MAYER RANCH 40

Operated by UPP OPERATING, LLC (P-5 875310) in the SAWYER (CANYON) field. Every figure below is a volume the Railroad Commission published, multiplied by a monthly price you can check.

Gas lease lease 257185District 7CField 812673332 tax incentive programmesCondensateGasSaveExport
Value, all time
$204 k
Jul 2010 – May 2026
Value, last 12 filed months
$2 k
at the published price for each month
Months reported
191
no gaps in the span
Streams
2
condensate, gas

The Railroad Commission's own record for the field this lease produces from, including the spacing rule that governs how close together its wells may be drilled.

These are facts about the field, not about this lease. The field holds 6,629 leases and 6,629 wells, and the rule below applies to all of them.

Discovered
1967-07-01
as the register files it
Field class
Gas
the register's own label
Between wells
1,000 ft
minimum
From a lease line
500 ft
minimum

A drilling unit in this field needs at least 40 acres. The field rule took effect on 2003-06-24.

The Commission's schedule remark for this field reads: FIELD PER ORDER 7C-0234582 6/2403

Severance-tax incentive filings

Applications the operator filed to have this lease's gas taxed at a reduced state rate. A filing is an application, and this page never calls one a reduction that was granted.

ProgrammeFilingsWith an approval dateDatedDocket
High Cost Gas112011-08-15203203
NGPA1none

This says nothing about a royalty. A severance tax is charged to the operator. Whether a reduced rate reaches a royalty owner depends on the wording of the lease instrument, which is a private contract this site does not hold.

What this lease produced, and what it was worth

Oil and condensate are valued on the volume the state records as disposed of; gas and casinghead gas on the volume produced. They are different columns of different files, and the difference is not cosmetic.

StreamBasisVolumeValue
CondensateDisposition148 bbl$11,349
GasProduction48,689 Mcf$192,936
Total$204,285

Wells on this lease (1)

Every wellbore the Railroad Commission records against this lease key, with the depth, the last completion and the plug date exactly as filed. A well with no plug date is not stated to be producing — the state files no such flag.

These wells centre on 30.6779, -100.9239. A lease has no coordinate of its own — that point is the mean of its wells, and they span 0.0 miles.

30.67790, -100.92385 · centre of the wells drawn, derived

What these wells add up to

Every figure below is counted over all of this lease's wells, not over the rows listed above. The Railroad Commission files two facts about a well's state — a plug date and a proration-schedule flag — and a well can carry both, so they are published as separate counts and never merged into a status.

On the schedule
0.0%
0 of 1 wells
With a plug date
0.0%
0 of 1 wells
Median depth
8,600 ft
1 wells filed one
Completion to plug
no well filed both dates

What the state filed about each well

On the RRC proration schedule
00.0%
A plug date is filed
00.0%
BothOn the schedule and plugged. Neither fact cancels the other.
00.0%
NeitherNo plug date, and not on the schedule.
1100.0%

A plug date is the date the Commission recorded the wellbore as sealed with cement and abandoned. It is the only end-of-life fact Texas files. There is no "active" flag on a well, so this page does not print one — a well with no plug date is not stated to be producing.

How deep they were drilled

The one well that filed a depth was drilled to 8,600 ft.

Completions filed
Jul 2010
1 of 1 wells

1 well

42-4353929578,600 ftJul 2010

The API number is the state's, prefixed 42 for Texas. A well is matched to this lease by the lease key the Commission files on the wellbore record, so a well that has moved between leases appears under each one it was filed against.

Every month this lease reported (191)

Volume × price = value, one row per cycle. The price columns are the same series published on the prices page — nothing here is modelled.

