WARD, JOHN A.

Operated by UPP OPERATING, LLC (P-5 875310) in the SAWYER (CANYON) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 228339District 7CField 812673332 tax incentive programmesCondensateGasSaveExport
Value, all time
$859 k
Oct 2006 – May 2026
Value, last 12 filed months
$495
at the published price for each month
Months reported
236
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6,629 leases and 6,629 wells, and the rule below applies to all of them.

Discovered
1967-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,000 ft
minimum
From a lease line
500 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2003-06-24.

The Commission's schedule remark for this field reads: FIELD PER ORDER 7C-0234582 6/2403

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112007-08-14175325
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition503 bbl$38,995
GasProduction142,029 Mcf$819,830
Total$858,825

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.5332, -100.7167. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.53321, -100.71665 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
7,873 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 7,873 ft.

Completions filed
Oct 2006
1 of 1 wells

1 well

42-4353808387,873 ftOct 2006

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (236)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

236 months

May 202605106.413.05$15
Apr 20260598.932.87$14
Mar 20260589.753.15$16
Feb 20260263.503.75$8
Jan 20260659.138.00$48
Dec 202501356.664.41$57
Nov 202501858.593.93$71
Oct 202501859.383.30$59
Sep 202501862.743.08$55
Aug 202501363.933.01$39
Jul 202501666.743.32$53
Jun 202501966.483.13$59
May 202501860.553.23$58
Apr 202501762.363.54$60
Mar 202501167.704.27$47
Feb 202501070.884.34$43
Jan 202501574.324.28$64
Dec 202411568.993.12$116
Nov 202401869.052.20$40
Oct 202402271.372.28$50
Sep 202402369.612.36$54
Aug 202402275.632.06$45
Jul 202402479.932.15$52
Jun 202403178.082.63$82
May 202403578.812.20$77
Apr 202412484.451.66$124
Mar 202402180.301.55$32
Feb 202401576.091.78$27
Jan 202401673.023.30$53
Dec 202322171.262.61$197
Nov 202301977.892.81$53
Oct 202302085.443.09$62
Sep 202301989.042.74$52
Aug 202302180.522.67$56
Jul 202301874.852.64$48
Jun 202351668.962.26$381
May 202301470.622.23$31
Apr 20230978.122.24$20
Mar 20230772.852.39$17
Feb 20230875.112.47$20
Jan 202318876.533.39$1,405
Dec 202201576.415.73$86
Nov 2022322085.005.65$2,833
Oct 202202187.185.86$123
Sep 202203284.888.16$261
Aug 202203194.529.13$283
Jul 2022029101.587.54$219
Jun 2022040115.097.98$319
May 20229735109.378.43$10,904
Apr 2022036104.226.84$246
Mar 2022041108.885.08$208
Feb 202203191.054.86$151
Jan 202203981.844.54$177
Dec 202104471.323.90$172
Nov 2021723477.435.24$5,753
Oct 202103679.795.71$206
Sep 202102669.865.35$139
Aug 202103266.024.22$135
Jul 202104370.783.98$171
Jun 2021843669.493.38$5,959
May 202102063.483.02$60
Apr 202101660.362.76$44
Mar 202101561.302.72$41
Feb 202101957.805.55$105
Jan 202102450.412.81$67
Dec 202001144.642.68$29
Nov 20200838.772.71$22
Oct 20200236.972.48$5
Sep 20200137.091.99$2
Aug 20200139.982.39$2
Jul 20200038.371.83$0
Jun 20200134.901.69$2
May 20200316.921.81$5
Apr 202053214.751.80$785
Mar 20201230.341.86$34
Feb 202001449.881.98$28
Jan 202003357.252.09$69
Dec 201903859.012.30$88
Nov 201904155.302.75$113
Oct 201904253.472.42$102
Sep 201913655.052.66$151
Aug 201904653.112.30$106
Jul 201906356.272.46$155
Jun 20190052.782.49$0
May 201902158.482.74$58
Apr 201902862.632.75$77
Mar 20190756.803.06$21
Feb 20190250.852.79$6
Jan 20190346.033.23$10
Dec 20180246.594.19$8
Nov 20180652.934.24$25
Oct 20180361.443.40$10
Sep 20180059.543.11$0
Aug 20180159.403.07$3
Jul 201811165.142.93$97
Jun 201808060.183.08$246
May 201808065.382.90$232
Apr 201807263.842.90$209
Mar 201807361.222.79$203
Feb 201807561.782.77$207
Jan 201829062.874.01$487
Dec 201709357.272.92$272
Nov 201709655.423.12$299
Oct 201708249.292.98$245
Sep 201708047.523.09$247
Aug 201708945.373.00$267
Jul 201708843.873.09$272
