Operated by ZARVONA ENERGY LLC (P-5 950523) in the OZONA, NE. (CANYON 7520) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 224823District 7CField 679985002 tax incentive programmesCondensateGasSaveExport
Value, all time
$473 k
Oct 2006 – May 2026
Value, last 12 filed months
$602
at the published price for each month
Months reported
236
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 592 leases and 641 wells, and the rule below applies to all of them.

Discovered
1966-01-17
as the register files it
Field class
Oil and gas
the register's own label
Between wells
660 ft
minimum
From a lease line
330 ft
minimum

A drilling unit in this field needs at least 20 acres. The field rule took effect on 2013-10-22.

The Commission's schedule remark for this field reads: PER DOCKET 01-0299858, THIS FIELD HAS BEEN DESIGNATED AS A UFT

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112007-03-22172566
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition382 bbl$30,289
GasProduction76,116 Mcf$442,578
Total$472,867

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.7628, -100.9937. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.76279, -100.99367 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
8,017 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 8,017 ft.

Completions filed
Oct 2006
1 of 1 wells

1 well

42-105401229038,017 ftOct 2006

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (236)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

236 months

May 202605106.413.05$15
Apr 202601298.932.87$34
Mar 20260089.753.15$0
Feb 202601363.503.75$49
Jan 202606359.138.00$504
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 2025016674.324.28$710
Dec 2024016668.993.12$518
Nov 2024010869.052.20$237
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240175.632.06$2
Jul 20240179.932.15$2
Jun 20240078.082.63$0
May 20240478.812.20$9
Apr 202401484.451.66$23
Mar 202403780.301.55$57
Feb 202401476.091.78$25
Jan 2024011973.023.30$392
Dec 202302571.262.61$65
Nov 20230277.892.81$6
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230575.112.47$12
Jan 20230176.533.39$3
Dec 20220176.415.73$6
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 202208384.888.16$678
Aug 20220194.529.13$9
Jul 2022010101.587.54$75
Jun 202201115.097.98$8
May 202202109.378.43$17
Apr 2022027104.226.84$185
Mar 20220165108.885.08$838
Feb 2022037891.054.86$1,837
Jan 2022035181.844.54$1,593
Dec 202109271.323.90$359
Nov 202104377.435.24$225
Oct 202101579.795.71$86
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 202103563.483.02$106
Apr 202103060.362.76$83
Mar 202105861.302.72$158
Feb 2021021457.805.55$1,187
Jan 2021022250.412.81$624
Dec 2020014644.642.68$391
Nov 202002638.772.71$70
Oct 202004336.972.48$107
Sep 202004137.091.99$82
Aug 202003039.982.39$72
Jul 202003538.371.83$64
Jun 202004334.901.69$73
May 202005616.921.81$102
Apr 2020020714.751.80$374
Mar 2020028230.341.86$523
Feb 2020063249.881.98$1,252
Jan 2020057857.252.09$1,211
Dec 2019055059.012.30$1,267
Nov 2019044655.302.75$1,227
Oct 2019028553.472.42$689
Sep 201905455.052.66$143
Aug 201906453.112.30$147
Jul 201905056.272.46$123
Jun 201905052.782.49$125
May 201905458.482.74$148
Apr 201905562.632.75$151
Mar 201906056.803.06$184
Feb 201905550.852.79$154
Jan 2019011646.033.23$374
Dec 2018045246.594.19$1,892
Nov 2018029652.934.24$1,254
Oct 201809361.443.40$316
Sep 201807559.543.11$233
Aug 201838159.403.07$427
Jul 201807865.142.93$229
Jun 201807660.183.08$234
May 201808465.382.90$244
Apr 201808463.842.90$244
Mar 201808761.222.79$242
Feb 201808161.782.77$224
Jan 201809362.874.01$373
Dec 201709257.272.92$269
Nov 201708655.423.12$268
Oct 201709249.292.98$275
Sep 201709547.523.09$293
Aug 2017011745.373.00$352
Jul 2017011443.873.09$352
Jun 2017012242.493.09$377
May 2017012545.373.26$408
Apr 2017013247.933.21$424