191 months

May 2026036106.413.05$110
Apr 202602898.932.87$80
Mar 202603089.753.15$94
Feb 202603263.503.75$120
Jan 202602759.138.00$216
Dec 202512856.664.41$180
Nov 202512758.593.93$165
Oct 202502759.383.30$89
Sep 202512862.743.08$149
Aug 202512863.933.01$148
Jul 202512866.743.32$160
Jun 202502866.483.13$88
May 202513660.553.23$177
Apr 202503162.363.54$110
Mar 202513267.704.27$204
Feb 202502970.884.34$126
Jan 202503374.324.28$141
Dec 202403268.993.12$100
Nov 202403269.052.20$70
Oct 202403271.372.28$73
Sep 202403169.612.36$73
Aug 202403275.632.06$66
Jul 202403279.932.15$69
Jun 202403178.082.63$82
May 202413278.812.20$149
Apr 202403284.451.66$53
Mar 202403480.301.55$53
Feb 202403276.091.78$57
Jan 202403373.023.30$109
Dec 202313471.262.61$160
Nov 202303577.892.81$98
Oct 202303185.443.09$96
Sep 202313289.042.74$177
Aug 202303480.522.67$91
Jul 202303474.852.64$90
Jun 202303468.962.26$77
May 202313570.622.23$149
Apr 202313578.122.24$156
Mar 202333672.852.39$305
Feb 202303275.112.47$79
Jan 202303776.533.39$125
Dec 202203776.415.73$212
Nov 202203785.005.65$209
Oct 202213787.185.86$304
Sep 202203584.888.16$286
Aug 202203794.529.13$338
Jul 2022136101.587.54$373
Jun 2022036115.097.98$287
May 2022054109.378.43$455
Apr 2022037104.226.84$253
Mar 2022039108.885.08$198
Feb 202203491.054.86$165
Jan 202204081.844.54$182
Dec 202104071.323.90$156
Nov 202104077.435.24$209
Oct 202104279.795.71$240
Sep 202103869.865.35$203
Aug 202104166.024.22$173
Jul 202104070.783.98$159
Jun 202104069.493.38$135
May 202104263.483.02$127
Apr 202104160.362.76$113
Mar 202104361.302.72$117
Feb 202103857.805.55$211
Jan 202104550.412.81$126
Dec 202004444.642.68$118
Nov 202004338.772.71$116
Oct 202004536.972.48$112
Sep 202004437.091.99$88
Aug 202004439.982.39$105
Jul 202004538.371.83$82
Jun 202004434.901.69$74
May 202008616.921.81$156
Apr 202005014.751.80$90
Mar 202005230.341.86$97
Feb 202005049.881.98$99
Jan 202005357.252.09$111
Dec 201905459.012.30$124
Nov 201905355.302.75$146
Oct 201905553.472.42$133
Sep 201905355.052.66$141
Aug 201905453.112.30$124
Jul 201905556.272.46$135
Jun 201905552.782.49$137
May 201905758.482.74$156
Apr 201905762.632.75$157
Mar 201905956.803.06$181
Feb 201905450.852.79$151
Jan 201906046.033.23$194
Dec 201806146.594.19$255
Nov 201805852.934.24$246
Oct 201806161.443.40$207
Sep 201805959.543.11$183
Aug 201806159.403.07$187
Jul 201806165.142.93$179
Jun 201806160.183.08$188
May 201806565.382.90$189
Apr 201806463.842.90$186
Mar 201806661.222.79$184
Feb 201816161.782.77$231
Jan 201816762.874.01$331
Dec 201716857.272.92$256
Nov 201706755.423.12$209
Oct 201716949.292.98$255
Sep 201706647.523.09$204
Aug 201706945.373.00$207
Jul 201706943.873.09$213
Jun 201706942.493.09$213
May 201707745.373.26$251
Apr 201707547.933.21$241
Mar 201707846.772.98$233
Feb 201717150.452.95$260
Jan 201717849.413.42$316
Dec 201608048.763.72$298
Nov 201617842.492.64$249
Oct 201608146.193.09$250
Sep 201608141.553.10$251
Aug 201618441.442.92$287
Jul 201608741.622.92$254
Jun 201608745.352.69$234
May 201617642.521.99$194
Apr 201619036.561.99$216
Mar 201619433.011.79$202
Feb 201609126.472.06$188
Jan 201619727.352.36$257
Dec 201519632.362.00$225
Nov 201519538.792.17$245
Oct 2015110043.552.43$286
Sep 2015114442.992.76$440
Aug 2015111640.162.87$373
Jul 2015111148.152.95$375
Jun 201509856.152.88$283
May 201508055.212.96$236
Apr 201509949.822.71$268
Mar 2015011042.892.93$323
Feb 201508644.662.98$256
Jan 201509343.433.10$288
Dec 2014020254.693.59$725
Nov 20140070.464.25$0
Oct 201405578.303.90$215
Sep 2014014386.164.05$579
Aug 2014010489.394.04$420
Jul 2014110196.564.18$519
Jun 2014012498.164.74$587
May 2014011894.734.73$558
Apr 201408595.944.81$409
Mar 2014014895.895.06$748
Feb 2014014097.406.19$867
Jan 2014019390.404.86$938
Dec 201309791.824.35$422
Nov 2013017488.853.74$650
Oct 2013015997.423.78$601
Sep 20130187104.113.72$695
Aug 2013086104.253.52$303
Jul 20132160102.523.72$800
Jun 2013015094.403.93$590
May 2013016994.834.15$701
Apr 2013017093.964.28$728
Mar 2013015593.623.91$606
Feb 2013012691.233.42$431
Jan 2013016291.603.42$554
Dec 2012018086.773.42$616
Nov 2012012486.953.62$450
Oct 2012018989.383.40$643
Sep 2012021294.672.92$619
Aug 2012020992.662.91$608
Jul 2012019885.133.02$598
Jun 2012024779.822.52$622
May 2012028191.612.49$699
Apr 20120280101.652.00$559
Mar 20120256105.052.22$569
Feb 20120286101.102.57$735
Jan 2012030698.092.73$837
Dec 2011029596.873.24$956
Nov 2011233795.723.31$1,307
Oct 2011236784.983.65$1,509
Sep 2011023383.623.99$929
Aug 2011029283.404.15$1,212
Jul 2011387394.144.52$4,226
Jun 201151,64092.904.64$8,074
May 201151,83698.134.40$8,578
Apr 201171,615105.964.33$7,740
Mar 201121,75396.364.06$7,305
Feb 201181,78585.644.18$8,146
Jan 201172,28486.504.59$11,086
Dec 201062,71985.734.35$12,336
Nov 201093,17380.843.80$12,770
Oct 201033,32378.103.51$11,894
Sep 2010173,90972.633.98$16,790
Aug 2010124,77373.684.42$21,978
Jul 2010224,13472.554.74$21,177

How to read this page

The arithmetic is one multiplication per stream per month. Here it is, worked, on a real row from the table above.

May 2026 — as filed, then multipliedworked
Condensate             0 bbl  × $106.41 =         $0
Gas                   36 Mcf  × $  3.05 =       $110

────────────────────────────────────────────────────
Month total                                     $110

The volumes are the state's, unchanged

Every barrel and every Mcf on this page is a number the Railroad Commission of Texas published in its monthly production query. Nothing is modelled, estimated or filled in.

The dollars are a multiplication, not a valuation

Volume × a published monthly price. It is not what the operator was paid: it takes no account of a contract, a differential, a transportation deduction, or the share any one owner holds.

Oil and gas are priced differently

Oil is a Texas realisation — the crude oil first purchase price. Gas is a benchmark, because no free Texas wellhead gas series exists at any date. The prices page publishes the difference rather than correcting it away.

A lease is not a well

The state reports oil on lease and gas on well, and this page is the lease grain. 7C/G/257185 is the state's own key, not one this site invented.