Jun 201708642.493.09$266
May 201719045.373.26$339
Apr 201708047.933.21$257
Mar 201709146.772.98$272
Feb 201708150.452.95$239
Jan 201708749.413.42$297
Dec 201609248.763.72$343
Nov 2016010142.492.64$267
Oct 2016210446.193.09$414
Sep 2016010341.553.10$319
Aug 2016010441.442.92$304
Jul 2016033641.622.92$983
Jun 201609945.352.69$266
May 2016210442.521.99$292
Apr 2016010036.561.99$199
Mar 2016010233.011.79$183
Feb 2016010126.472.06$208
Jan 2016011727.352.36$277
Dec 2015012332.362.00$246
Nov 2015112438.792.17$308
Oct 2015013943.552.43$337
Sep 2015014742.992.76$405
Aug 2015019240.162.87$552
Jul 2015017148.152.95$504
Jun 2015016256.152.88$467
May 2015016655.212.96$491
Apr 2015016749.822.71$452
Mar 2015020042.892.93$587
Feb 2015026444.662.98$786
Jan 2015044943.433.10$1,392
Dec 2014047354.693.59$1,699
Nov 2014047770.464.25$2,028
Oct 2014052178.303.90$2,032
Sep 2014051986.164.05$2,100
Aug 2014055489.394.04$2,235
Jul 2014056996.564.18$2,378
Jun 2014057198.164.74$2,705
May 2014062294.734.73$2,940
Apr 2014063595.944.81$3,054
Mar 2014073995.895.06$3,737
Feb 20140497.406.19$25
Jan 201401190.404.86$53
Dec 2013059591.824.35$2,591
Nov 2013068988.853.74$2,576
Oct 2013052597.423.78$1,984
Sep 20130523104.113.72$1,944
Aug 20130543104.253.52$1,913
Jul 20130542102.523.72$2,015
Jun 2013056794.403.93$2,230
May 2013061594.834.15$2,552
Apr 2013061793.964.28$2,642
Mar 2013065893.623.91$2,575
Feb 2013062091.233.42$2,120
Jan 2013070891.603.42$2,421
Dec 2012071986.773.42$2,459
Nov 2012069986.953.62$2,534
Oct 2012076689.383.40$2,604
Sep 2012080094.672.92$2,335
Aug 2012088992.662.91$2,585
Jul 2012099585.133.02$3,006
Jun 201221,01679.822.52$2,719
May 201201,05991.612.49$2,635
Apr 20120983101.652.00$1,963
Mar 201201,034105.052.22$2,298
Feb 201211967101.102.57$3,598
Jan 2012092998.092.73$2,540
Dec 2011092796.873.24$3,003
Nov 2011899795.723.31$4,067
Oct 201141,05084.983.65$4,171
Sep 201151,07783.623.99$4,711
Aug 201101,16383.404.15$4,826
Jul 201151,19194.144.52$5,851
Jun 201181,16892.904.64$6,163
May 201101,05998.134.40$4,665
Apr 201181,163105.964.33$5,887
Mar 2011111,24596.364.06$6,111
Feb 2011111,15685.644.18$5,774
Jan 2011111,19486.504.59$6,431
Dec 201001,04685.734.35$4,548
Nov 2010097080.843.80$3,681
Oct 201031,35378.103.51$4,982
Sep 201001,18972.633.98$4,732
Aug 201001,34873.684.42$5,957
Jul 201001,23372.554.74$5,840
Jun 201061,34570.364.91$7,027
May 201061,34771.124.24$6,132
Apr 201071,35581.694.12$6,158
Mar 201001,42978.394.39$6,271
Feb 201001,33373.585.44$7,255
Jan 201001,55974.365.96$9,298
Dec 200901,68971.445.48$9,262
Nov 200902,16574.593.75$8,122
Oct 20090072.544.11$0
Sep 20090065.543.06$0
Aug 200901,36867.423.22$4,403
Jul 200901,43361.133.46$4,965
Jun 200901,42166.163.90$5,535
May 200901,52654.743.93$5,991
Apr 200901,37646.773.59$4,936
Mar 200901,46542.144.06$5,946
Feb 200901,31932.814.63$6,111
Jan 200901,49135.865.37$8,008
Dec 200801,59737.105.98$9,545
Nov 200801,58255.496.86$10,853
Oct 200801,65375.246.92$11,442
Sep 200801,642101.767.88$12,934
Aug 200801,727114.228.48$14,650
Jul 200801,773131.0811.39$20,193
Jun 200801,734131.3313.03$22,599
May 200801,872123.1711.57$21,667
Apr 200801,913110.3110.45$20,000
Mar 200802,123101.909.66$20,517
Feb 200801,87992.538.77$16,480
Jan 200801,52990.388.21$12,547
Dec 200701,84188.337.30$13,443
Nov 200702,02291.677.29$14,744
Oct 200702,11482.856.92$14,633
Sep 200702,13975.846.24$13,356
Aug 2007212,21369.066.39$15,587
Jul 200702,26370.906.39$14,456
Jun 200702,13562.007.55$16,116
May 200703,44458.747.85$27,023
Apr 200703,64759.617.81$28,466
Mar 200704,29756.927.30$31,377
Feb 200703,78455.108.22$31,089
Jan 200704,64650.306.73$31,253
Dec 200605,57656.656.92$38,577
Nov 200605,71354.207.62$43,519
Oct 2006019054.906.01$1,143

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                    5 Mcf  × $  3.05 =        $15

────────────────────────────────────────────────────
Month total                                      $15

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/228339 is the state's own key, not one this site invented.