Mar 2017014346.772.98$427
Feb 2017012350.452.95$363
Jan 2017015349.413.42$523
Dec 2016015548.763.72$577
Nov 2016014342.492.64$378
Oct 2016016046.193.09$494
Sep 2016415441.553.10$644
Aug 2016016141.442.92$471
Jul 2016016541.622.92$483
Jun 2016015745.352.69$422
May 2016016542.521.99$329
Apr 2016116536.561.99$365
Mar 2016016933.011.79$303
Feb 2016015726.472.06$324
Jan 2016017227.352.36$407
Dec 2015017432.362.00$348
Nov 2015016838.792.17$364
Oct 2015017143.552.43$415
Sep 2015017242.992.76$474
Aug 2015016740.162.87$480
Jul 2015017248.152.95$507
Jun 2015019656.152.88$565
May 2015015255.212.96$449
Apr 2015016349.822.71$441
Mar 2015018442.892.93$540
Feb 2015016744.662.98$497
Jan 2015018143.433.10$561
Dec 2014017754.693.59$636
Nov 2014017170.464.25$727
Oct 2014016978.303.90$659
Sep 2014017086.164.05$688
Aug 2014020489.394.04$823
Jul 2014019696.564.18$819
Jun 2014020198.164.74$952
May 2014018694.734.73$879
Apr 2014020795.944.81$995
Mar 2014020195.895.06$1,016
Feb 2014019997.406.19$1,232
Jan 2014021690.404.86$1,050
Dec 2013018191.824.35$788
Nov 2013021688.853.74$807
Oct 2013021297.423.78$801
Sep 20130223104.113.72$829
Aug 20130229104.253.52$807
Jul 20130236102.523.72$877
Jun 2013021094.403.93$826
May 2013022794.834.15$942
Apr 2013322093.964.28$1,224
Mar 20134114893.623.91$4,418
Feb 2013018691.233.42$636
Jan 2013021691.603.42$739
Dec 2012022286.773.42$759
Nov 2012024286.953.62$877
Oct 2012025089.383.40$850
Sep 2012024894.672.92$724
Aug 2012026692.662.91$774
Jul 2012026385.133.02$794
Jun 2012026379.822.52$663
May 2012026891.612.49$667
Apr 20120264101.652.00$527
Mar 20120273105.052.22$607
Feb 20120266101.102.57$684
Jan 2012028798.092.73$785
Dec 2011028396.873.24$917
Nov 2011028595.723.31$944
Oct 2011030084.983.65$1,095
Sep 2011029483.623.99$1,172
Aug 2011029883.404.15$1,237
Jul 2011032094.144.52$1,446
Jun 2011030992.904.64$1,434
May 2011033198.134.40$1,458
Apr 20110283105.964.33$1,226
Mar 2011034396.364.06$1,392
Feb 2011030485.644.18$1,271
Jan 2011035686.504.59$1,634
Dec 2010034785.734.35$1,509
Nov 2010136180.843.80$1,451
Oct 2010037878.103.51$1,326
Sep 20102137872.633.98$3,029
Aug 2010041173.684.42$1,816
Jul 2010037172.554.74$1,757
Jun 2010040070.364.91$1,964
May 2010039871.124.24$1,686
Apr 2010040281.694.12$1,657
Mar 2010045378.394.39$1,988
Feb 2010042473.585.44$2,308
Jan 2010046174.365.96$2,749
Dec 2009048571.445.48$2,660
Nov 2009049674.593.75$1,861
Oct 2009052572.544.11$2,158
Sep 2009052365.543.06$1,603
Aug 2009056867.423.22$1,828
Jul 20093754561.133.46$4,150
Jun 2009054066.163.90$2,103
May 2009060754.743.93$2,383
Apr 2009047846.773.59$1,715
Mar 2009055842.144.06$2,265
Feb 2009058132.814.63$2,692
Jan 2009064635.865.37$3,470
Dec 2008067637.105.98$4,041
Nov 2008076255.496.86$5,228
Oct 2008095775.246.92$6,624
Sep 200898672101.767.88$15,266
Aug 20080830114.228.48$7,041
Jul 20080964131.0811.39$10,979
Jun 20080967131.3313.03$12,603
May 200801,045123.1711.57$12,095
Apr 200801,045110.3110.45$10,925
Mar 200801,122101.909.66$10,843
Feb 200801,16592.538.77$10,218
Jan 200801,31290.388.21$10,766
Dec 200701,24088.337.30$9,054
Nov 200701,32091.677.29$9,625
Oct 200701,48082.856.92$10,245
Sep 200701,50375.846.24$9,385
Aug 20071731,63669.066.39$22,398
Jul 200701,70770.906.39$10,904
Jun 200701,66762.007.55$12,583
May 200701,84758.747.85$14,492
Apr 200701,80059.617.81$14,049
Mar 200702,03256.927.30$14,838
Feb 200702,16955.108.22$17,821
Jan 200702,50650.306.73$16,857
Dec 200602,97956.656.92$20,610
Nov 200603,80854.207.62$29,007
Oct 2006054454.906.01$3,272

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                    5 Mcf  × $  3.05 =        $15

────────────────────────────────────────────────────
Month total                                      $15

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/224823 is the state's own key, not one this site invented.