Operated by UPP OPERATING, LLC (P-5 875310) in the SAWYER (CANYON) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 235343District 7CField 812673332 tax incentive programmesCondensateGasSaveExport
Value, all time
$764 k
May 2007 – May 2026
Value, last 12 filed months
$0
at the published price for each month
Months reported
229
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6,629 leases and 6,629 wells, and the rule below applies to all of them.

Discovered
1967-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,000 ft
minimum
From a lease line
500 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2003-06-24.

The Commission's schedule remark for this field reads: FIELD PER ORDER 7C-0234582 6/2403

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112008-06-23179201
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition378 bbl$30,124
GasProduction145,331 Mcf$734,237
Total$764,362

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.4195, -100.7139. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.41946, -100.71393 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
6,975 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 6,975 ft.

Completions filed
May 2007
1 of 1 wells

1 well

42-43538465146,975 ftMay 2007

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (229)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

229 months

May 202600106.413.05$0
Apr 20260098.932.87$0
Mar 20260089.753.15$0
Feb 20260063.503.75$0
Jan 20260059.138.00$0
Dec 20250056.664.41$0
Nov 20250058.593.93$0
Oct 20250059.383.30$0
Sep 20250062.743.08$0
Aug 20250063.933.01$0
Jul 20250066.743.32$0
Jun 20250066.483.13$0
May 20250060.553.23$0
Apr 20250062.363.54$0
Mar 20250067.704.27$0
Feb 20250070.884.34$0
Jan 20250074.324.28$0
Dec 20240068.993.12$0
Nov 20240069.052.20$0
Oct 20240071.372.28$0
Sep 20240069.612.36$0
Aug 20240075.632.06$0
Jul 20240079.932.15$0
Jun 20240078.082.63$0
May 20240078.812.20$0
Apr 20240084.451.66$0
Mar 20240080.301.55$0
Feb 20240076.091.78$0
Jan 20240073.023.30$0
Dec 20230071.262.61$0
Nov 20230077.892.81$0
Oct 20230085.443.09$0
Sep 20230089.042.74$0
Aug 20230080.522.67$0
Jul 20230074.852.64$0
Jun 20230068.962.26$0
May 20230070.622.23$0
Apr 20230078.122.24$0
Mar 20230072.852.39$0
Feb 20230075.112.47$0
Jan 20230076.533.39$0
Dec 20220076.415.73$0
Nov 20220085.005.65$0
Oct 20220087.185.86$0
Sep 20220084.888.16$0
Aug 20220094.529.13$0
Jul 202200101.587.54$0
Jun 202200115.097.98$0
May 202200109.378.43$0
Apr 202200104.226.84$0
Mar 202200108.885.08$0
Feb 20220091.054.86$0
Jan 20220081.844.54$0
Dec 20210071.323.90$0
Nov 20210077.435.24$0
Oct 20210079.795.71$0
Sep 20210069.865.35$0
Aug 20210066.024.22$0
Jul 20210070.783.98$0
Jun 20210069.493.38$0
May 20210063.483.02$0
Apr 20210060.362.76$0
Mar 20210061.302.72$0
Feb 20210057.805.55$0
Jan 20210050.412.81$0
Dec 20200044.642.68$0
Nov 20200038.772.71$0
Oct 20200036.972.48$0
Sep 20200037.091.99$0
Aug 20200039.982.39$0
Jul 20200038.371.83$0
Jun 20200034.901.69$0
May 20200016.921.81$0
Apr 20200014.751.80$0
Mar 20200030.341.86$0
Feb 20200049.881.98$0
Jan 20200057.252.09$0
Dec 20190059.012.30$0
Nov 20190055.302.75$0
Oct 20190053.472.42$0
Sep 20190055.052.66$0
Aug 201908653.112.30$198
Jul 2019049456.272.46$1,215
Jun 2019048652.782.49$1,211
May 2019049158.482.74$1,346
Apr 2019071462.632.75$1,964
Mar 201901,18656.803.06$3,632
Feb 201901,29150.852.79$3,605
Jan 201901,13646.033.23$3,667
Dec 2018052546.594.19$2,197
Nov 2018045552.934.24$1,928
Oct 2018054061.443.40$1,835
Sep 2018055959.543.11$1,737
Aug 2018058659.403.07$1,797
Jul 2018056065.142.93$1,642
Jun 2018053960.183.08$1,658
May 2018054265.382.90$1,572
Apr 2018051863.842.90$1,503
Mar 2018053461.222.79$1,488
Feb 2018051861.782.77$1,433
Jan 2018057662.874.01$2,309
Dec 2017462357.272.92$2,049
Nov 2017063455.423.12$1,977
Oct 2017357749.292.98$1,869
Sep 2017042547.523.09$1,312
Aug 201703345.373.00$99
Jul 2017341543.873.09$1,413
Jun 2017043442.493.09$1,340
