1,890
Mar 2019084156.803.06$2,575
Feb 2019065850.852.79$1,837
Jan 2019083146.033.23$2,683
Dec 2018071446.594.19$2,988
Nov 2018084852.934.24$3,593
Oct 2018063661.443.40$2,161
Sep 2018094759.543.11$2,943
Aug 2018048259.403.07$1,478
Jul 2018063165.142.93$1,850
Jun 2018066160.183.08$2,034
May 2018067965.382.90$1,970
Apr 2018091963.842.90$2,666
Mar 2018098761.222.79$2,751
Feb 2018090061.782.77$2,490
Jan 2018090362.874.01$3,620
Dec 201701,00057.272.92$2,922
Nov 201701,00155.423.12$3,121
Oct 201701,04549.292.98$3,118
Sep 201701,01147.523.09$3,121
Aug 201701,05745.373.00$3,176
Jul 201701,14343.873.09$3,529
Jun 2017090042.493.09$2,779
May 2017057345.373.26$1,870
Apr 2017063647.933.21$2,043
Mar 2017082646.772.98$2,465
Feb 2017083150.452.95$2,454
Jan 2017095749.413.42$3,272
Dec 201601,01148.763.72$3,764
Nov 201601,01742.492.64$2,689
Oct 2016090446.193.09$2,794
Sep 2016097241.553.10$3,014
Aug 201601,06241.442.92$3,106
Jul 201601,05141.622.92$3,073
Jun 201601,04645.352.69$2,809
May 201601,09642.521.99$2,182
Apr 201601,07836.561.99$2,146
Mar 201601,12233.011.79$2,013
Feb 201601,24026.472.06$2,559
Jan 2016081827.352.36$1,934
Dec 2015076932.362.00$1,539
Nov 2015082138.792.17$1,779
Oct 2015092643.552.43$2,247
Sep 201501,03242.992.76$2,847
Aug 201501,10040.162.87$3,160
Jul 201501,12248.152.95$3,304
Jun 201501,11656.152.88$3,217
May 201501,15755.212.96$3,419
Apr 201501,10849.822.71$2,999
Mar 201521,16142.892.93$3,493
Feb 201501,04344.662.98$3,104
Jan 201501,15343.433.10$3,575
Dec 201401,11754.693.59$4,012
Nov 201401,10170.464.25$4,681
Oct 201401,17078.303.90$4,564
Sep 201401,19286.164.05$4,822
Aug 201401,09289.394.04$4,406
Jul 201401,20496.564.18$5,032
Jun 201401,18298.164.74$5,599
May 201401,15894.734.73$5,473
Apr 201401,25195.944.81$6,016
Mar 201401,07195.895.06$5,416
Feb 201401,11397.406.19$6,892
Jan 201401,24890.404.86$6,066
Dec 201301,22491.824.35$5,330
Nov 201301,16788.853.74$4,363
Oct 201301,29497.423.78$4,890
Sep 201301,262104.113.72$4,692
Aug 201301,346104.253.52$4,741
Jul 201301,337102.523.72$4,971
Jun 201301,34594.403.93$5,290
May 201301,47094.834.15$6,099
Apr 201301,20693.964.28$5,165
Mar 201301,28793.623.91$5,036
Feb 201301,11991.233.42$3,827
Jan 2013074791.603.42$2,555
Dec 201201,22186.773.42$4,176
Nov 201201,44686.953.62$5,242
Oct 201201,17989.383.40$4,008
Sep 201201,01994.672.92$2,974
Aug 201201,43392.662.91$4,167
Jul 201201,24585.133.02$3,761
Jun 2012098279.822.52$2,474
May 2012090091.612.49$2,239
Apr 20120971101.652.00$1,939
Mar 201201,391105.052.22$3,091
Feb 201201,360101.102.57$3,496
Jan 201221,56098.092.73$4,461
Dec 201101,10196.873.24$3,567
Nov 201101,02895.723.31$3,404
Oct 201101,13084.983.65$4,123
Sep 201101,60983.623.99$6,413
Aug 2011077983.404.15$3,232
Jul 201101,30394.144.52$5,886
Jun 201101,29192.904.64$5,990
May 201101,35498.134.40$5,964
Apr 201101,246105.964.33$5,399
Mar 201101,23596.364.06$5,011
Feb 201101,13185.644.18$4,728
Jan 201101,02186.504.59$4,685
Dec 201001,37185.734.35$5,961
Nov 201001,24780.843.80$4,733
Oct 201001,24078.103.51$4,351
Sep 201001,45972.633.98$5,806
Aug 201001,47873.684.42$6,532
Jul 201001,21772.554.74$5,764
Jun 201001,50470.364.91$7,385
May 201001,55371.124.24$6,577
Apr 201001,56281.694.12$6,440
Mar 201021,74578.394.39$7,815
Feb 201001,26673.585.44$6,890
Jan 201001,62874.365.96$9,710
Dec 200901,36771.445.48$7,496
Nov 200901,45374.593.75$5,451
Oct 200901,53272.544.11$6,297
Sep 200901,61565.543.06$4,950
Aug 200901,73967.423.22$5,597
Jul 200901,76761.133.46$6,122
Jun 200901,75266.163.90$6,824
May 200901,96154.743.93$7,698
Apr 200901,59746.773.59$5,729
Mar 200901,84742.144.06$7,497
Feb 200901,70032.814.63$7,876
Jan 200902,00735.865.37$10,780
Dec 200801,46937.105.98$8,780
Nov 200801,68555.496.86$11,560
Oct 200801,87375.246.92$12,965
Sep 200801,923101.767.88$15,148
Aug 200801,952114.228.48$16,559
Jul 200802,034131.0811.39$23,166
Jun 200802,005131.3313.03$26,130
May 200802,108123.1711.57$24,399
Apr 200802,083110.3110.45$21,777
Mar 2008132,134101.909.66$21,948
Feb 200802,02292.538.77$17,734
Jan 200802,19990.388.21$18,044
Dec 200702,26788.337.30$16,554
Nov 200702,24691.677.29$16,377
Oct 200702,37182.856.92$16,412
Sep 200702,34075.846.24$14,611
Aug 200702,46769.066.39$15,759
Jul 200702,51870.906.39$16,085
Jun 200702,49062.007.55$18,796
May 200702,60358.747.85$20,424
Apr 200702,54259.617.81$19,841
Mar 200702,73056.927.30$19,934
Feb 200702,47755.108.22$20,351
Jan 200702,67750.306.73$18,008
Dec 200602,74356.656.92$18,977
Nov 200602,73054.207.62$20,796
Oct 200602,85754.906.01$17,181
Sep 200602,67860.085.04$13,490
Aug 200602,79068.717.34$20,478
Jul 200602,18469.376.34$13,853
Jun 200601,29166.286.38$8,242

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                   13 Mcf  × $  3.05 =        $40

────────────────────────────────────────────────────
Month total                                      $40

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/222040 is the state's own key, not one this site invented.