May 2017343345.373.26$1,549
Apr 2017042847.933.21$1,375
Mar 2017043646.772.98$1,301
Feb 2017037750.452.95$1,113
Jan 2017043249.413.42$1,477
Dec 2016143548.763.72$1,668
Nov 2016018042.492.64$476
Oct 201629046.193.09$371
Sep 2016453141.553.10$1,813
Aug 2016062041.442.92$1,813
Jul 2016062941.622.92$1,839
Jun 2016461545.352.69$1,833
May 2016064742.521.99$1,288
Apr 2016063836.561.99$1,270
Mar 2016366433.011.79$1,290
Feb 2016058826.472.06$1,213
Jan 2016066327.352.36$1,568
Dec 2015067932.362.00$1,359
Nov 2015065938.792.17$1,428
Oct 2015467943.552.43$1,822
Sep 2015365342.992.76$1,930
Aug 2015014140.162.87$405
Jul 2015060048.152.95$1,767
Jun 2015462556.152.88$2,026
May 2015064955.212.96$1,918
Apr 2015062649.822.71$1,694
Mar 2015066442.892.93$1,949
Feb 2015057544.662.98$1,711
Jan 2015065443.433.10$2,028
Dec 2014464454.693.59$2,532
Nov 2014363970.464.25$2,928
Oct 2014062178.303.90$2,423
Sep 2014365286.164.05$2,896
Aug 2014368789.394.04$3,040
Jul 2014370896.564.18$3,249
Jun 2014066798.164.74$3,160
May 2014071194.734.73$3,361
Apr 2014071695.944.81$3,443
Mar 2014360095.895.06$3,322
Feb 2014064397.406.19$3,981
Jan 2014372090.404.86$3,771
Dec 2013367791.824.35$3,223
Nov 2013364788.853.74$2,685
Oct 2013366197.423.78$2,790
Sep 20133681104.113.72$2,844
Aug 20133686104.253.52$2,729
Jul 20133580102.523.72$2,464
Jun 2013068794.403.93$2,702
May 2013373894.834.15$3,347
Apr 2013071093.964.28$3,041
Mar 2013376893.623.91$3,286
Feb 2013371691.233.42$2,722
Jan 2013382491.603.42$3,093
Dec 2012373686.773.42$2,778
Nov 2012680786.953.62$3,447
Oct 2012385189.383.40$3,161
Sep 2012384994.672.92$2,762
Aug 2012582892.662.91$2,871
Jul 2012386585.133.02$2,868
Jun 2012378579.822.52$2,217
May 2012581991.612.49$2,496
Apr 20123839101.652.00$1,980
Mar 20120944105.052.22$2,098
Feb 201231,079101.102.57$3,077
Jan 201231,12298.092.73$3,362
Dec 2011495696.873.24$3,485
Nov 2011392895.723.31$3,360
Oct 2011395784.983.65$3,747
Sep 2011391883.623.99$3,910
Aug 2011397783.404.15$4,304
Jul 2011398794.144.52$4,741
Jun 2011385792.904.64$4,255
May 201131,00098.134.40$4,699
Apr 20115952105.964.33$4,655
Mar 201131,02596.364.06$4,448
Feb 2011387585.644.18$3,914
Jan 201131,02286.504.59$4,949
Dec 201061,05585.734.35$5,101
Nov 201031,04680.843.80$4,212
Oct 201031,12878.103.51$4,192
Sep 201051,06472.633.98$4,597
Aug 2010287373.684.42$4,005
Jul 2010288072.554.74$4,313
Jun 2010084570.364.91$4,149
May 201031,15971.124.24$5,122
Apr 201031,10281.694.12$4,788
Mar 201031,20378.394.39$5,515
Feb 201021,07673.585.44$6,003
Jan 201031,05874.365.96$6,533
Dec 200931,26571.445.48$7,151
Nov 200951,27274.593.75$5,145
Oct 200961,32372.544.11$5,873
Sep 200961,34365.543.06$4,509
Aug 200931,46967.423.22$4,930
Jul 200961,48661.133.46$5,515
Jun 200961,49466.163.90$6,216
May 200931,55754.743.93$6,277
Apr 200931,29946.773.59$4,800
Mar 200921,55742.144.06$6,404
Feb 200951,44532.814.63$6,859
Jan 200931,59835.865.37$8,690
Dec 200831,63537.105.98$9,884
Nov 200871,70355.496.86$12,072
Oct 200831,83875.246.92$12,948
Sep 200871,825101.767.88$15,088
Aug 200861,896114.228.48$16,769
Jul 200831,917131.0811.39$22,227
Jun 200831,855131.3313.03$24,570
May 200862,032123.1711.57$24,258
Apr 200832,221110.3110.45$23,551
Mar 200872,305101.909.66$22,989
Feb 200842,28892.538.77$20,437
Jan 200852,55190.388.21$21,385
Dec 200772,67088.337.30$20,115
Nov 2007132,73591.677.29$21,135
Oct 2007113,04782.856.92$22,003
Sep 2007102,99675.846.24$19,466
Aug 200752,89369.066.39$18,826
Jul 200792,93970.906.39$19,412
Jun 200783,40662.007.55$26,206
May 200731,53458.747.85$12,212

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

Aug 2019 — as filed, then multipliedworked
Condensate             0 bbl  × $ 53.11 =         $0
Gas                   86 Mcf  × $  2.30 =       $198

────────────────────────────────────────────────────
Month total                                     $198

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/235343 is the state's own key, not one this site invented.